Works on Aktau seaport expansion to end by July.

Full range of work on Aktau seaport in the north direction will be completed by July 2015, Vice President of the Kazkahstan Temir Zholy JSC Roman Sklyar told the CCS press briefing on May 6.

According to him, under the project of expanding the Aktau sea port, the construction of three freight terminals with the capacity of 3 million tons of freight per year is going on in the north direction. As well as one more grain terminal with the capacity of 1.5 million tons of grain per year will be launched.

According to the KTZ, as a result of expanding there will be increase in capacity of the Aktau sea port from 18 to 21 million tons a year.

Moreover, according to the vice president of the Company, the construction of float complex is going on at the Kuryk port in the Caspian sea.

"We expect the construction of hydraulic structures, piers, administrative and auxiliary buildings, driveway railway from the Ersai station. The power of float complex will be 4 million 100 thousand tons of ferry cargo a year, " said R.Sklyar.

Also, according to the KTZ, on July 1 it is expected to complete the construction of the railway line Borzhakty Ersai with 14 km.

News Agency I...IUIypress - 2001-2015 Provided by SyndiGate Media Inc. ( Syndigate.info ).

COPYRIGHT 2015 SyndiGate Media Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2015 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:AKIpress News Agency
Date:May 6, 2015
Words:220
Previous Article:Tajikistan president's "son" arrested in Dushanbe.
Next Article:Kyrgyzstan plans to establish twin-region relations with Turkey's Kayseri.
Topics:

Terms of use | Privacy policy | Copyright © 2019 Farlex, Inc. | Feedback | For webmasters