Vermont asbestos mine deal is official; future of Eden site less clear.

Negotiations over Vermont Asbestos Group's operations on Belvidere Mountain are settled: Howard Manosh's company will have until 2023 to pay $50,000 toward cleaning up his company's 1,550-acre toxic waste site.

But the closed mine's fate is hardly sealed. The state is "open to suggestions" about what can be done there --from installing a solar array to letting in a developer who can reuse some of the 30 million tons of hazardous material currently sitting in piles, quarries and buildings across the 650-acre site.

A settlement between VAG and the Vermont Attorney General's Office, along with the U.S. Environmental Protection Agency, was signed Oct. 16 by Judge William Sessions III in U.S. District Court. No public comments on the proposed consent decree were received in the preceding month.

Assistant Attorney General Thea Schwartz said the state will continue to pursue the case. The defendant agreed to work with the state and EPA to recover as much money as possible from insurance policies. Any funds obtained will compensate for the governments' past and future efforts to contain the hazardous ore, mine tailings and waste rock.

The total long-term cost of remediation may range from $135 million to $208 million for 200 years of operation, maintenance and monitoring, according to state documents.

Vermont Asbestos Group was found to be financially unable to cover the remediation costs; the settlement obligates VAG to pay $50,000 over the next 10 years. During that time, VAG also will continue maintaining the temporary mitigation structures put in place by the EPA since 2007--environmental features such as water bars, diversion trenches and berms to minimize runoff.

A feasibility study for siting a solar array on the property was completed in April by the National Renewable Energy Laboratory. "The scale of the mine is such that many large, non-vegetated flat open areas containing removed and graded cap rock within the 1,550-acre site could potentially be used for utility -scale solar development," the report says.

At old mines in the western part of the country new technology is now being used to extract metals from previously unusable materials. Asbestos may be particularly valuable for its magnesium.

VAG representatives routinely visit the site to ensure erosion-control measures are holding up to the weather. Many hoped the mine would find a place in the federal government's Superfund program to clean up "uncontrolled hazardous waste sites," but local residents voted against the designation.

Other federal monies may be available for remediation. About 1,000 to 2,000 cubic yards of ore were removed last week with help from EPA

There's little to no chance that all the waste will ever be totally removed. The goal is to flatten the massive piles and cover them up. Some, that aren't too steep, were planted with a cover crop of legumes and clover about three years ago.

Schwartz said no other litigation regarding the site is pending at this time. An earlier settlement with the mine's prior owner, G-I Holdings, continues to be enforced. Part of that agreement includes perimeter air monitoring and site security. G-I also will fund future efforts to scan company documents left in the operation's offices.

Source: Hilary Niles, vtdigger.org

COPYRIGHT 2013 Jade Media Partners
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2013 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Hazardous Waste Superfund Alert
Date:Oct 24, 2013
Words:534
Previous Article:PA Township landfill is focus of nearly $500,000 federal lawsuit.
Next Article:EPA eyes New Jersey's pure earth recycling facility as possible superfund site.