United States-Centralized Remedial Action Schemes (CRAS) Project.

Project End : 2014

Project Location : United States

Description: The Centralized Remedial Action Schemes (CRAS) project will centralize control and operation of SCE s special protection systems on the SCE transmission grid. The CRAS will transition existing special protection systems from an Intelligent Electronic Device (IED) at substations to a redundant and highly secure centralized processing system. The CRAS will

accommodate complex special protection systems that would not be possible with individual IED systems.

Cost: Approximately $51 million (estimated direct costs in nominal dollars, excluding corporate overheads).

Status: The project is anticipated to be completed during the third quarter of 2014.

Investment Partners: None.

Benefits: The CRAS will 1) mitigate and permit existing and new generation projects to connect to the grid and to meet California%s RPS goal; 2) enhance the coordination and effectiveness of existing special protection technology; 3) enhance the ability to build new schemes to enable

a more efficient generator interconnection process; and 4) improve the efficiency of managing and maintaining existing and new special protection systems.

country :United States

2013 Al Bawaba (Albawaba.com)

Provided by Syndigate.info an Albawaba.com company
COPYRIGHT 2013 Al Bawaba (Middle East) Ltd.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2013 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Mena Report
Date:Mar 4, 2013
Words:186
Previous Article:United States-Tehachapi Wind Energy Storage Project (TSP).
Next Article:India : Setting up 500 Big Dairy Farms in Anand and Kheda.

Terms of use | Privacy policy | Copyright © 2019 Farlex, Inc. | Feedback | For webmasters