Traffic light work to begin.

WORK to install new traffic lights at five entry roads on the A19 and A66 will start next week.

The lights are being installed as part of a new scheme to support future development, improve traffic flows, and reduce congestion at the junctions.

The Highways Agency aims to better regulate traffic joining these roads. Work will begin on Monday November 15.

The system, known as ramp metering, will be ready to switch-on by the end of March 2011.

The ramp metering sites are: * A19/A1027 southbound entry slip road * A19/A139 southbound entry slip road * A19/A1046 southbound entry slip road * A19/A1130 northbound entry slip road * A66 Teesside Park eastbound entry slip road Work will take place during day time off peak hours from 10.30am to 3.30pm, and over night between 10pm and 5am.

During the work there will be a small number of full night time closures on the entry slip roads and A19 and A66.
COPYRIGHT 2010 MGN Ltd.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2010 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Evening Gazette (Middlesbrough, England)
Date:Nov 12, 2010
Words:160
Previous Article:When the chips are down... Customers support takeaway owner in planning wrangle.
Next Article:DEATHS.
Topics:

Terms of use | Privacy policy | Copyright © 2018 Farlex, Inc. | Feedback | For webmasters