Setting up of 90-MW Sorfjord vindpark wind farm in Nordkraft AS.

The particular portfolio includes the 90-MW Sorfjord projects that are fully-permitted and are expected to enter into service in2019, respectively.The sale of the assets is expected to be finalised in the first quarter of 2017.

Nordkraft has already some infrastructure in Srfjorden. The largest hydroelectric plant in northern Kraft Group, Srfjord I, located in the immediate vicinity of the wind farm. Smkraft Administration Srfjord II is located in the area wind park is planned.

Summer 2009: Prior notification delivered NVE

October 2011: The license application submitted to NVE

December 2012: NVE awarded Nordkraft Vind construction license for construction and operation of the plant. The decision was appealed to the Ministry of Petroleum and Energy.

November 2015: OED has given Nordkraft Wind concession Srfjord Vindkraftverk with associated grid connection.

Project completion date : 2019-12-31 12:00:00

Major organization : NORDKRAFT AS

Address : Teknologiveien 2B,

8517 Narvik

Country :Norway

Email : post@nordkraft.no

Url : http://www.nordkraft.no/

[c] 2016 Al Bawaba (Albawaba.com) Provided by SyndiGate Media Inc. ( Syndigate.info ).

COPYRIGHT 2016 SyndiGate Media Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2016 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Mena Report
Date:Nov 11, 2016
Words:181
Previous Article:nstadblheia Vindpark.
Next Article:Karamana-Kaliyikkavila stretch Reach II four-laning.
Topics:

Terms of use | Privacy policy | Copyright © 2019 Farlex, Inc. | Feedback | For webmasters