Name of client: Saudi Aramco -- Saudi Arabian Oil Company Estimated budget: $800 million Facility type: Gas processing Sector: Gas Status: EPC ITB Location: Tabuk Feed: Mustang Engineering

Background Saudi Aramco plans to develop a gas processing plant at the Midyan non-associated gas field. The plant will be built in Tabuk.

The aim of the project is to reduce the burning of crude oil for power generation in the northwest of the kingdom in the summer months.

Upon completion, the production capacity of the non-associated gas field is expected to reach 75 million cubic feet per day (cfd) of natural gas and 4,500 barrels per day (bpd) of condensates.

Project status Jan 2013: Companies have submitted their bids for the EPC contract. An award is expected in April 2013.

Project scope The scope of the project involves the development of non-associated onshore Midyan gas field to produce 75 million cubic feet per day (cfd) of gas and 4,500 barrels per day (bpd) of NGL condensate for a period of 20 years. The output will be transported by pipeline to a power plant in the coastal town of Duba that is 135 kilometres to the southwest of the field.

Project schedule Feasibility study Q2-2012 Feed Q2-2012 EPC ITB Q3-2012 EPC Q2-2013 Completion Q2-2015

Copyright 2012 www.tradearabia.com

Copyright 2013 Al Hilal Publishing & Marketing Group

Provided by Syndigate.info an Albawaba.com company
COPYRIGHT 2013 Al Bawaba (Middle East) Ltd.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2013 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Oil & Gas News
Date:May 20, 2013
Words:233
Previous Article:New input system for biogas.
Next Article:Dana Gas net profit up 17pc in Q1; revenue down.
Topics:

Terms of use | Privacy policy | Copyright © 2021 Farlex, Inc. | Feedback | For webmasters