Reliability, risk management, and contingency of construction processes and projects/Statybos procesu ir projektu patikimumas, rizikos ir atsitiktinumu valdymas.

1. Introduction

Risks that emerge from inability to keep deadlines and remain within the budget are important to all participants of an investment process. Recently, a vast number of researches and investigations were dedicated to this topic aiming to determine effective risk management measures.

In some cases, articles do not seem to consider the available research results. However, this could be explained by the complex nature of construction projects, which means that the focus of a research may depend on the type of a project, operational conditions, the particular phase of an investment project, the point of view (of the process subject), the manner of organisation, and etc.

Development of risk analysis methods reveals an interesting evolution of notions, methods and cases. This evolution can be traced back to the first results of the tripartite academic colloquia, which were comprised of academic centres of Vilnius (namely, VGTU, formerly known as VCEI), Leipzig (HTWK, formerly--THL) and Poznan (the University of Technology) since 1986. The meetings not only focused on such topics as selection, multicriteria optimisation and decision-making tools, but also discussed the issues of reliability of production and risk management in construction industry. Professor Oleg Kaplinski has significantly contributed to the development and application of the latter. The paper briefly describes achievements of these colloquia and presents the overview of work by Professor Kaplinski, the active member and the chair of the Polish delegation of the colloquia since 1989.

The colloquia were initiated by Professor Zavadskas, whose achievements have been described in a number of publications (e.g., Kaplinski 2009a, b). Held biennially, the colloquia have left behind a trail of studies and summaries such as Zavadskas and Kaklauskas (2001), Kaplinski et al. (2004), Kaklauskas et al. (2005), Peldschus et al. (2006), Zavadskas (2008), Peldschus (2009). As the result of the most recent colloquia (in 2009 and 2011), which stressed the issue of Operational Research in the context of sustainability, the EURO Working Group OR in Sustainable Development and Civil Engineering (EWG-ORSDCE) was established--c.f., Kaplinski (2010) and Tamosaitiene et al. (2010). Furthermore, several joint colloquia resulted in dozens of jointly published books and articles in Germany, Poland and Lithuania. Besides, the meetings inspired a number of dissertations. Members to the colloquia also acted as reviewers of PhD theses.

The outstanding personality and contribution of Professor Oleg Kaplinski (Fig. 1) to all colloquia has been invaluable. Born in Vilnius on 15 June 1942, he graduated from the Faculty of Civil Engineering of the Poznan University of Technology (PUT) in 1965. It is in this University that the Professor worked as the Head of the Department of Construction Engineering and Management for thirty years. Recently, he was re-elected as a member of the Committee on Civil Engineering and Hydroengineering of the Polish Academy of Sciences for the fifth term of office. For a number of years, the Professor has been in charge of the Section for Civil Engineering Projects of the Committee. In the winter semester of 1985, he was a guest lecturer at the Vilnius Gediminas Technical University (known as Vilnius Civil Engineering Institute at the time), which awarded the Professor an honorary doctorate in 1996. At VGTU, he supervised nine PhDs. In addition, the Professor is an international member of the Building Academy in Kiev. Works by Professor Kaplinski have been presented on several continents. 240 works including 11 books have been published. His areas of interest include construction industry production management, construction process modelling and theory of decision-making.

[FIGURE 1 OMITTED]

In 1967, the first research by Professor Kaplinski was devoted to application and development of network and mathematical methods for organisation and planning of a construction site. This later developed into two books (Kaplinski, Stefanski 1970; Kaplinski, Skarzynski 1973). The book on network methods has three editions and countless citations. His PhD thesis was on the subject of transport and assembly of prefabricated elements. In the history of Poland, it was the first practical application of the theory of queues in construction industry. He deffended his post-doctoral dissertation on balancing construction processes under stochastic conditions (Kaplinski 1978) at the Krakow University of Technology.

His academic work focused on methodology of research, analysis and reasoning of the phenomena of expectation and balance; he researched the principles of balancing and concentration under stochastic and unspecified conditions. In further research, he developed the subjects of reliability of production, the use of expert systems and hybrid methods. Later, he researched issues of governance including risk management, integrated management and the use of information technology (IT); and finally, the standardisation of the management process in the investment process. Some of these topics are discussed below in the context of the above mentioned colloquia.

2. Reliability of production processes

The first cases of risk assessment discussed at the tripartite academic colloquia were based on reliability. Naturally, the methods evolved. Some elements of reliability theory are effectively used to analyse the time required for implementation of technological processes. Initiation dates of processes were also studied, as well as buffering (introducing time reserves) (Borucka, Kaplinski 1982; Kaplinski 1997; Kaplinski, Zavadskas 2002). Such issues as non-uniformity of production (Kaplinski 1993 a, 1997), material supplies (Kaklauskas et al. 2007), the impact of weather conditions on work technology (Paslawski 2003, 2010), the accident rate in construction industry (Kaplinski 2002a; Zavadskas, Vaidogas 2008, 2009), and selection of implementation options (Shevchenko et al. 2008; Vaidogas, Zavadskas 2007; Zavadskas 1996) were researched as well.

Although initially Professor Kaplinski focused on methods of reserving or redundancy, later he also considered such issues as serious time-lag or inertia (Kaplinski 2001a, b). Inertia is usually treated as elapsed time from the onset of a breakdown to the system's inability to work. The phenomenon of inertia often occurs in accessory production and is rarely recognised as an excellent tool for increasing reliability. In the course of further research under the supervision of Professor Kaplinski, the risk analysis was extended to reliability of operation of systems (e.g., production systems). A simulator was built to consider the series structure. It allowed ascribing any structure and delay to every single element (phase) of the system. Every element worked in two states: work (ability) and disability. The method not only required defining the system structure, but also the types of distribution of those two states for each element of the system formatted in a dry way. As final effect, two distributions could be achieved: proper work of the system and breakdowns of the system. The idea of this extended method is presented in Fig. 2. The method is described in Kaplinski (1985a, b, 1997), Kaplinski and Milosz (1996). Three stages of the modelling procedure (TMT)--which is consistent with the induction method much needed for research on production --are presented on the left side of Fig. 2.

3. Reliability and contingency

Kaplinski (1974) proposed a method for determining time reserves--delays in the integration of successive sequences of processes within the Flow Line Method. His works were published much earlier than the Critical Chain Method (Goldratt 1997). Since then, the Theory of Constrains on the Reliability Theory prevails in applications for the organization of production. The way this subject matter was developed is presented in Fig. 3.

Prevention of disturbances in deadlines of scheduled work still relies on various types of reserves, mainly reserves of time. This is crucial for design of heterogeneous processes. These methods gained a greater status thanks to the development of heuristic methods and measures ensuring robustness of schedules.

The work on robustness continues, as exemplified by predictive/proactive scheduling and reactive scheduling. The most valuable direction of research in this area is predictive/proactive scheduling under a limited availability of resources. Resource-Constrained Project Scheduling Problems (Lambrechts et al. 2008) could be a good example of such work. In Poland, work by Klimek is noteworthy, including the PhD thesis (Klimek 2010).

In consequence, these approaches allow determining time contingency. This applies especially to time buffer allocation at the end of processes (the end of the project). The above mentioned direction of development results in contingency of resources, including--above all--costs. In the engineering practice (practical aspect of investment), contingencies have the following meanings:

--Contingency period means extension of the time of project implementation, which the contractor should accept at an assumed level of risk.

--Contingency amount means an amount of money which a contractor should have saved as a form of collateral in view of project implementation, assuming a certain level of risk.

Contingency is given a slightly wider angle in the overall project risk management. In this case, other aspects are also taken into account, in accordance with the cycle of risk analysis, as shown in Fig. 3. Two concepts are utilised here: contingency plan and contingency budget (Kaplinski 2010; Kaplinski et al. 2011a, b). This line of research is promising and has an important practical aspect (Paslawski 2008a, b, 2009; Nassar 2002; Burger 2003; Barraza, Bueno 2007; Sonmez et al. 2007; Kasprowicz 2004; Jaskowski, Biruk 2011a, b).

[FIGURE 2 OMITTED]

4. Management of construction projects

4.1. Application of expert systems and hybrid methods

The publication by Kaplinski and Hajdasz (1987) was an attempt to merge reliability with design work and expert systems. Collaboration with Lithuanian colleagues resulted in a number of joint publications, such as Kaplinski and Zavadskas (1997), and Kaplinski's book with coauthors (Zavadskas et al. 1995). It was the first book on applications of expert systems in construction industry in this part of Europe. At the same time, Professor O. Kaplinski's team was working on combined methods, which were later identified as hybrid methods (Kaplinski 1985a, b). They emerged in response to criticism regarding the "pure" expert systems, which were believed to have little utility in construction practice. Hybrid approach was proposed instead, as reflected in subsequent publications (Kaplinski 1990, 1993b, 1997).

[FIGURE 3 OMITTED]

Further research focused on advisory systems. An advisory system is a developed and specialised form of an expert system. Such systems are usually hybrids by nature. The team built a hybrid advisory system for the purpose of repairing concrete industrial floors (HASRICF) (Gajzler 2008a, b). The system, basing on answers provided by the user during a dialogue, generates conclusions and informs about the possible material and technological solutions, as well as costs and corrective algorithms. The HASRICF advisory system is based on system modules. The most important of those are: a knowledge base (in the form of fuzzy, rule base), a database, an inferential mechanism that uses ANN, and a dialogue interface. While the inferential mechanism in the form of ANN has proved to be an effective solution, the knowledge acquisition form requires amelioration. At present, a solution is sought for in the group of automatic acquisition methods (data/text mining, induction of rules from decision trees) (see Gajzler 2010).

The hybrid approach allows incorporating a wide range of Multiple Criteria Decision Making (MCDM) methods. Review of the applications of these methods was given by Zavadskas and Turskis (2011).

4.2. Risk management

The tripartite academic colloquia especially focused on the risk management topic. In view of project management, different approaches were presented (i.e., Kaplinski et al. 2002; Kaplinski 2002b; Dziadosz, Kaplinski 2008; Dziadosz 2010; Zavadskas et al. 2010; Meszek, Dziadosz 2011). The team constantly worked on devising various risk management instruments (i.e., Kaplinski, Thiel 1990; Kaplinski, Meszek 1992; Paslawski 2003).

Identification of the so-called risk factors is of major importance in risk analysis. The risk factors and relationships between them are significant concepts in risk management. COMPASS (prepared in U.S., 1996) was one of the first methods for early identification and control of risk factors. It was a type of Decision Support System that covered four modules (Hastak et al. 1996). The year 2000 brought further interesting methods, such as RAMP and ICRAM. RAMP is a systematised process of identification, assessment and risk management in investment processes (RAMP 2005). ICRAM is used to analyse risk at international construction markets. Three risk levels were introduced, i.e. macro, market and project levels (Hastak, Shaked 2000). MOCRA (Method of Construction Risk Assessment) was developed in Poland (Skorupka 2005). It uses an idea suggested in the ICRAM method. This method is accompanied by two tables:

--correlation of construction project operations with risk factors,

--hierarchy of risk factors (AHP).

In consequence, the analysis allows defining the differences between forecasted time and costs and real time and costs. Two alternative schedules are then offered. Sometimes, such solutions are controversial, particularly in cooperation with subcontractors. The evaluation of alternative schedules was presented in Kaplinski (2010).

The following concepts are related to the notion of risk management:

--the risk of bankruptcy, for example of a building company. An assessment of such a risk using scoring methods was presented in (Kaplinski 2008b);

--the approach to risk (aversion or disposition to risk). The use of utility theory and conditional probabilities in this regard is also presented in the last work by Kaplinski (2012).

The above presented issues belong to a separate area of research and apply not only to the area of economic evaluation, but also to the psychology of a decision making.

4.3. An attempt at a comprehensive approach

Experience suggests the need of an extended project risk analysis. This analysis arises in an evolutionary way. A number of trends can be identified here. First of all, the above discussed production reliability trend. Discount methods provide a different outlook, i.e., Net Present Value or Value at Risk.

Another interesting trend is based on the analysis of current network models, together with the Earned Value (EV) and Earned Schedule (ES) models. While discount methods are more useful to investors, EV and ES methods are more useful to contractors. These aspects are also presented in publications (Kaplinski 2010; Kaplinski et al. 2011b). It is significant that there is a need to extend this approach with the introduction of integrated management, including such systems as Enterprise Resource Planning (ERP) and Business Intelligence. However, it may take a long time before building companies will fully implement such systems (Kaplinski 2008a, 2009c, d).

4.4. Standardisation in investment process management

Investment process is mainly affected by current legal regulations. Due to randomness of events and a desire to unify procedures, there has been a shift towards standardisation and clear, simple guidelines and rules of conduct. There is a tendency to disseminate knowledge in the following areas: project management, use of PMBOK[R]PMI and PRINCE2--methods for controlling work progress, standard contract conditions (including FIDIC), which leads to integrated management.

The new management paradigm (based on process management) fosters identification and quantification of risk. Nonetheless, it has become necessary to simultaneously manage the company and risk itself.

Terms of contract--which are a part of international standards--not only necessitate adoption of an appropriate organisational structure, but also indicate the areas of responsibility and the way risk is shared. The most recent research results in this area are provided in the publications (Kaplinski 2011; Kaplinski et al. 2011 b).

5. Final remarks

The review of achievements by Professor Kaplinski should be supplemented by publications synthesising knowledge and achievements of other participants of the colloquia. The most significant are the articles and books on processes and construction project modelling (Kaplinski 1997, 2005, 2007; Kaplinski et al. 2002). In addition to articles evaluating the colloquia, there are publications focusing on assessment of the academic community working in this area, including evaluations of promotional work (Kaplinski, Zavadskas 2002). The syntheses of academic heritage of other prominent colloquia members were also presented in Kaplinski (2009a, b), Kaplinski and Peldschus (2011a, b), Kaplinski and Tamosaitiene (2010), Kaplinski and Tupenaite (2011). These publications reveal the evolution of concepts and methods aimed at resolving the risk management problem in construction industry.

This overview shows that the risk can be analysed depending on a context. Risk should be treated as a state, in which there is a possibility of a loss. One of the most relevant concepts of risk is the dispersion of actual and expected results. This concept leaves room for contingency.

Processes in construction industry, as well as implementation of construction projects are governed by specific laws. The need to standardise legislation results from international cooperation in the execution of contracts and requirements of banks. This promotes standardisation, especially at the stage of preparation for and implementation of investments.

Efforts to create standards in planning and implementation of construction project activities allowed for elimination of such phenomena as instability of processes, unreliability, decrease in quality, unpredictability of events, and etc. Further research should be continued in this direction.

doi: 10.3846/13923730.2012.672931

References

Barraza, G. A.; Bueno, R. A. 2007. Cost contingency management, Journal of Management in Engineering ASCE 23(3): 140-146. http://dx.doi.org/10.1061/(ASCE)0742-597X (2007)23:3(140)

Borucka, E.; Kaplinski, O. 1982. Simulations methode zur Bewertung der Zuverlassigkeit von Produktionsprozessen in Plattenwerke, Wissenschaftliche Zeitschrift der Hochschule fur Architektur und Bauwesen, Weimar, Heft 2: 129-132.

Burger, R. 2003. Contingency, qualifying the uncertainty, Journal of Cost Engineering 45(8): 12-17.

Dziadosz, A. 2010. Przeglad wybranych metod wspomagajacych analize ryzyka przedsiewziec budowlanych [A review of selected methods supporting the construction projects risk analysis], Przeglad budowlany [Overview of construction] 7-8: 76-77.

Dziadosz, A.; Kaplinski, O. 2008. Ryzyko w inzynierii przedsiewziec budowlanych. Retrospekcja z konferencji w Ciechocinku (1999-2007) [The risk in engineering construction projects. Retrospection from the conferences in Ciechocinek (1999-2007)], in J. Bizon-Gorecka (Ed.). Strategie zarzadzana ryzykiem w przedsiebiorstwie--ryzyko przedsiebiorstwa a ryzyko projektu [Strategies for risk management in the enterprise--enterprise risk and project risk]. Bydgoszcz-Ciechocinek: TNOiK Press, 29-46.

Gajzler, M. 2008a. Hybrid advisory systems and the possibilities of it usage in the process of industrial flooring repairs, in Proc. of the 25th International Symposium on Automation and Robotics in Construction (ISARC-2008), 26-29 June, 2008, Vilnius, Lithuania, Ed. by E. K. Zavadskas, A. Kaklauskas, M. J. Skibniewski, 459-164.

Gajzler, M. 2008b. Hybrid advisory system for repairs of concrete industrial floors. PhD thesis. Poznan: Poznan University of Technology. (in Polish).

Gajzler, M. 2010. Text and data mining techniques in aspect of knowledge acquisition for decision support system in construction industry, Technological and Economic Development of Economy 16(2): 219-232. http://dx.doi.org/10.3846/tede.2010.14

Goldratt, E. M. 1997. Critical chain. Great Barrington: The North River Press Publishing Corporation. 246 p.

Hastak, M.; Halpin, D. W.; Vanegas, J. 1996. COMPASS--new paradigm for project cost control strategy and planning, Journal of Construction Engineering and Management ASCE 122(3): 254-264. http://dx.doi.org/10.1061/ (ASCE)0733-9364(1996)122:3(254)

Hastak, M.; Shaked, A. 2000. ICRAM-1: model for international construction risk assessment, Journal of Management in Engineering ASCE 16(1): 59-69. http://dx.doi.org/10. 1061/(ASCE)0742-597X(2000)16:1(59)

Jaskowski, P.; Biruk, S. 2011a. Ocena porownawcza miernikow odpornosci harmonogramow budowlanych [Evaluating surrogate measures of construction Project schedule robustness], Civil and Environmental Engineering / Budownictwo I Inzynieria Srodawiska 2: 501-505. http://dx.doi.org/10.3846/20294913.2011.580587

Jaskowski, P.; Biruk, S. 2011b. The method for improving stability of construction project schedules through buffer allocation, Technological and Economic Development of Economy 17(3): 429-444.

Kaklauskas, A.; Kaplinski, O.; Peldschus, F.; Zavadskas, E. 2005. Historie und Trends des Kolloquiums, 20 Iahre wissenschaftlicher Gedankenaustausch [History and trends of the colloquium, 20 years of scientific exchange], Podium, Sonderheft [Panel, Special Issue], 2005, 11 Jahrgang, N 1. (10th International Colloquium "Planning tools for managing the project", 19-20 May, 2005, Leipzig), 3-9. http://dx.doi.org/10.1016/j.engappai.2006.06.009

Kaklauskas, A.; Zavadskas, E. K.; Trinkunas, V. 2007. A multiple criteria decision support on-line system for construction, ngineering pplications of rtificial Intelligence 20(2): 163-175.

Kaplinski, O. (Ed.). 2007. Metody i modele badan w inzynierii przedsiewziec budowlanych [Methods and models of research in construction project engineering]. Warszawa: PAN, KILiW, IPPT, Serie Studia z Zakresu Inzynierii [Series of Studies in Engineering], No. 57. 415 p. http://dx.doi.org/10.1080/01446199300000064

Kaplinski, O. 1974. Niektore problemy metody pracy rownomiernej w warunkach stochastycznych [Some problems of flow line method under stochastic conditions], in XX Jubileuszo a onferencja aukoa oitetu Inzynierii Ladowej i Wodnej PAN i Komitetu Nauki PZITB [Material of XX Anniversary Scientific Conference], Krynica 5: 129-137.

Kaplinski, O. 1978. Harmonizacja cyklicznych procesow budowlanych w ujeciu stochastycznym [Balancing of cyclic construction processes--stochastic approach]. Poznan: Poznan University of Technology Press, serie Rozprawy, no. 91. 166 p.

Kaplinski, O. 1985a. Die Ausnutzung der Simulationstechnik zur Untersuchung und die Steuerung der Zuverlassigkeit von Produktionsprozessen im Bauwesen [The utilization of the simulation technique for studying and controlling the reliability of production processes in the construction industry], in Informatik-Fachberichte [Computer science expert reports], Band 109: Simulatiostechnik, Springer-Verlag, 517-521.

Kaplinski, O. 1985b. Die simulations-analytischen und simulations-heuristischen Methoden zur Bestimmung der Produktionsparameter, Wiss. Beitrage IH-Wismar, Sonderheft 3: 32-33.

Kaplinski, O. 1990. The combined/hybrid expert systems in construction, in Proc. of the International Symposium on Building Economics and Construction Management, CIB W 55-W 65 Joint Symposia, Vol. 2. Design Economics. Expert Systems, Sydney, 505-513.

Kaplinski, O. 1993a. Diminishing non-uniformity of construction processes, Construction Management and Economics 11(1): 53-61. http://dx.doi.org/10.1080/01446199300000064

Kaplinski, O. 1993b. From classical methods to hybrid expert systems in construction, Journal of Real Estate & Construction 3(1): 85-97.

Kaplinski, O. 1997. Modelling of construction processes: a managerial approach. Warszawa: KILiW PAN, Instytut Podstawowych Problemow Techniki, serie: Studia z Zakresu Inzynierii, No. 43. 175 p.

Kaplinski, O. 2001a. Phenomenon of inertia in construction industry, Statyba--Journal of Civil Engineering and Management 7(4): 281-285.

Kaplinski, O. 2001b. Risk compensation in execution phase: from bottleneck to inertia, IABSE Conference Report: Safety, Risk and Reliability--Trends in Engineering, Malta, 2001, 423-424.

Kaplinski, O. 2002a. Accident rate on building sites as a quality data in a simulation model of production, in Proc. of the Triennial Conference CIB WO99 "Implementation of Safety and Health on Construction Sites", 7-10 May, 2002, Hong Kong, 95-101.

Kaplinski, O. 2002b. Klasyfikacja ryzyka w zarzadzaniu wedlug Andreasa Klinkego i Ortwina Renna [Classification of risk in management by Andreas Klinkeand Ortwin Renn], Przeglad Organizacji [Review of the organization] 5: 13-17.

Kaplinski, O. 2005. Modelling construction processes: a review of research and dissertations at the Poznan University of Technology, Civil and Environmental Engineering Reports 1: 85-105.

Kaplinski, O. 2008a. Development and usefulness of planning techniques and decision making foundations on the example of construction enterprises in Poland, Technological and Economic Development of Economy 14(4): 492-502. http://dx.doi.org/10.3846/1392-8619.2008.14.492-502

Kaplinski, O. 2008b. Usefulness and credibility of scoring methods in construction industry, Journal of Civil Engineering and Manageent 14(1): 21-28. http://dx.doi.org/10.3846/1392-3730.2008.14.21-28

Kaplinski, O. 2009a. Professor Edmundas K. Zavadskas: the research achievements and trans-border cooperation, Archives of Civil Engineering 55(3): 287-300.

Kaplinski, O. 2009b. Sapere Aude: Professor Edmundas Kazimieras Zavadskas, Inzinerine Ekonomika--Engineering Economics 20(5): 113-119.

Kaplinski, O. 2009c. Information technology in the development of the Polish construction industry, Technological and conoic evelopent of conoy 15(3): 437-452. http://dx.doi.org/10.3846/1392-8619.2009.15.437-452

Kaplinski, O. 2009d. Problems of the information technologies use in Polish construction sector: state of the art, Archives of Civil Engineering 55(2): 173-198.

Kaplinski, O. 2010. Risk analysis of construction projects: from risk identification to contingency timetable, in The 4th International Conference on Structural Engineering, Mechanics and Computation (SEMC 2010), 6-8 September, 2010, Cape Town, South Africa, Ed. by A. Zingoni, Advances and Trends in Structural Engineering, Mechanics and Computation, CRS Press Balkema, Taylor & Francis Group, London. Abstract: 268, paper CD, 1051-1054.

Kaplinski, O. 2011. Report of the Section of the Committee for Civil Engineering in the term 2007-2010, Archives of Civil Engineering 57(1): 5-16.

Kaplinski, O. 2012. The utility theory in maintenance and repair strategy, in The 2 International Conference on Rehabilitation and Maintenance in Civil Engineering, Solo, March 8th-10th, 2012.

Kaplinski, O.; Dziadosz, A.; Zioberski, J. L. 2011a. Proba standaryzacji procesu zarzadzania na etapie planowania i realizacji przedsiewziec budowlanych [An attempt of management process standardisation at the stage of planning and implementation of construction projects], Zeszyty Naukowe Politechniki Rzeszoskiej. Budownictwo i Inzynieria Srodowiska [Scientific Papers of Rzeszow University of Technology. Civil and Environmental Engineering] 58(3/I): 79-100.

Kaplinski, O.; Dziadosz, A.; Zioberski, J. L. 2011b. Proba standaryzacji procesu zarzadzania na etapie planowania i realizacji przedsiewziec budowlanych [An attempt to standardize the process of managing the planning and execution of construction projects], Zeszyty naukowe politechniki rzeszowskiej, budonictwo i inzynieria srodowiska [Scientific papers of Rzeszow University of Technology, Civil and Environmental Engineering] 58(3/11/i): 79-100.

Kaplinski, O.; Hajdasz, M. 1987. Design of technology and organization of construction with the aid of simulation and expert systems (Problems, experiences, prospects), in Proc. of the 4th International Symposium on Robotics & Artificial Intelligence in Building Construction, Haifa, Israel 2: 788-798.

Kaplinski, O.; Meszek, W. 1992. Catastrophic and strategic aspects of building processes balancing, Construction Management and Economics 10(1): 81-88. http://dx.doi.org/10.1080/01446199200000007

Kaplinski, O.; Peldschus, F. 2011a. The problems of quantitative evaluation of socio-economic systems' development, Inzinerine Ekonomika--Engineering Economics 22(4): 345-355.

Kaplinski, O.; Peldschus, F. 2011b. Socio-economic systems: a school of Professor Romualdas Ginevicius, Civil and Environental Engineering--Budownictwo i Inzynieria Srodowiska (2): 517-520.

Kaplinski, O.; Skarzynski, A. 1973. Wybrane metody matematyczne w organizacji i planowaniu budowy [Selected mathematical methods in the organization and planning of construction]. Poznan: Poznan University of Technology Press. 116 p.

Kaplinski, O.; Stefanski, A. 1970. Metody sieciowe w organizacji i planowaniu budowy [Network Methods in the organization and planning of construction]. 1st ed. Poznan: Poznan University of Technology Press. 144 p.

Kaplinski, O.; Tamosaitiene, J. 2010. Game theory applications in construction engineering and management, Technological and Economic Development of Economy 16(2): 348-363. http://dx.doi.org/10.3846/tede.2010.22

Kaplinski, O.; Thiel, T. 1990. Some aspects of sensitivity analysis in the Entropy method, Foundations of Control Engineering 15(1): 39-18.

Kaplinski, O.; Tupenaite, L. 2011. Review of the multiple criteria decision making methods, intelligent and biometric systems applied in modern construction economics, Transformations in Business & Economics 10(1): 166-181.

Kaplinski, O.; Werner, W.; Kosecki, A.; Biernacki, J.; Kuczmarski, F. 2002. Current state and perspectives of research on construction management and mechanization in Poland, Journal of Civil Engineering and Management 8(4): 221-230.

Kaplinski, O.; Zavadskas, E. K.; Peldschus, F.; Kaklauskas, A. 2004. Problems and evolving trends of construction colloquia on decision making and operational research, Foundations of Civil and Environmental Engineering 5: 83-90.

Kaplinski, O.; Zavadskas, E. K. 2002. An overview of the problems related to research in construction engineering, management and economics in Poland, Journal of Civil Engineering and Management 8(4): 231-239.

Kaplinski, O. 2010. Review of trans-border co-operation in construction management between Lithuania, Germany and Poland, Evolution of Science and Technology 2(1): 5-18. http://dx.doi.org/10.3846/est.2010.22

Kaplinski, O.; Milosz, M. 1996. Reliability of complex production systems, Civil Engineering Systems 13(1): 61-73. http://dx.doi.org/10.1080/02630259608970186

Kaplinski, O.; Zavadskas, E. 1997. Expert systems for construction processes, Statyba--Journal of Civil Engineering and Management 12(4): 49-61.

Kasprowicz, T. 2004. Kontyngencja przedsiewziec budowlanych [Contingency of construction projects], Biuletyn Wojskowej Akademii Technicznej [Bulletin of the Military Technical Academy] 53(8): 91-108.

Klimek, M. 2010. redyktyno-reaktyne haronograowanie produkcji z ograniczona dostepnoscia zasobow [Predictive-reactive production scheduling with limited availability of resources]. PhD thesis. Krakow: AGH.

Lambrechts, O.; Demeulemeester, E.; Herroelen, W. 2008. A tabu search procedure for developing robust predictive project schedules, International Journal of roduction Economics 111(2): 493-508. http://dx.doi.org/10.1016/j.ijpe.2007.02.003

Meszek, W.; Dziadosz, A. 2011. Wplywnie efektywnos cirynku nieruchomosci na dokladnosc opisu wartosci nieruchomosci za pomoca liniowych modeli regresji wielorakiej [The influence of inefficiency of property market on the accuracy of description of property value using linear models of multiple regression], Civil and Environmental Engineering/Budownictwo I Inzynieria Srodowiska 2: 589-594.

Nassar, K. 2002. Cost contingency analysis for construction projects using spreadsheets, Cost Engineering 44(9): 26-35.

Paslawski, J. 2003. Risk management in technological DSS in construction industry, Journal of Decision Systems 12(3-4): 329-344. http://dx.doi.org/10.3166/jds.12.329-344

Paslawski, J. 2008a. Flexibility approach in construction process engineering, Technological and Economic Development of Economy 14(4): 518-530. http://dx.doi.org/10.3846/1392-8619.2008.14.518-530

Paslawski, J. 2008b. Flexibility approach in the runway pavement using FLEMANCO method, Transport 23(4): 341-350. http://dx.doi.org/10.3846/1648-4142.2008.23.341-350

Paslawski, J. 2009. Flexibility in highway noise management, Transport 24(1): 66-75. http://dx.doi.org/10.3846/1648 4142.2009.24.66-75

Paslawski, J. 2010. Risk management using flexibility in construction engineering, in Proc. of the 10th International Conference "Modern Building Materials, Structures and Techniques", 19-21 May, 2010, Vilnius, Lithuania. Ed. by P. Vainiunas and E. K. Zavadskas 1: 489-492.

Peldschus, F. 2009. 29 years of successful scientific cooperation, in Proc. of the 12th German-Lithuanian-Polish Colloquium on Sustainable Development in Civil Engineering and Multi-Attribute Decision Making, 23-25 May, 2009, Vilnius, Lithuania, 12-15.

Peldschus, F.; Kaplinski, O.; Zavadskas, E. K.; Kaklauskas, A. 2006. Historie und Trends des Kolloquiums, Technological and Economic Development of Economy 12(3): 227-235.

RAMP 2005. Risk Analysis and Management for Projects (RAMP). 2nd ed. Actuarial Profession, Institute of Civil Engineers. London: Thomas Telford Publishing. 148 p.

Shevchenko, G.; Ustinovichius, L.; Andruskevicius, A. 2008. Multi-attribute analysis of investments risk alternatives in construction, Technological and Economic Development of Economy 14(3): 428-443. http://dx.doi.org/10.3846/1392-8619.2008.14.428-443

Skorupka, D. 2005. The method of identification and quantification of construction project risk, Archives of Civil Engineering 51(4): 647-662.

Sonmez, R.; Ergin, A.; Birgonul, M. T. 2007. Quantitative methodology for determination of cost contingency in international projects, Journal of Management in Engineering ASCE 23(1): 35-39. http://dx.doi.org/10.1061/(ASCE)0742-597X(2007)23:1(35)

Tamosaitiene, J.; Bartkiene, L.; Vilutiene, T. 2010. The new development trend of operational research in civil engineering and sustainable development as a results of collaboration between German-Lithuanian-Polish scientific triangle, Journal of Business Economics and Management 11(2): 316-340.

Vaidogas, E. R.; Zavadskas, E. K. 2007. Introducing reliability measures into multi-criteria decision-making, International Journal of Management and Decision Making 8(5/6): 475-496. http://dx.doi.org/10.1504/IJMDM.2007.013413

Zavadskas, E. 1996. Zusammenhang zwischen der Mehrzweckselektierung und der Zuverlassigkeit im Bauwesen, Statyba --Journal of Civil Engineering and Management 6(2): 23-26.

Zavadskas, E. K.; Vaidogas, E. R. 2008. Bayesian reasoning in managerial decisions on the choice of equipment for the prevention of industrial accidents, Inzinerine Ekonomika--Engineering Economics (5): 32-40.

Zavadskas, E. K.; Vaidogas, E. R. 2009. Multiattribute selection from alternative designs of infrastructure components for accidental situations, Computer--Aided Civil and Infrastructure Engineering 24(5): 346-358. http://dx.doi.org/10.1111/j.1467-8667.2009.00593.x

Zavadskas, E.; Kaplinski, O.; Kaklauskas, A.; Brzezinski, J. 1995. xpert systes in construction industry: trends, potentials and applications. Vilnius: Technika. 180 p.

Zavadskas, E. K. 2008. History and evolving trends of construction colloquia on sustainability and operational research, Technological and Economic Development of conoy 14(4): 578-592. http://dx.doi.org/10.3846/1392-8619.2008.14.578-592

Zavadskas, E. K.; Kaklauskas, A. 2001. History and trends of development of colloquy, Journal of Civil Engineering and Management 8(4): 265-275.

Zavadskas, E. K.; Turskis, Z. 2011. Multiple criteria decision making (MCDM) methods in economics: an overview, Technological and Economic Development of Economy 17(2): 397-427. http://dx.doi.org/10.3846/20294913.2011.593291

Zavadskas, E. K.; Turskis, Z.; Tamosaitiene, J. 2010. Risk assessment of construction projects, Journal of Civil Engineering and Management 16(1): 33-46. http://dx.doi.org/10.3846/jcem.2010.03

Zenonas Turskis (1), Marcin Gajzler (2), Agnieszka Dziadosz (3)

(1) Faculty of Civil Engineering, Vilnius Gediminas Technical University, Sauletekio al. 11, 10223 Vilnius, Lithuania

(2,3) Faculty of Civil and Environmental Engineering, Poznah University of Technology, Piotrowo 5, 60-965 Poznah, Poland

E-mails: (1) zenonas.turskis@vgtu.lt (corresponding author); (2) marcin.gajzler@put.poznan.pl; (3) agnieszka.dziadosz@put.poznan.pl

Zenonas TURSKIS. Doctor of Technical Science, senior research fellow of Construction Technology and Management Laboratory of Vilnius Gediminas Technical University. Research interests: building technology and management, decision- making theory, computer-aided automation in design, expert systems.

Marcin GAJZLER. PhD C.E., Assistant Professor, Poznah University of Technology, Institute of Structural Engineering, Division of Construction Engineering and Management. Analyst at the stage of solving decision problems in the area of construction engineering. Research interests: decision-making theory, AI methods in construction industry (fuzzy logic, artificial neural networks, advisory systems), methods of knowledge acquisition (data & text mining), investment process, economic and management in construction.

Agnieszka DZIADOSZ. PhD student, Poznah University of Technology, Institute of Structural Engineering, Division of Construction Engineering and Management. Graduated Krakow Technical University. She is working on her PhD thesis on risk management in construction projects. Additional research interests: statistical analysis and operational research in construction, investment process and decision-making theory.
COPYRIGHT 2012 Vilnius Gediminas Technical University
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2012 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Author:Turskis, Zenonas; Gajzler, Marcin; Dziadosz, Agnieszka
Publication:Journal of Civil Engineering and Management
Article Type:Report
Geographic Code:4EXPO
Date:Apr 1, 2012
Words:5481
Previous Article:Comparison of testing results of three poorly streamlined entertainment venues/Triju sudetingo pavidalo pramoginiu statiniu maketu bandymu rezultatu...