 PLYMOUTH, Mass., June 1 /PRNewswire/ -- On Friday, May 28 at 1:21 a.m., Pilgrim was restarted. The plant returned to the grid on Sunday, May 30th, following a 57-day refueling outage. During the outage, 140 fuel bundles, about 1/3 of the reactors's core, were replaced. Other work completed during the outage includes maintenance, testing, and inspections which cannot be done during plant operation. On the non-nuclear side of the plant, a major turbine overhaul was completed.
 On Monday evening, May 31st at 7:20 p.m., a turbine load reject resulted in an automatic plant shut-down.
 The shut-down occurred when the plant was at 25 percent power, and in the process of transferring plant systems to internal electrical power sources. During plant outages, Pilgrim Station uses electricity from the New England power grid.
 The reason for the plant trip is under investigation. Restart is expected later this week.
 -0- 6/1/93
 /CONTACT: David Tarantino or Anita Flanagan of Boston Edison, 508-224-4803/


CO: Boston Edison ST: Massachusetts IN: OIL SU:

DD -- NE012 -- 4041 06/01/93 14:42 EDT
COPYRIGHT 1993 PR Newswire Association LLC
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1993 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:PR Newswire
Date:Jun 1, 1993
Words:181
Previous Article:NRC MONTHLY INSPECTION REPORT
Next Article:SACRAMENTO TOURISM 'CLEANS UP' AS FORD DELIVERS CLEAN FUEL TAURUS FFVs TO RENTAL CAR COMPANIES
Topics:


Related Articles
PEACH BOTTOM UNIT 3 RETURNS FROM REFUELING OUTAGE
BOSTON EDISON TEMPORARILY SHUTS PILGRIM NUCLEAR POWER STATION TO INVESTIGATE OPERATION OF STEAM LINE VALVE
PILGRIM STATION BEGINS PLANNED MAINTENANCE SHUTDOWN
PECO'S LIMERICK 2 BACK ON LINE AHEAD OF SCHEDULE
PILGRIM STATION WILL BE TAKEN OFF LINE FOR TWO MONTHS
NRC MONTHLY INSPECTION REPORT
BOSTON EDISON TO BRING PILGRIM NUCLEAR POWER STATION TO 'COLD SHUTDOWN'
PILGRIM NUCLEAR POWER STATION; NRC MONTHLY INSPECTION REPORT
PEACH BOTTOM UNIT 3 RETURNS TO SERVICE AFTER REFUELING OUTAGE
RIVER BEND RETURNS TO ENTERGY ELECTRIC GRID; SETS NEW RECORD

Terms of use | Copyright © 2017 Farlex, Inc. | Feedback | For webmasters