NRC STAFF PROPOSES $25,000 FINE AGAINST WASHINGTON PUBLIC POWER SUPPLY SYSTEM

 NRC STAFF PROPOSES $25,000 FINE AGAINST WASHINGTON
 PUBLIC POWER SUPPLY SYSTEM
 WALNUT CREEK, Calif., Feb. 7 /PRNewswire/ -- The Nuclear Regulatory Commission staff is proposing to fine the Washington Public Power Supply System (WPPSS) $25,000 for an alleged violation of NRC requirements concerning the containment atmospheric control system (CAC) at Washington Nuclear Project No. 2, located 11 miles north of Richland, Wash. NRC Regional Administrator John B. Martin notified the company of the alleged violation by letter on Feb. 6, 1992.
 On Oct. 31, 1991, WPPSS reported that both hydrogen recombiner systems at WNP-2 were inoperable, since they would not function in the automatic mode, from before initial plant startup in 1984 until August 1991, due to installation of an improper component. The hydrogen recombiners, which constitute the CAC, are necessary to reduce the consequences of certain potential accidents. WNP-2 is required to shutdown within 12 hours if either recombiner is out of service longer than thirty days.
 During an inspection conducted Nov. 4 through Dec. 8, 1991, NRC inspectors identified information supporting the alleged violation.
 The alleged violation has been categorized as Severity Level III on a scale of I to V, with Level I representing a violation of very significant regulatory concern and Level V a violation of minor concern. The base civil penalty for Severity Level III is $50,000. The base civil penalty was reduced 50 percent, resulting in a proposed civil penalty of $25,000, because the Supply System's corrective actions were aggressive, prompt and thorough.
 Two Severity Level IV violations were also identified. One involves seven CAC pipe supports which were not installed as designed. The other involves late notification by WPPSS to the NRC of the inoperability of the hydrogen recombiners. No additional civil penalty was proposed.
 WPPSS now has 30 days to submit a written statement to the NRC admitting or denying the alleged violations, explaining the reasons for them if admitted, stating the corrective actions which have been or will be taken and the date when full compliance was or will be achieved.
 The Supply System also has 30 days to pay the proposed fine or to protest it, in whole or in part. If the fine is protested and later imposed, WPPSS may request a public hearing.
 -0- 2/7/92
 /CONTACT: Greg Cook of U.S. Nuclear Regulatory Commission, 510-975-0346 (office) or 707-644-2428 (home)/ CO: U.S. Nuclear Regulatory Commission ST: California IN: SU:


DG -- SF009 -- 7939 02/07/92 16:51 EST
COPYRIGHT 1992 PR Newswire Association LLC
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1992 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:PR Newswire
Date:Feb 7, 1992
Words:415
Previous Article:CALIFORNIA LENDERS SHARE OF REAL ESTATE LOAN MARKET DECLINES IN 1991
Next Article:FLORIDA REGIONAL STOCK REPORT FOR FRIDAY, FEB. 7
Topics:


Related Articles
NRC STAFF PROPOSES $125,000 CIVIL PENALTY AGAINST CP&L FOR ALLEGED VIOLATION OF NRC REQUIREMENTS AT BRUNSWICK
BRUNSWICK PLANT CITED FOR NRC VIOLATION
NRC STAFF ISSUES SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE FOR CAROLINA POWER & LIGHT COMPANY'S BRUNSWICK NUCLEAR POWER PLANT
NRC STAFF PROPOSES $125,000 FINE AGAINST DUKE POWER FOR ALLEGED VIOLATION OF NRC REQUIREMENTS AT OCONEE
NRC STAFF PROPOSES TWO FINES TOTALLING $162,500 AGAINST ARIZONA PUBLIC SERVICE COMPANY
Power play.
NRC STAFF PROPOSES $18,750 FINE AGAINST SIEMENS POWER
NEW YORK POWER AUTHORITY WORKING TO CORRECT INDIAN POINT PROBLEMS
NRC APPROVES SPENT FUEL STORAGE CONTAINER FOR PALISADES NUCLEAR PLANT
NRC OKS FIRST DESIGN FOR AN ADVANCED NUCLEAR POWER PLANT WITH APPROVAL OF GENERAL ELECTRIC'S ABWR

Terms of use | Copyright © 2016 Farlex, Inc. | Feedback | For webmasters