Modeling of risk acceptance criteria for tunnel and underground engineering.

The importance of risk acceptance criteria research and the calculation principle for determining them are analyzed in according with the present state of art. And some fundamental risk acceptance criteria, such as the individual risk (IR), societal risk (SR), economical risk and environmental risk, are comprehensively introduced. The paper furthermore addresses and discusses some key points, future application and development of these criteria for tunnel and underground engineering. Finally a number of problems are highlighted and the needs for further research are stressed.

INTRODUCTION

The 21st is the big century of the utility and development for tunnelling and underground works (Song Kezhi et al; 2004). Due to the inherent uncertainties, including ground and groundwater conditions and their variability, it might be significant cost overrun, fatalities and time delays as well as environmental risks during the tunnelling construction. Also, for the complexity and immaturity of tunnelling technique in urban areas there is a risk of damage to a range of third party about property and persons, which will be of particular concern by public where heritage designated buildings are involved. Furthermore, there is a risk to public protests affecting the course of the projects. Finally, there has been an increasing societal concern on sustainable developments focusing on the conservation of the environment, the welfare and safety of the individual during the last decade. As demonstrated by spectacular tunnel collapse and other fatal disasters in the recent past like shanghai (Ministry of Construction, China, 2003), there is a potential for large scale accidents during tunnelling. In order to reduce and mitigation the risk, the research and application of some methods of risk management and risk control for tunnelling and underground works are paid attention in recent years.

As a consequence the methods of risk analysis in civil engineering, mainly developed during the last decades, are increasing gaining importance as a useful tool in tunnelling engineering applications (M.H.Faber; 2003). It is important to realize that risk analysis is very complex theory which is often entwined with not only many technical aspects but also some political, psychological and social processes. A number of issues that risk analysis attempt to resolve include (Hood C.C et al; 1992): What information is required for 'scientific and rational' risk management and how to make a decision? Where is the line to be drawn between that are to be managed by individuals, group or corporations? Who is to bear what level of risk? What actions make what difference to risk outcomes? These matters or problems are not easily resolved, are not for risk analysis to solve alone and are all related to risk acceptance criteria; namely, what risks are acceptable? And some risk acceptance criteria for decision-making should be established qualitatively or quantitatively in advance (Ohtsubo.H et al; 2000). The paper attempts to summarize broadly an overview of some risk acceptance criteria irrespective of the type of applicable risk (individual, social, environment and other risk). It ends with some discussion and conclusion of the need to establishing some risk acceptance criteria for tunnelling and underground engineering.

THE MODEL OF RISK ACCEPTANCE CRITERION

In the study of risk analysis and assessment, the risk control and reduction measures are taken involving some money, techniques and labors. And these risk measures are determined based on the balance of loss (damage) or benefit. It is obvious that risk is in interrelation with investment and benefit. How to draw a line or play game between the risk and investment or benefit for decision-making is complied with a risk acceptance criterion. The development and implementation of risk acceptance criteria involves (M.H.Faber; 2003): (1) Perception of risk, ensure that levels of system risk, such as safety, economy and environment, is acceptance (or tolerable); (2) Formal decision analysis: analytical techniques to balance or compare risks against benefit (e.g. risk cost-benefit analysis, life-cycle cost analysis); (3) Regulatory safety goals: legislative and statutory framework for the development and enforcement of risk acceptance criteria.

As is known to us, the risk acceptance criteria are the foundation of risk analysis for decision-making. They generally are adopted by the U.S Nuclear Regulatory Commission (NRC), U.K Health and Safety Executive (HSE), Dutch Technical Advisory Committee on Water Defenses (TWA) and other regulatory authorities. Mainly, there are two basic principles for defining the risk level used for a qualitative or quantitative risk analysis (Melchers RE et al; 1993, Sharp JV et al; 1993): 'As Low As Reasonably Possible (ALARP)' and 'As Low As Reasonably Achievable (ALARA)'. The definition for such terms as 'Low', 'Reasonably', 'Possible' and 'Attainable' are highly subjective and prone to being interpreted in a conservative manner. Some expressions and models have been made to define these criteria in more tangible limit in terms of quantitative risks.

THE CLASSIFICATION OF RISK ACCEPTANCE CRITERIA

The risk acceptance criteria are a complex attribute that results from three influenced factors, safety (personal risk and social risk), economy (potential economical loss, construction schedule) and environment, from a technical perspective of the basic classification of engineering risk (Li Dianqing et al; 2003). And they are established based on not only some quantitative indexes like economical loss or time delays, but also many unquantized indexes such as potential environment damage, the monetary valuation of human life and the public influence, etc. Therefore, the establishment of risk acceptance criteria is a complicated, difficult and controversial task (Ditlevsen O et al; 1996). The risk acceptance criteria can be classified into four elementary categories from the recent overview of recent research around the world (Li Dianqing et al; 2003, S. N. Jonkman et al; 2003): (1) Individual Risk; (2) Social Risk; (3) Economical Risk; and (4) Environmental Risk. Every section starts with an overview of the risk mathematical definition, and then the risk acceptance criteria and their application are described as follows.

Individual Risk

The individual risk (IR), as used by the Dutch Ministry of Housing, Spatial Planning and Environment (VROM), is defined as the probability that an average unprotected person, permanently present at a certain location, is killed due to an accident resulting from a hazardous activity (P.H. Bottelberghs et al; 2000).

IR = [P.sub.f] x [P.sub.d|f] (1)

Where [P.sub.f] is the probability of failure and [P.sub.d|f] probability of dying of an individual in the case of failure, assuming the permanent unprotected presence of the individual.

The risk individual is highly subjectively, which is determined by the individual predilection whether or not the individual is actually voluntary or involuntary. Besides the individual risk as mentioned above, four other expressions are described (T. Bedford et al; 2001). (1) The Loss of Life Expectancy shows the decrease of life expectancy due to various caused; (2) The Delta Yearly Probability of Death computes the intensity at which a given activity is to be performed (in suitable units) to increase the yearly probability of death by 10-6; (3) The Activity Specific Hourly Mortality Rate reflects the probability per time unit while engaged in a specified activity. (4) A variant is the Death per Unit Activity, which replaces the time unit by a unit measuring the amount of activity. A different definition is used by the UK's health and safety executive (HSE) (Health and Safety Executive, 1989) that is the risk which a typical user of a development is exposed to a dangerous dose or worse of toxic substance, heat or blast overpressure. To limit the risks, there are many criteria such as ALARA, Risk Matrix, AFR (Annual Fatality Risk), AIR (Average Individual Risk) and AI (Aggregated Indicator) etc.

Social risk

The societal risk is defined as "the relationship between frequency and the number of people suffering from a specified level of harm in a given population from the realization of specified hazards" (Institute of Chemical Engineering; 1985). Where individual risk gives the probability of dying on a certain location, the societal risk gives a number for a whole area, no matter precisely where the harm occurs within that area. To limit the social risks, there are many criteria such as ALARP, Risk Matrix, F-N curve, PLL (Potential Loss of Life), FAR (Fatal Accident Rate), VIIH (Value of Injuries and Ill Health), ICAF (Implied Cost of Averting a Facility) and LQI (Life Quality Index) etc.

1 - [F.sub.N](x) = P(N > x) = [[integral].sup.[infinity].sub.x][f.sub.N](x)dx (2)

Where [f.sub.N](x) is the probability density function (PDF) of the number of fatalities per year; [F.sub.N](x) is the cumulative probability distribution function (CPDF) of the number of fatalities per year, signifying the probability of less than fatalities per year.

Economic risk

Besides the loss of life due to certain activities, the economic risks play an important role in risk analysis. A FD-curve displays the probability of exceedance as a function of the economic damage (S. N. Jonkman et al; 2003). The FD-curve and the expected value of the economic damage can be derived from the PDF of the economic damage ([f.sub.D](x)).

1 - [F.sub.D](x) = P(D > x) = [[integral].sup.[infinity].sub.x][f.sub.D](x)dx (3)

E(D) = [[integral].sup.[infinity].sub.0]x x [f.sub.D](x)dx (4)

Where [f.sub.D](x) is the cumulative probability distribution function of the economic loss and E(D) is the expected value of the economic damage.

Novgorodsky's study on the economic risks in the Russian region (A.N.Yelokhin et al; 1997) is an example of the use of a FD-curve. Jansen (H.M.A et al; 1998) has tried to obtain a financial economic risk limit in the form of a FD-curve. The expected value of the economic damage is used as part of cost benefit analyses of flood prevention measures in the UK (D.J. Parker et al; 1997) and in The Netherlands (H.M. Zhou et al; 1995). A limit for the expected economic damage per year for dams has been proposed by BC Hydro (Hydropower & Dams; 1998), in which the financial risks for one dam should not exceed: E(D) < 10000 (US $/per year).

Environmental risk

The Environmental Risk (ER) is different with the individual risk and social risk for engineering construction activities in a certain circumstance. There is a risk of damage to a range of third property and persons and of pollution to environment. The competitive standing of the Norwegian offshore sector (NORSOK) has proposed the probability of exceedance of the time needed by the ecosystem to recover from the damage as a measure for environmental risk (NORSOK; 1998).

1 - [F.sub.T](x) = P(T > x) = [[integral].sup.[infinity].sub.x][f.sub.T](x)dx (5)

E(T) = [[integral].sup.[infinity].sub.0]x x [f.sub.T](x)dx (6)

Where [F.sub.T](x) is the cumulative probability distribution function of the recovery time; [f.sub.T](x) is the probability density function of the recovery time of the ecosystem. A Limit for the environmental risks of offshore activities is set by NORSOK. The following limit to determine the acceptable risk for oil platforms is derived from the quoted criterion (NORSOK; 1998).

1 - [F.sub.T](x) < 0.05/x (7)

THE MODEL OF RISK ACCEPTANCE CRITERION FOR TUNNEL AND UNDERGROUND WORKS

It is worthwhile to recognize that the criteria and calculations of risk acceptance have a fundamental and special bearing to different industries and engineering. The determination of risk acceptance criteria is a complex task which is entwined with comprehensive several courses and much technique knowledge. And there are many problems on which need to spend more research. At the present time, the study of risk acceptance criteria of risk analysis is a hot research point to which a great number of researchers pay attention in the world (M.H.Faber; 2003, Li Dianqing et al; 2003). Furthermore, it is the beginning stage of the risk analysis that is applied currently in the tunnel and underground engineering. Although it is fortunate that we have started and made some progress of the application of risk management in tunnel and underground engineering, we still have a great deal of work problems to be resolved. As explained in the above of the paper, the model of the risk acceptance criteria for tunnel and underground work is explained below.

The loss consequences of risk in tunnel and underground engineering may be mainly categorized into four types: economic loss, personnel fatalities, work time delays and the damage to environment. The unitive model of risk occurrence mechanism in tunnel and underground engineering is showed as follow (See Figure 1). Therefore, according to the above risk standards and the model, we can build up a calculation model of risk acceptance criterion for unifying the standard.

[FIGURE 1 OMITTED]

1 - [F.sub.R](x) = P(R > x) = [[integral].sup.[infinity].sub.x][f.sub.R](x)dx (8)

E(R) = [[integral].sup.[infinity].sub.0]x[f.sub.R](x)dx (9)

1 - [F.sub.R](x) < C/[x.sup.n] (10)

Where [f.sub.R](x) is the probability density function (PDF) of the risk loss per unite engineering; [F.sub.R](x) is the cumulative probability distribution function (CPDF) of t the risk loss per unite engineering, is the expected value of the risk loss, is the steepness of the limit line and the constant that determines the position of the limit line.

In order to establish the unitive model of risk acceptance criteria in detail, we should design a database, which is used for storing some risk events investigation and record data, and do some research work based on the existing risk acceptance criteria (Beacher GB et al; 1987) all over the world (See Figure 2). At the present time, we all lack the foundation data and need to do much work of investigation and collection. If we have accumulated enough useful engineering risk data and much experience, the parameter value of formula (8), (9) and (10) can be got from doing statistical study. Moreover, the relation of risk acceptance criteria and the development of national economy will be analyzed and established.

[FIGURE 2 OMITTED]

At present time, there is not a technical risk acceptance criterion for the risk analysis in tunnel and underground engineering in China. Furthermore, it is difficult to establish a new one without some basic research in the area. Therefore, in order to carry out the risk management and control and promote the future risk research in tunnel and underground engineering, it is an imperative task for all engineering risk researchers nowadays. And we can get some reference from the reliability-based design theory. The failure rate of tunnel structures can be calculated by the reliability methods considering the variability of design parameters.

Human error is an important source of risk. It is typically found that actual failure rates of engineering construction exceed predicted failure rates through the reliability methods, perhaps as much ad three orders of magnitude. Further research reveals that most of the risk events are the result if human error, for example, some structures not built according to the work plans, materials not meeting the design specification, etc. It is inherently difficult to include human errors involving design, construction, organization and management. Therefore, how to assess the human errors and whether it can be accepted that depend on the context of risk acceptance. But it is a blank research area that needs us to pay attention.

CONCLUSION AND FINAL REMARKS

The application of risk analysis into tunnel and underground engineering in China is a little later than other developed countries. The risk analysis and assessment of Yangtze Channel Tunnel in Shanghai is the first example which is began in 2002 and finished in 2003. Risk analysis is a systematical science which is composed of three main subjects: risk identification and measure, risk assessment and decision-making, and risk management and control. The core of risk in the three subjects is the risk acceptance. Risk analysis involving workers or public or nature resources or economy should be analyzed and assessed based on some risk acceptance criteria, especially when the balance of cost, benefit, risk loss and the public's concerns are to be considered. It can be difficult to perform a comprehensive and quantitative risk analysis because of the many variables involved, insufficient data, distribution of parameters and the lack of a reference base in similar types of structures. So, the application of risk management and control in tunnel and underground engineering is the beginning. And I wish the paper can push and promote the further research of the risk acceptance criteria in tunnel and underground engineering.

REFERENCES

Song Kezhi, Wang Mengshu. 2004) "Shield machine selection lining domestication," West- China Exploration Engineering, Vol.5, 99-100 (in Chinese).

Ministry of Construction, China. (2003) The report of investigation and management of risk accident of Metro No.4 in Shanghai, China. Vol. 10 (in Chinese).

M.H.Faber, M.G.Stewart. (2003) "Risk assessment for civil engineering facilities: Critical overview and discussion," Reliability Engineering and System Safety, Vol. 80, 173-184.

Hood C.C., Jones D.K.C., Pidgeon N.F., and Turner B.A., etc. (1992) Risk management, risk: analysis, perception and management. London: the royal society, 92-135.

Ohtsubo.H, Sumi Y. (2000) Committee reports on risk assessment, Proceedings of the 14th international ship and offshore structures congress. Nagasaki, Japan, Vol. 2, 1-41.

Melchers RE, Society. Tolerable and the ALARP principle. In: Melchers RE, Stewart MG, Editors. (1993) Probabilistic risk and hazard assessment. Netherlands: Balkema, 243-295.

Sharp JV, Kam JC, Birkinshaw M. (1993) Review of criteria for inspection and maintenance and artic engineering (OMAE 1993), Vol.2, New York: ASME, 363-371.

Li Dianqing, Tang Wenyong, Zhang Shengkun. (2003) Review of risk acceptance criteria for ocean engineering], The Ocean engineering, Vol.21 (5), 96-102 (in Chinese).

Ditlevsen O. (1996) Risk acceptance criteria and design/or decision optimization, 15th IABSE Congress: Structural engineering in consideration of economy, environment and energy, Copenhagen.

S. N. Jonkman, P.H.A.J.M. van Gelder and J. K. Vrijling. (2003)An overview of quantitative risk measures for loss of life and economic damage. Journal of Hazardous Materials, Vol.99 (1-4), 1-30.

A.N.Yelokhin, (1997) Complex risk analysis for Novgorodsky's region's population, in: B.-M. Drottz Sjoberg (Ed.), Proceedings of the Annual Meeting of the Society for Risk Analysis-Europe: New Risk Frontiers, Stockholm.

H.M.A. Jansen, (1988) Financieel economische risicolimiet financial economic risk limit, in Dutch), Min. van Volkshuisvesting, Ruimtelijke Ordening en Milieu, directie stralenbescherming.

D.J. Parker, C.H. Green, P.M. Thompson, Urban Flood Protection Benefits, Gower Technical Press, 1987.

H.M.Zhou, (1995) Towards an Operational Risk Assessment in Flood Alleviation, Delft University Press, ISBN 90-407-1146-1.

Hydropower & Dams, (1998) Risk Based Dam Safety Evaluations, Conference Report: Part 2, Hydropower Dams.

NORSOK, Risk and emergency preparedness, (Z-013 rev.1), Annex C: Methodology for establishment and use of environmental risk acceptance criteria, (http://www.nts.no/norsok/) 1998.

Beacher, GB, (1987) Geotechnical Risk Analysis User's Guide, FHWA/RD-87-011, Fed. Hwy. Admin.

HU QUNFANG

Department of Geotechnical Engineering, Tongji University, 1239 siping road Shanghai 200092 China

HUANG HONGWEI

Department of Geotechnical Engineering, Tongji University, 1239 siping road Shanghai 200092 China
COPYRIGHT 2005 World Scientific Publishing Co. Pte Ltd.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Author:Qunfang, Hu; Hongwei, Huang
Publication:Geotechnical Engineering for Disaster Mitigation and Rehabilitation
Article Type:Conference news
Geographic Code:9CHIN
Date:Jan 1, 2005
Words:3203
Previous Article:Iran's strategy on natural disaster risk management.
Next Article:Minimizing karst related risks in highway construction.
Topics:


Related Articles
THE BIG DIG.
What lies beneath: lawmakers introduce tunnel legislation.
Disposal of Hazardous Waste in Underground Mines.
Geotechnical aspects of underground construction in soft ground; proceedings.
Underground Construction and Ground Movement: Proceedings.
Design of hazardous mechanical structures, systems and components for extreme loads.
Holding the low ground: daunting challenges face those waging subterranean warfare.
Safety and security engineering II; proceedings.
Disposal of Hazardous Waste in Underground Mines.

Terms of use | Privacy policy | Copyright © 2021 Farlex, Inc. | Feedback | For webmasters