Making a mark.

Summary: BP has laid solid foundations at the first phase development of Khazzan gas field. Exporting Khazzans first volume of gas marks the end of a 10-year journey. An OER report

When BP achieved first gas at its Khazzan field on September 22, 2017, safely, ahead of schedule and below budget, it was one of the biggest BP start-ups anywhere in the world during the year.

The phase one development started gas production ten years after the signing of BPs production sharing contract with Oman and almost four years after the de- velopment was approved. Phase one will include a total of 200 wells feeding into a two-train Central Processing Facility (CPF), where production is expected to plateau at 1 billion cubic feet of gas per day (bcfd). When the second phase of development of the Khazzan field, known as Ghazeer, is fully on-stream total production is expected to rise to 1.5 (bcfd). In total, approximately 300 wells are expected to be drilled over the estimated lifetime of these two phases of development of the Khazzan field.

The most important stages of the huge project are horizontal and vertical wells. BP has drilled the wells across the field, laid hundreds of kilometres of pipelines and built a two-train Central Processing Facility (CPF). In addition, the company has put in place road, telecoms, water and power infrastructure and completed the construction of accommodation facilities.

The company is also able to run CPF at record time with high production. It already exports natural gas and condensate from train 1 and 2 and is looking to increase the production to one billion standard cubic feet of gas per day and 25,000 barrels per day of gas condensate.

SOLID FOUNDATION

Exporting Khazzans first volume of gas marked not only the end of a 10-year long journey to build and set up the facility, but also BPs commitment to operations in Oman for many moreyears to come. There was a clear focus on building the infrastructure to support operations roads, camps, water and power which are vitalfor continued smooth progress. The ramp-up of rigs at the start of the well drilling programme was particularly demanding in this respect, but the company overcame these challenges successfully. The infrastructure BP has put in place should only need minor additions to develop Ghazeer.

Says Mohsin Al Mahrouqi, Onshore Site Manager, Khazzan, The operations of the giant Khazzan field are divided into three main sections: the operation of well sites and gathering systems;the central processing facility; and the export systems. The most important stages of this huge project werethe drilling of the horizontal and vertical wells across the field and the construction, commissioning and startup of the Central Processing Facility (CPF). The fluid from the reservoir constitutes a mixture of gas, hydrocarbon condensate and produced water, which needs to be separated in order to achieve export quality gas and condensate, as well as proper disposal of produced water.

The fluid from the production wells is routed to the inlet of the plant (CPF) via a series of five gathering systems. At the inlet of the plant, the mixed fluid enters the finger type slug catcher where the mixed fluid is separated into three phases: gas, condensate and produced water. Gas flows at the top of the slug catcher and then enters two identical trains with a combined processing capacity of 1 billion standard cubic feet of gas per day for further processing. Here the gas undergoes various processes to remove impurities, water and heavy hydrocarbon in order to achieve export pipeline spec. Quality spec gas is then exported using 3 x gas turbine driven gas export compressors and connects in to the National gas network via a 36 gas export pipeline. The power is provided by five gas turbine generators located at the CPF.

Condensate from the bottom of the stabiliser is routed to the liquid train for stabilisation and then stored or exported to the Main Oil Line (MOL). The remaining product, water is sent to the produced water unit where it is treated for safe disposal to the water disposal wells.

The above operation is supported by associated infrastructure including a raw water treatment plant; sewage treatment plant; Khazzan operating base (KOB); the central control building (CCB) housing the central control room and two main residential complexes.

HUMAN CAPITAL

With gas now flowing through its pipelines, making sure everyone at Khazzan can work together seamlessly is critical to success. A modern complex operation like Khazzan, needs a

great deal more than just pipes and drilling rigs: it requires safety experts, geological scientists, procurement specialists, and an array of other talented staff. People are at the heart of everything BP does and so its no surprise that BPs one team value is lived by all staff working at Khazzan.

BP launched its Technicians training Development Programme in 2012. This was a great example of collaboration between the operations and learning team to support the development

of capabilities ensure everyone was ready to operate the Khazzan field. Technicians were provided with development opportunities in alignment with the programmes goals at various locations, including overseas (USA & UK). Closer to home we had different groups join Oman LNG and Oman Oil Company Exploration & Production (OOCEP) for a period of time. These opportunities provided 85 people with the appropriate technician skill sets, enabling them to commence work on the Khazzan Project.

The technicians, most of whom now have an NVQ3 qualification; as part of their Development Programme, joined Khazzan at a time when commission- ing of the plant was in progress, provid- ing them with the opportunity to get engaged in commissioning activities of the facility. This offered them a glimpse of how a well site, central processing facility and export systems are commis- sioned and started for the first time.

On her experience working at the field, Husna Al Mamari, Production Techni- cian says; I have had a very enriching experience working at the field. It is not easy, but through my work and interacting with people, I have gained more experience, knowledge and self-confidence.

Ensuring everyones safety and understanding of BPs safety standards was paramount, particularly given that so many people from varying companies and countries were working together with differing understandings towards safety practices. The issue of synchronising various stages of the workflow construction, mechanical completion, commissioning and start-up required close attention to ensure safety was maintained and effectiveness maximised.

With Phase 2 of the development due to commence in early 2018, much of what has been learned and delivered to date will be vital for continued smooth progress.

Copyright 2018 United Press & Publishing LLC Provided by SyndiGate Media Inc. ( Syndigate.info ).
COPYRIGHT 2018 SyndiGate Media Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2018 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Oman Economic Review (OER)
Geographic Code:7OMAN
Date:Feb 20, 2018
Words:1116
Previous Article:TAPPING NEW POTENTIAL.
Next Article:POISED FOR REVIVAL.
Topics:

Terms of use | Privacy policy | Copyright © 2019 Farlex, Inc. | Feedback | For webmasters