Perth, Australia, Jan 22, 2014 - (ABN Newswire) - Australian based iron ore development company, Kogi Iron Limited (ASX:KFE) ("Kogi", "Kogi Iron", or the "Company") and its 100% owned Nigerian operating company, KCM Mining Limited ("KCM"), are pleased to report the results of a recently completed optimisation of its Niger River Barging Study.

Niger River Barging Study

On 14 October 2013 the Company announced the results of the Niger River Barging Study, which was conducted by South African port and costal engineering consultants Prestedge Retief Dresner Wijnberg (Pty) Ltd ("PRDW"). The study investigated the feasibility of using river barges to transport iron ore concentrate from the Company's Agbaja Project via the Niger River to the Gulf of Guinea, then transhipment to large ocean going vessels ("OGVs"). The study concluded that river barging and transhipment was feasible and an economic transport option. The study recommended that iron ore concentrate be initially transported by river barge from a barge loading location south of Banda on the Niger River to the established port of Warri in the Gulf of Guinea where existing port infrastructure would be used to stockpile then re-load the concentrate onto a separate fleet of deeper draft ocean going barges for transhipment to OGVs moored offshore.

As part of the current Preliminary Feasibility Study ("PFS"), PRDW in conjunction with engineering consultants Wilson, Campbell & Associates ("WCA") have completed an optimisation of the Niger River Barging Study. The optimisation has resulted in the removal of the proposed re-handle of iron ore concentrate at Port Warri, bringing about a reduction in capital and operating cost estimates. The previously contemplated Port Warri stockpile and re-handle will be replaced with a river barge to ocean going barge transfer station at Escravos, in the Niger River delta ("Escravos Transfer Station").

Optimised PFS Transport Solution

The optimised transport solution involves iron ore concentrate being pumped from the Agbaja Plateau down to the Banda barge loading facility (located on the west bank of the Niger River close to Banda), a distance of ~22 km. The concentrate will then be filtered to reduce the moisture content to less than 10% and conveyed to a covered stockpile.

Barge loading from the stockpile will take place using a travelling, luffing, telescoping barge loader filling Mississippitype barges in a four barge configuration.

Each barge configuration will have dimensions of 21m by 286m long and are designed to carry loads of 4,800t to 8,000t, depending on river water levels. A configuration will be propelled by shallow draft four engine push boats with a preferred speed of 10 knots. Iron ore concentrate will be transported ~ 602km from Banda along the Niger River to the Escravos Transfer Station, a journey time of ~33 hours.

At the Escravos Transfer Station the concentrate will be transferred to a 20,000t ocean going sea barge. A stockpile arrangement (twin storage domes) may be required to ensure that each river barge configuration can be unloaded while the large ocean barge is travelling to the transhipment facility. The Escravos stockpile will allow the ocean barge to be loaded at a rate of 4,000t/hr and will minimise loading wait times and river barge cycles.

The 20,000t self-propelled and self-unloading ocean going barge will be capable of transferring the concentrate to a floating transhipment storage facility in the Gulf of Guinea approximately 33km offshore. The floating transhipment facility will have a storage capacity of 200,000t and allow for the loading of Panamax and Cape size OGV's for global export markets.

Estimated Barging Costs

As part of the PFS, barging costs have been estimated to include the loading of river barges at Banda, river travel, transfer costs at Escravos, ocean travel to the floating transhipment facility, subsequent loading of OGV's and owner operating costs. The Free on Board (FOB) operating cost estimate including the lease of river and ocean barges, as well as the transhipment facility and owners costs is detailed in Table 1.

Table 1

Kogi Iron Managing Director Iggy Tan said: "The Company is pleased with the outcome of the barging optimisation work which demonstrates that barging transportation of iron ore concentrate is not only a readily available and effective transport solution, but a most economic option. Barging is widely accepted as a lower cost form of bulk commodity transport compared to both rail and trucking, so the proximity of river transport remains a unique competitive advantage of the Agbaja Iron Ore Project. Our estimated FOB transport cost of just under 3 cents/tonne per kilometre, or around $19.00 per tonne of concentrate, puts us in good stead for a highly competitive overall operating cost estimate in our PFS."

To view diagrams, please visit:

http://media.abnnewswire.net/media/en/docs/ASX-KFE-664718.pdf

About Kogi Iron Limited:

Kogi Iron Limited ("Kogi Iron" or the "Company") is an ASX listed company focused on being an African iron ore producer through the development of its 100% owned Agbaja iron ore project located in Kogi State, Republic of Nigeria, West Africa ("Agbaja" or "Agbaja Project").

In recent years Nigeria has sought to diversify its economy, which is dominated by hydrocarbons, into minerals and related industries. Nigeria is the largest country by population in Africa. Nigeria had a GDP real growth rate of 7.2% in 2011, and in 2007 passed a new Mining and Minerals Act, which includes favourable fiscal terms for foreign investment in mining.

The Company holds a land position of approximately 400km2 covering 15 tenements, with the main focus being EL12124 covering most of the Agbaja Plateau. The Agbaja Plateau hosts an extensive, shallow, flat-lying channel iron deposit with an Inferred Mineral Resource of 488 million tonnes with an in-situ iron grade of 42.7% reported in accordance with the JORC Code. This mineral resource comprises approximately 20% of the prospective Agbaja plateau area within EL12124. The Agbaja Project is uniquely positioned with transport infrastructure access to Warri port via an existing and underutilised standard gauge railway, and the Niger River for barging.

Copyright 2014 ABN Newswire Provided by Syndigate.info , an Albawaba.com company
COPYRIGHT 2014 Al Bawaba (Middle East) Ltd.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2014 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:ABN Newswire
Date:Jan 23, 2014
Words:1010
Previous Article:Tiger Resources Limited (ASX:TGS) Boosts Kipoi NPV 100% to US$755M for Stage 2.
Next Article:Besra Gold Inc. (ASX:BEZ) Announces Stage One Feasibility for Bau Gold Project in East Malaysia.
Topics:

Terms of use | Privacy policy | Copyright © 2021 Farlex, Inc. | Feedback | For webmasters |