B-292997 January 15, 2004

Protest:

Kaman Dayron, Inc. protests the award of a contract to AMTEC Corporation by the Department of the Army, U.S. Army Joint Munitions Command, under request for proposals (RFP) No. DAAA-09-03-R-0002, for M549A1 40-millimeter (mm) grenade fuzes. Kaman Dayron, the incumbent contractor, challenges the technical evaluation primarily on the basis that the agency unreasonably considered Kaman Dayron's experience and that of AMTEC to be equal.

Decision:

We sustain the protest

Decision Summary:

Protest is sustained where, under a solicitation that indicated that when rating proposals under the technical evaluation factor particular importance would be placed on the similarity of the items previously produced to the grenade fuze being procured, the record does not support the agency's ultimate determination that the awardee's experience producing part of a different fuze was nearly identical to the experience of the protester in producing the fuze being procured here such that both offerors were entitled to the same "excellent" rating.
COPYRIGHT 2004 Stonehenge International
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2004 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:General Accounting Office Reports & Testimony
Date:Aug 1, 2004
Words:160
Previous Article:ViroMed Laboratories, Inc.
Next Article:Paradise Landscape Maintenance, Inc.


Related Articles
Auxiliary Equipment and Supplies.
Index of capabilities.
2/Auxiliary equipment and supplies.
NDIA corporate: index of capabilities.
NDIA corporate index of capabilities.

Terms of use | Privacy policy | Copyright © 2021 Farlex, Inc. | Feedback | For webmasters |