Illinois Tollway Lane Closure Application: Illinois State Toll Highway Authority.

A. SYSTEM

1. Name of system and ESIG category for which you are applying. Illinois Tollway Lane Closure Application for consideration in the Enterprise System ESIG award category.

2. A letter from the executive administrator authorizing submission of the system application. Please see Appendix A.

3. One page, or less, summary of what the system accomplishes and why it is exemplary. Lane closures allow the Illinois Tollway to perform maintenance and provide improvements to the Tollway infrastructure in a safe and efficient manner. Before the introduction of the Lane Closure Application, lane closures were handled in a time consuming, labor intensive, paper-based process. The Lane Closure Application offers a Geographic Information System based system to manage lane closures. The Application provides spatially based analysis and approval of requested lane closures within the Illinois Tollway. In addition, the Lane Closure Application distributes the workload for closure approvals.

4. Three "user testimonials."

Please see Appendix B.

B. JURISDICTION

1. Name of jurisdiction Illinois State Toll Highway Authority

2. Population served by the organization/agency The combined population of the counties containing the Illinois Tollway is 8.85 million.

3. Annual total budget for jurisdiction The Illinois State Toll Highway Authority's budget for 2006 is $1.2 billion.

4. Name, title, and address of chief elected and/or appointed official.

Mr. Jack Hartman

Executive Director

Illinois Tollway

2700 Ogden Avenue

Downers Grove, IL 60515

5. Name, title, address, telephone, FAX, and email for contact person for system

Mr. Rocco Zucchero

Deputy Chief of Engineering for Planning

The Illinois State Toll Highway

Downers Grove, IL 60515

Phone: 630-241-6800 ext. 3909

Fax: (630) 241-6100

T.T.Y: 630-241-6898

Email: rzucchero@getipass.com

C. SYSTEM DESIGN

1. What motivated the system development?

Prior to the Lane Closure Application's introduction, the Tollway's analysis and approval procedures were paper-based in their nature. Requests were submitted with a written form directly, or via fax. The viability of a lane closure was then determined by a single, knowledgeable individual. This individual's detailed knowledge of the Tollway system served as the primary means of lane closure analysis and approval. The system worked well, but there was obvious room for improvement. Various systems at the Tollway had been markedly improved through GIS integration, including the American Council of Engineering Companies of Illinois award winning I-Plans document management system. Lane closure request analysis and approval seemed to be another system that could benefit through the use of a GIS.

The automation and spatial analysis of the lane closure system was motivated by three factors: The need to manage a larger number of closures (due to Illinois Open Road Tolling Projects), the desire to distribute the workload among Tollway personnel, and the need to create a system with fewer limitations of request submission requirements.

2. What special service or services was the system intended to improve?

The Lane Closure Application improved or introduced the following services:

Closure request process

The lane closure request process was dramatically improved. Prior to the Lane Closure Application's introduction, lane closures were submitted daily, no matter how long the closure was scheduled to last. Each closure was then approved, re-approved or denied. This required extensive, repetitive work for extended closures. Planning was also difficult for those whose work was conducted in or near the closed lanes; the possibility existed that a closure would be denied. The Lane Closure Application now allows for requests to be submitted up to one week in advance and to run for multiple days.

Analysis capabilities

The GIS basis of the Lane Closure Application allows the system to automatically analyze requested closures for both feasibility and traffic impact associated with ADT volumes and possible conflicts for special events (such as major summer events in the Chicago region). The system will allow Tollway personnel to flag closures that would pose a significant traffic flow problem. Personnel can place flags through an interactive map interface. The application will immediately deny the flagged impending closures.

Distribution of closure information

The Lane Closure Application is capable of e-mailing a list of closures to an approved group of internal Tollway personnel, police departments and members of the media. The updated lane closure information is also posted to the Tollway's automated Traffic Information Management Staff (TIMS) for use in traffic management and monitoring operations. The application provides Internal Tollway staff access to real-time mapping of closures and approved closure reports.

Potential public access to closure information

The Lane Closure Application was designed to allow closure information to be easily accessible from a public website. When all closures for the day have been approved, an XML document is generated. The XML document can be easily published on a website or as an RSS stream. The Tollway has plans to utilize this information to make a public lane closure website operational during Phase 2 of the project this summer.

3. What, if any, unexpected benefits did you achieve?

Tollway maintenance staff members are able to use the Lane Closure Application to submit their own closures. The map-based submittal form helped maintenance staff to perform their own pre-request analyses. Staff members were able to visualize and then modify closure requests to make them acceptable based on lane configuration, as well as other lane closures, prior to formally submitting them for review, saving time and providing a more accurate request.

4. What system design problems were encountered?

Web-based functionality was designed to allow for external access to closure information, and to allow contractors to request lane closures for construction work. However, the Illinois Tollway does not have external hosting capabilities, and therefore the site was not made available to the general public.

5. What differentiates this system from other similar systems?

The Lane Closure Application is unique in its ability to combine mapping and analysis to provide a spatial view component for approval decisions of requested closure approvals. In addition, the Lane Closure Application distributes the workload for closure approvals. The tasks of requesting closures, approving closures, publication of closure details and data entry have been dispersed from one very busy individual to fifteen system users. The new group of users ensures that lane closures occur quickly, with real-time analysis of the closure impact.

IMPLEMENTATION

1. What phases did you go through in developing the system?

System development included:

* Preliminary system requirement determination

* Preliminary system design

* Final system design or System Requirement Specification (SRS)

* Final system requirement specification or Task Order

* System development

* System demonstration and acceptance by Tollway operations staff with a live prototype

* Final changes to the application from comments received from the prototype

* Installation of the application at the Tollway--further System testing

* User training--Near 50 individuals took part in the training

* Go live with the application

* Support

2. Were there any modifications to the original system design? Why? What?

After initial user testing, the Lane Administration interface was changed from a purely text-based system to a text and graphic-based system. The number of lanes, their direction, and the proposed closure are displayed in a graphic accompanying the Lane Administration menu.

Tollway operations staff members are assigned roles within the application based upon authority to request, monitor, and approve or deny lane closures. Tollway staff use their current user names and permissions within the Tollway's Windows security system via Active Directory Services (ADS). The application does not require a user sign-on page to access the system, but simply allows Tollway staff to access the application and complete work within the tool based upon roles assigned in ADS. Based upon these roles, users see certain information within the application and can make changes or query the status of a closure.

ORGANIZATION IMPACT

1. What user community does the system serve and how?

The Lane Closure Application serves the following communities:

* Lane Closure Management Personnel--Those responsible for approving lane closures now have a web-based tool that provides access to more information and a visual representation of requested closures. These features allow for more immediate, in-depth analysis of each request.

* Maintenance staff--Maintenance staff now have the ability to manage their own closure requests.

* Tollway internal staff and Traffic Information Management Staff (TIMS) Tollway employees can easily access the Lane Closure Application to review closures. Internal staff also receives e-mail detailing all closures.

* The police and media--Both groups receive lane closure e-mail bulletins.

2. What are the ultimate decisions/operations/services being affected? If appropriate, provide a few examples including, but not limited to: screen input/output forms, paper products, or other descriptive graphics.

There are a large number of process decisions, operations, and services that are being affected by the implementation of the Lane Closure Application.

The process of creating the daily temporary and long-term closure report that is e-mailed and posted on the Tollway website has been completely provided within the application. Also, the decision to produce the report has been affected by allowing the dispersion of the approval process, the visualization in a map (lane level) of requested closures, and the ability to view current events and ADT data when submitting or approving a closure. (Please see Appendix C for an example of Lane Closure Report and Figure 3 for a list of closures and Figure 4 for an example of the approved closure map)

The Lane Closure Application has been set up to automate the process of retrieving the closure report and inserting the information as new events into the TIMS system through an XML output.

The operation of requesting a closure has been automated such that an internal Tollway user can enter a lane closure without being constrained to the XML output following day. Users can select from an existing closure for a new request in addition to requesting the same closure over multiple days. (Please see Appendix D for the Lane Closure Request Guide and Figure 5 for the lane closure request menu)

3. What were the quantitative and qualitative impacts of the system?

The impacts of the lane closure system are shown in two major areas:

* Greater depth of analysis allows for improved closure approval leading to increased roadway safety

* The distributed web-based system allows for productivity gains in the form of reduced staff time for the approval request process

The greater depth of analysis of lane closure approvals allows the Tollway to make more accurate decisions to limit non-effective closures. Allowing closures that are spaced too closely together, at the wrong time of day, or independent from information on other existing closures and events can cause major traffic flow problems. The Lane Closure Application provides tools to limit these improper closures. Decreased traffic flow problems results in the increase of traffic safety for the driving public. Safety is the largest goal of the Illinois Tollway; by decreasing traffic congestion, the Lane Closure application is helping to achieve this goal.

The productivity gains from the Lane Closure application are seen in the form of reduced time required for the approval process. The lane closure report originally took until about 2:00 or 3:00 pm to create on a normal weekday. Using the Lane Closure Application, the lane closure report can be created before 10:00 am. The maintenance staff and Project Coordination Liason (PCL) can now request Open Road Tollway closures (35% of total lane closures) more than a day in advance, allowing the staff to request an entire week of closures in consecutive operations instead of making the same request daily. This can save the PCL and Maintenance staff (a total of 44 individuals) from 2 to 4 hours a week.

4. What effect has the system had on productivity?

The productivity of Tollway staff has greatly improved as a result of the application. Before the introduction of the Lane Closure Application, details regarding closures were determined, transcribed, disseminated via mail or fax, and, in some cases, transcribed again. The Lane Closure Application produces closure information in digital format, removing the need for transcription, and disseminated automatically.

As an additional benefit, the Lane Closure Application provides immediate feedback regarding requested closures. Such feedback allows for project planning based on closure approvals to begin immediately. Affected staff no longer must wait to make sure that their closure is approved.

5. What, if any, other impacts has the system had?

The Lane Closure Application Empowers Tollway staff to have a role in lane closure operations including the maintenance department that had limited roles with regard to this issue.

The Lane Closure Application continues to further disseminate GIS technology throughout the Tollway's operations. This project is another example of GIS addressing a real world problem in a comprehensive manner.

6. How did the system change the way business is conducted with and/or service delivered to clients? Give specific examples comparing the old way with the new.

The Lane Closure Application was able to change the way the Tollway distributes closure approvals, and created more stringent rule-based policies on summiting closure requests. Now, requests can be submitted remotely, when in the past paper forms had to be hand-delivered to a specific individual at the Tollway main office.

SYSTEM RESOURCES

1. What are the system's primary hardware components? Give a brief list or description of the hardware configuration supporting the system.

The application uses a separate ArcGIS Server configuration using a SQL Server cluster for a backend database and for holding the ArcSDE data repository. The application currently does not reach outside of the Tollway's firewall via the Internet.

[ILLUSTRATION OMITTED]

2. What are the system's primary software components? Describe the primary software and, if a commercial package, any customizations required for the system.

The application uses ESRI ArcGIS Server as the primary platform for the application code. ArcSDE was also used to manage the GIS data layers required for the application.

3. What data does the system work with? List and briefly describe the database(s).

The application uses the Tollway's ArcSDE data repository for all GIS data layers. The lane closures use event layers to map current existing and proposed lane closures based upon the current roadway configurations (number of lanes at each mile maker, toll plazas and highway ramp location, etc.). The application also uses a SQL Server database to maintain other required business data associated with the application, including ADT data and special event tracking.

4. What staff resources were required to implement the system (i.e., report approximate staff and consultant time as FTE's)?

Implementation of the Lane Closure Application required 0.5 FTE's.

[FIGURE 1 OMITTED]

[FIGURE 2 OMITTED]

[FIGURE 3 OMITTED]

[FIGURE 4 OMITTED]

[FIGURE 5 OMITTED]

[ILLUSTRATIONS OMITTED]
TOLLWAY TEMPORARY LANE / SHOULDER CLOSURES

Maint. bldg. or
Contract # and
Description MP. DIR & NEAREST CROSSROADS REASON

Thursday nite - Friday, May 19, 2006 OVERNIGHT CLOSURE

Tri-State Tollway (I -94/294)

5153: IDOT Ramp 0.0 - 2.0 SB: between IL 394 Pavement Striping
Replcmnt & Thornton Quarry

[??] [??] [??]

8939: Rdwy 0.1 - 0.2 NB: between Grand Barrier Wall
Widening Trunk RR & Thorn Creek Relocate

[??] [??] [??]

5316: ORT 5.2 - 5.8 NB: between I-80 Sawcutting
 Flyover & 163rd St Plaza

5316: ORT 5.8 - 6.5 SB: between 159th Sawcutting
 St & 163rd St Plaza

5336: ORT 19.5 NB: 83rd St Plaza Sign structure
 relocation

5336: ORT ONE 15 minute NB FULL CLOSURE with Trooper
 Assistance

5336: ORT 20.5 - 21.1 NB: between Sign structure
 Archer Ave & Mile Long erection
 Bridge

5336: ORT 20.8 - 22.0 SB: between Sign structure
 LaGrange Rd & Mile Long erection
 Bridge

5336: ORT THREE 15 minute SB FULL CLOSURES with Trooper
 Assistance

5335: ORT 30.0 - 30.2 NB: N of Cermak Pavement striping
 Plaza

5335: ORT 30.0 - 30.2 NB: N of Cermak Pavement striping
 Plaza

5335: ORT 30.2 - 30.9 NB: between Pavement striping
 Cermak Plaza & I -290

M-02: 35.0 - 33.8 SB: Grand Av to Crack Sealing
Maintenance [??] Lake St

5310: ORT 72.5 - 73.5 NB: S of Sign Truss
 Wadsworth Rd Work/Inspection

Northwest Tollway (I -90)

5338: ORT 0.0 - 0.5 EB: between E Canopy Demo
 River Rd & River Rd Plaza

5151R: Bridge 35.4 - 36.9 WB: E of US 20 Bridge deck removal
Reconstruction

5151R: Bridge 36.5 - 38.0 EB: W of US 20 Bridge deck removal
Reconstruction

IDOT 64594: 67.0 - 73.0 WB: between Shoulder repair
Roadway and Riverside Rd & Burr Oak Rd
Bridge Widening

North-South Tollway (I -355)

7705: I -355 South 12.3 - 13.6 NB: between I-55 Shoulder
Extension & Boughton Rd resurfacing

Reagan Memorial Tollway (I -88)

5342: ORT 138.8 WB: Entrance Ramp Asphalt paving
 from NB I-294

5342: ORT 138.7 - 138.6 WB: E of Asphalt paving
 York Rd Plaza

5342: ORT 138.3 - 138.1 EB/WB: E & W Asphalt paving
 of York Rd Plaza

5342: ORT 135.7 - 134.9 EB: E & W of Barrier wall
 Meyers Rd removal

5342: ORT 135.7 - 134.9 EB: E & W of Barrier wall
 Meyers Rd removal

5198: Rdwy 123.7 - 122.0 EB: E & W of Pavement repairs
Widening IL 59

5342: ORT 110.8 - 109.0 EB/WB: E & W Pick up barrier
 of IL 47 wall

Friday, May 19, 2006 DAYTIME CLOSURE

Tri-State Tollway (I -94/294)

8939: Rdwy 1.1 SB: exit ramp to Noise Wall
Widening Lincoln Oasis Construction

8939: Rdwy 2.9 SB: entrance ramp from Load and Unloading
Widening Halsted St dump trucks

M-01: Maintenance 17.4 - 17.5 SB: 95th st to Shoulder Paving
 Harlem ave.

M-03: for 5410 49.0 - 49.1 SB: WILLOW RD. Soil Borings

5310: ORT 73.0 - 73.5 SB: S of Barrier wall
 Waukegan Plaza installation

5310: ORT 73.0 - 73.5 SB: S of Barrier wall
 Waukegan Plaza installation

Northwest Tollway (I -90)

5406: Survey [??] 61.4 - 68.4 EB: between Survey
 Newburg Rd & Rock Cut State
 Pk Rd

North-South Tollway (I -355)

M-14: Maintenance 20.8 - 21.1 NB/SB: Finley Bridge inspection

Reagan Memorial Tollway (I -88)

LR-00- 01: Adesta: 132.0 - 130.2 EB: between Fiber Optic Work
for 5118 Finley Rd & IL 53

M-08: Maintenance 123.4 WB: Rt.59 -C-ramp Shoulder Paving

5146: Bridge 113.3 WB: exit ramp to IL 56 Pavement Striping
Rehabilitation

5146: Bridge 113.3 WB: exit ramp to IL 56 Pavement Striping
Rehabilitation

Permit: EW-05-16: 78.5 - 76.0 EB/WB: between ComEd overhead
ComEd I-39 & IL 251 electrical work

Permit: EW-05-16: One 15 minute Full Closure with Trooper assistance
ComEd

M-12: Maintenance 69.4 - 69.5 EB: Between Ditch Line Cleaning
 Ashton Rd and Meridian Rd

Friday nite - Saturday, May 20, 2006 OVERNIGHT CLOSURE

Tri-State Tollway (I -94/294)

8939: Rdwy 0.2 - 4.0 SB: between Thorn Shoulder paving
Widening Creek & Markham Yard

8939: Rdwy 2.0 - 4.0 SB: between Barrier Wall
Widening Thornton Quarry & Markham Relocate
 Yard

5316: ORT 5.2 - 5.8 NB: between I-80 Cable installation
 Floyover & 163rd St Plaza

5316: ORT 5.8 - 6.5 SB: between I59th Cable installation
 St & 163rd St Plaza

5336: ORT 18.8 - 20.3 NB: between 87th ETC camera work
 St & 88th Ave

5336: ORT 18.8 - 20.3 NB: between 87th ETC camera work
 St & 88th Ave

5336: ORT 20.5 - 21.1 NB: between Sign
 Archer Ave & Mile Long Installation/Repair
 Bridge

5336: ORT 20.8 - 22.0 SB: between Sign
 LaGrange Rd & Mile Long Installation/Repair
 Bridge

5336: ORT THREE 15 minute SB FULL CLOSURES with Trooper
 Assistance

5335: ORT 29.6 - 30.9 SB: between Covering signs
 Cermak Rd & I- 290

5335: ORT 29.6 - 30.1 NB: between Pavement striping
 Cermak Rd & Cermak Plaza

5335: ORT 29.6 - 30.1 NB: between Pavement striping
 Cermak Rd & Cermak Plaza

Northwest Tollway (I -90)

5151R: Bridge 35.4 - 36.9 WB: E of US 20 Bridge deck removal
Reconstruction

5151R: Bridge 36.5 - 38.0 EB: W of US 20 Bridge deck removal
Reconstruction

Reagan Memorial Tollway (I -88)

5198: Rdwy 123.7 - 122.0 EB: E & W of Pavement Repair
Widening IL 59

Maint. bldg. or
Contract # and
Description Lanes Closed Lanes Open HOURS

Thursday nite - Friday, May 19, 2006 OVERNIGHT CLOSURE

Tri-State Tollway (I -94/294)

5153: IDOT Ramp Left & Right Center Lane 11pm - 5am
Replcmnt Only

[??] [??] [??] [??]

8939: Rdwy Left Lane Right Lane, 10pm - 3am
Widening Center

[??] [??] [??] [??]

5316: ORT Left Lane, All Other 8pm - 10pm
 IPX lanes Lanes

5316: ORT Left Lane, All Other 8pm - 10pm
 IPX lanes Lanes

5336: ORT All ORT lanes All plaza Midnight -
 lanes 12:30am

5336: ORT between
 Midnight -
 12:30am

5336: ORT Two Left Lanes Two Right Midnight - 4am
 Lanes

5336: ORT Three Right Far Left Lane Midnight - 5am
 Lanes

5336: ORT between
 1am - 3am

5335: ORT Left Local All Other 8pm - Midnight
 Lanes

5335: ORT Right Local All Other Midnight - 5am
 Lanes

5335: ORT Far Right Lane Three Left
 Lanes 8pm - 5am

M-02: Two Right Two Left Lanes 11pm - 5am
Maintenance [??] Lanes

5310: ORT Two Left Lanes Right Lane 11pm - 2am
 Only

Northwest Tollway (I -90)

5338: ORT Right Manual All Other 10pm - 5am
 Lane Lanes

5151R: Bridge Right Lane Left Lane 8pm - 5am
Reconstruction

5151R: Bridge Right Lane Left Lane 8pm - 5am
Reconstruction

IDOT 64594: Right Lane Left Lane 3am - 7am
Roadway and
Bridge Widening

North-South Tollway (I -355)

7705: I -355 South Left Lane Right Lane 9pm - 5am
Extension

Reagan Memorial Tollway (I -88)

5342: ORT Right Side Left Side Ramp 8pm - 5am
 Ramp

5342: ORT Right Lane Two Left Lanes 8pm - 5am

5342: ORT Right Lane Two Left Lanes 8pm - Midnight

5342: ORT Right Lane Two Left Lanes 8pm - Midnight

5342: ORT Two Right Left Lane Only Midnight - 5am
 Lanes

5198: Rdwy Two Left Lanes Right Lane 8pm - 4am
Widening Only

5342: ORT Right Lane Left Lane 6pm - 5am

Friday, May 19, 2006 DAYTIME CLOSURE

Tri-State Tollway (I -94/294)

8939: Rdwy Right shoulder Ramp Open 5am - 5pm
Widening

8939: Rdwy Right shoulder Ramp Open 5am - 5pm
Widening

M-01: Maintenance Right shoulder All Lanes Open 9am - 2pm

M-03: for 5410 Right shoulder All Other 9am - 3pm
 Lanes

5310: ORT Right Lane Two Left Lanes 7am - 11am

5310: ORT Left Lane Two Right 11am - 3pm
 Lanes

Northwest Tollway (I -90)

5406: Survey [??] Left Lane Right Lane 9am - 3pm

North-South Tollway (I -355)

M-14: Maintenance Left shoulder, All Other 9am - 2pm
 Right shoulder Lanes

Reagan Memorial Tollway (I -88)

LR-00- 01: Adesta: Right shoulder All Lanes Open 9am - 5pm
for 5118

M-08: Maintenance Left Side Ramp Right Side 9am - 2pm
 Ramp

5146: Bridge Left Lane Right Lane 7am - Noon
Rehabilitation

5146: Bridge Right Lane Left Lane Noon - 3pm
Rehabilitation

Permit: EW-05-16: Right Lane Left Lane 8:30am - 10am
ComEd

Permit: EW-05-16: between
ComEd 9am - 9:30am

M-12: Maintenance Right shoulder All Other 8am - 2pm
 Lanes

Friday nite - Saturday, May 20, 2006 OVERNIGHT CLOSURE

Tri-State Tollway (I -94/294)

8939: Rdwy Left Lane Two Right 9:30pm - 6am
Widening Lanes

8939: Rdwy Left Lane, Right Lane 11pm - 6am
Widening Center Lane Only

5316: ORT Left Lane, All Other 10pm -
 IPX lanes Lanes Midnight

5316: ORT Left Lane, All Other 10pm -
 IPX lanes Lanes Midnight

5336: ORT ORT Lane 2 All Other 8pm - Midnight
 Lanes

5336: ORT All ORT lanes All Other Midnight - 6am
 Lanes

5336: ORT Two Left Lanes Two Right Midnight - 4am
 Lanes

5336: ORT Three Right Far Left Lane Midnight - 5am
 Lanes

5336: ORT between
 1am - 3am

5335: ORT Far Right Lane Three Left 10pm - 5am
 Lanes

5335: ORT Right Approach All Other 10pm - 2am
 Lane Lanes

5335: ORT Left Approach All Other 2am - 6:30am
 Lane Lanes

Northwest Tollway (I -90)

5151R: Bridge Left Lane Right Lane 8pm - 5am
Reconstruction

5151R: Bridge Left Lane Right Lane 8pm - 5am
Reconstruction

Reagan Memorial Tollway (I -88)

5198: Rdwy Left Lane, Right Lane 8pm - 5am
Widening Center Lane Only

ALL TEMPORARY CLOSURES ARE SUBJECT TO WEATHER CONDITIONS

**** Remember to also reference the LONG-TERM CLOSURE report.
Closures that last more than one day may not always be reported
in the TEMPORARY LANE CLOSURE report ****

TOLLWAY LONG-TERM LANE/SHOULDER CLOSURES as of May 18, 2006

Maint. bldg. or
Contract # and
Description MP. DIR & NEAREST CROSSROADS REASON

Tri-State Tollway (I -94/294)

8939: Roadway 0.0 - 1.1 NB: between IL 394 Pavement and Bridge
and Bridge & Lincoln Oasis Widening
Widening

8939: Roadway 0.0 - 1.1 SB: between IL 394 Pavement and Bridge
and Bridge & Lincoln Oasis Widening
Widening

8939: Roadway 1.1 - 3.4 SB: between Pavement and Bridge
and Bridge Lincoln Oasis & Center St Widening
Widening

8939: Roadway 1.1 - 3.6 NB: between Pavement and Bridge
and Bridge Lincoln Oasis & Ashland Widening
Widening

8939: Roadway 3.4 - 3.6 SB: between Center Pavement and Bridge
and Bridge Street and Ashland Widening
Widening

8940: Bridge 3.6 - 4.1 NB: between W or Bridge Widening
Widening Center St & Markham Yard

8940: Bridge 3.6 - 4.1 SB: between W of Bridge Widening
Widening Center St & Markham Yard

8941: Roadway 4.1 - 5.3 NB: between Pavement and Bridge
Widening Markham & I -80 flyover Widening

8941: Roadway 4.1 - 5.3 SB: between Pavement and Bridge
and Bridge Markham Yard & I -80 flyover Widening
Widening

8941: Roadway 4.2 - 4.2 NB: entrance ramp Pavement and Bridge
and Bridge from Wood St Widening
Widening

8941: Roadway 4.5 - 4.5 SB: exit ramp to Pavement and Bridge
and Bridge Dixie Hwy Widening
Widening

8941: Roadway 5.1 - 5.2 SB: EB I -80 Plaza
Widening Plaza (45) Reconfiguration

5336: ORT 19.5 NB: 83rd St Plaza (39) Plaza
 Reconfiguration

5336: ORT 19.8 SB: 82nd St Plaza (36) Plaza
 Reconfiguration

 Pavement & Shoulder
5335: ORT 29.2 - 29.8 SB: between
 I -88 & Cermak Rd Replacement

5335: ORT 29.2 - 29.8 NB: between Pavement & Shoulder
 I -88 to Cermak Rd Replacement

5335: ORT 29.6 NB: Entrance from Ramp Construction
 Cermak Rd

5335: ORT 29.6 SB: Exit from from Ramp Construction
 SB I -294

5335: ORT 30.0 - 30.6 NB: between Landscaping
 Cermak Plaza & Roosevelt Rd

5334: ORT 30.0 - 40.0 SB: between Pavement
 Irving Pk Plaza & Balmoral Reconstruction

5334: ORT 39.0 - 40.0 SB: between Sign Truss
 Lawrence & Balmoral Work/Inspection

5337: ORT 40.9 SB: Exit ramp to WB Pavement
 I -90 Northwest Tollway Reconstruction

5337: ORT 40.9 NB: Exit ramp to WB Pavement
 I -90 Northwest Tollway Reconstruction

5338: ORT 40.9 SB: Exit ramp to EB Barrier wall for
 I -90 Kennedy Expy ORT conversion

5310: ORT 73.5 NB: Waukegan Plaza Sawcutting

5310: ORT 73.5 SB: Waukegan Plaza Plaza
 Reconfiguration

Northwest Tollway (I -90)

5301: ORT 24.2 EB/WB: Exit ramps to Ramp Construction
 SB IL 31

5301: ORT 24.2 WB: entrance ramps Ramp Construction
 from SB IL 31

5301: ORT 25.0 EB/WB: Elgin Plaza (9) Toll lane
 conversions

5301: ORT 25.0 EB: Elgin Plaza Truss erection

5151R: Bridge 36.5 - 36.9 EB/WB: E & W of Bridge
Reconstruction US 20 overpass Reconstruction

5151R: Bridge 36.7 EB: entrance ramp from Bridge demolition
Reconstruction US 20

5368: ORT 39.8 - 41.7 EB: E & W of Plaza
 Marengo Plaza (7) Reconfiguration

5368: ORT 39.8 - 41.7 WB: E & W of Plaza
 Marengo Plaza (7) Reconfiguration

5340: ORT 55.0 - 55.7 EB: E & W of Plaza
 Belvidere Plaza (5) Reconfiguration

5340: ORT 55.0 - 55.7 WB: E & W of Plaza
 Belvidere Plaza (5) Reconfiguration

5339: ORT 74.1 - 76.1 WB: between Plaza
 McCurry Rd & Rockton Rd Reconfiguration

5339: ORT 75.5 - 76.1 EB: between Plaza
 Beloit Plaza & Rockton Rd Reconfiguration

5339: ORT 75.5 EB: S Beloit Plaza (1) Plaza
 Reconfiguration

5339: ORT 75.5 WB: S Beloit Plaza (1) Plaza

North-South Tollway (I -355) Reconfiguration

7705: I -355 12.3 - 12.4 SB: exit ramp Drain
Extension to IB I -55 Repair/Cleaning

7705: I -355 12.3 - 12.4 NB: entrance Drain
Extension ramp from IB I -55 Repair/Cleaning

7705: I -355 12.3 - 12.4 NB: entrance Drain
Extension ramp from OB I -55 Repair/Cleaning

7711: I -355 12.3 - 12.4 SB: exit ramp Pier Construction
Extension to OB I -55

7705: I -355 South 12.3 - 13.6 NB: between Ramp Construction
Extension I -55 & Boughton Rd

7711: I -355 12.4 - 12.5 SB: exit ramp Retaining Wall
Extension to OB I -55 Construction

7705: I -355 12.7 - 13.4 NB/SB: between Pavement and Bridge
Extension I -55 & Boughton Rd Widening

Reagan Memorial Tollway (I -88)

5342: ORT 138.7 - 138.6 WB: E of Asphalt paving
 York Rd Plaza

5342: ORT 138.3 - 138.1 EB/WB: E & W Asphalt paving
 of York Rd Plaza

5342: ORT 136.5 EB: Entrance ramp from Remove & replace
 Midwest Rd ramp

5342: ORT 133.7 - 134.6 EB/WB: W & E Sign
 of Highland Ave Installation/Repair

5342: ORT 135.9 - 133.6 EB: between New plaza
 Meyer Rd & Highland construction

5146: Bridge 113.3 - 113.3 WB: Exit ramp Bridge deck repair
Rehabilitation to IL 56

5372: ORT 86.9 - 85.6 EB/WB: between Plaza
 University Rd & Shabbona Rd Reconfiguration

5373: ORT 56.9 - 56.0 EB: between Red Pavement widening
 Brick Rd & Burkett Rd

5373: ORT 56.9 - 55.5 WB: between Pavement widening
 Red Brick & Burkett Rd

Maint. bldg. or
Contract # and
Description Lanes Closed Lanes Open DURATION

Tri-State Tollway (I -94/294)

8939: Roadway Left lane All Lanes Open until 6/1/2006
and Bridge shifted left
Widening

8939: Roadway All lanes All Lanes Open until 6/1/2006
and Bridge shifted right
Widening

8939: Roadway Left lane
and Bridge shifted left, All Lanes Open until 6/1/2006
Widening Two far lanes
 shifted far
 right

8939: Roadway All lanes All Lanes Open until 6/1/2006
and Bridge shifted right
Widening

8939: Roadway All lanes All Lanes Open until 6/1/2006
and Bridge shifted left
Widening

8940: Bridge All lanes until 9/1/2006
Widening shifted right

8940: Bridge All lanes until 9/1/2006
Widening shifted left

8941: Roadway All lanes All Lanes Open until 9/1/2006
Widening shifted right

8941: Roadway All lanes All Lanes Open until 9/1/2006
and Bridge shifted left
Widening

8941: Roadway Entrance Ramp until 9/1/2006
and Bridge Closed
Widening

8941: Roadway Exit Ramp until 9/1/2006
and Bridge Closed
Widening

8941: Roadway Two cash lanes One IPO lane, until 7/1/2006
Widening Two cash lanes

5336: ORT MxIPO Lanes All Other until 5/31/2006
 Lanes

5336: ORT MxIPO Lanes All Other until 6/7/2006
 Lanes

5335: ORT All lanes All Lanes Open until 6/3/2006
 shifted right

5335: ORT Two left lanes All Lanes Open until 6/3/2006
 shifted left,
 Two right
 lanes shifted
 right

5335: ORT Entrance Ramp None until 8/1/2006
 Closed

5335: ORT Exit Ramp None until 8/1/2006
 Closed

5335: ORT Right shoulder All Lanes Open until 8/1/2006

5334: ORT All lanes All Lanes Open until 6/30/2006
 shifted left

5334: ORT Right shoulder All Lanes Open until 6/2/2006

5337: ORT Right shoulder All Lanes Open until 8/7/2006

5337: ORT Left Lane Right Lane until 8/7/2006
 Only

5338: ORT Right Lane Left Lane until 10/1/2006

5310: ORT IPO Lanes All Other until 5/31/2006
 Lanes

5310: ORT Right MxIPO All Other until 5/24/2006
 Lanes

Northwest Tollway (I -90)

5301: ORT Left shoulder All Lanes Open until 5/31/2006

5301: ORT Left shoulder All Lanes Open until 5/31/2006

5301: ORT One cash lane All Other until 5/31/2006
 Lanes

5301: ORT Left Manual All Other until 5/26/2006
 Lane Lanes

5151R: Bridge Both shoulders All Lanes Open until
Reconstruction 11/22/2006

5151R: Bridge Entrance Ramp None until
Reconstruction Closed 11/22/2006

5368: ORT All lanes All Lanes Open until 8/1/2006
 shifted left

5368: ORT Left shoulder, All Lanes Open until 8/1/2006
 Right shoulder

5340: ORT Left shoulder, All Lanes Open until 8/1/2006
 Right shoulder

5340: ORT All lanes All Lanes Open until 8/1/2006
 shifted left

5339: ORT Left shoulder All Lanes Open until 6/1/2006

5339: ORT Left shoulder All Lanes Open until 6/1/2006

5339: ORT Two cash lanes All Other until 6/1/2006
 Lanes

5339: ORT Three right cash All Other until 6/1/2006

North-South Tollway (I -355) Lanes

7705: I -355 Left shoulder Ramp Open until
Extension 12/29/2006

7705: I -355 Left shoulder Ramp Open until
Extension 12/29/2006

7705: I -355 Right shoulder Ramp Open until
Extension 12/29/2006

7711: I -355 Left shoulder Ramp Open until
Extension 12/29/2006

7705: I -355 South Right Lane All lanes until 9/21/2007
Extension shifted left

7711: I -355 Right shoulder Ramp Open until
Extension 12/29/2006

7705: I -355 Right shoulder All Lanes Open until
Extension 12/29/2006

Reagan Memorial Tollway (I -88)

5342: ORT Right shoulder All Lanes Open until 6/30/2006

5342: ORT Right shoulder All Lanes Open until 6/30/2006

5342: ORT Entrance Ramp None until 8/25/2006
 Closed

5342: ORT Left shoulder All Lanes Open until 6/30/2006

5342: ORT All lanes All Lanes Open until 5/15/2006
 shifted right

5146: Bridge Left Lane Right Lane until 5/15/2006
Rehabilitation

5372: ORT Right Lane Left Lane until 5/25/2006

5373: ORT Right Lane Left Lane until 6/1/2006

5373: ORT Right Lane Left Lane until 6/1/2006
COPYRIGHT 2006 Urban and Regional Information Systems Association (URISA)
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2006 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Urban and Regional Information Systems Association Annual Conference Proceedings
Article Type:Report
Geographic Code:1USA
Date:Jan 1, 2006
Words:5578
Previous Article:The City of Calgary's application for the 2006 Exemplary System in Government Award--May 22, 2006.