 MIAMI, Sept. 1 /PRNewswire/ -- Comments from FPL Chairman and CEO


Jim Broadhead:
 -- FPL this morning has reduced the number of customer accounts
 without power to an estimated 230,000, all of them located in
 Dade County. Eight days after having 1.4 million customer
 accounts out of service, FPL has restored approximately 85
 percent of the homes and businesses affected by Hurricane Andrew.
 -- We returned to normal operations in Broward County on Monday
 afternoon. If customers there should be without power for any
 reason, we recommend they call FPL.
 -- In Dade County, however, we are still requesting that customers
 avoid calling us unless they need to report an emergency
 condition, such as a downed, sparking power line. We are aware
 of areas where power is still out, and we have more than 3,300
 crew members working in every area of Dade County. We continue
 to ship enormous quantities of equipment and material here. As
 an example, almost 10,000 wooden poles have been used to date --
 and we expect up to 20,000 more will be needed.
 -- FPL continues to stress safety as the first priority for our
 customers and employees as more people are moving about the area.
 We urge everyone to avoid downed lines of any kind, to supervise
 children closely and to hire licensed electricians for work on
 their home and business electrical systems. The proper use of
 portable generators also is important to protect neighbors and
 utility crews from the threat of electricity flowing out of a
 household and into the power grid.
 -- Before Bob Marshall and Bill Hamilton discuss FPL's restoration
 efforts in greater detail, we would like to repeat our appeal
 that motorists minimize their trips on Dade County's roads. This
 will facilitate the movement of equipment and crews needed to
 complete the restoration.
 -0- 9/1/92
 /CONTACT: Florida Power & Light corporate communications, 305-552-3883/ CO: Florida Power & Light ST: Florida IN: UTI SU:


JB-AW -- FL002 -- 5382 09/01/92 11:10 EDT
COPYRIGHT 1992 PR Newswire Association LLC
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1992 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:PR Newswire
Date:Sep 1, 1992
Words:334
Previous Article:WESTERN UNION PROVIDES NO-FEE MONEY TRANSFERS TO AREAS IN SOUTHERN FLORIDA AND LOUISIANA RAVAGED BY HURRICANE ANDREW
Next Article:REDEMPTION OF SUBORDINATED CAPITAL DEBENTURE ISSUE
Topics:


Related Articles
FLORIDA POWER & LIGHT: HURRICANE ANDREW RESTORATION OVERVIEW
FPL HURRICANE ANDREW RESTORATION OVERVIEW
FPL HURRICANE ANDREW RESTORATION OVERVIEW
FPL HURRICANE ANDREW RESTORATION OVERVIEW
FPL HURRICANE ANDREW RESTORATION OVERVIEW
FPL HURRICANE ANDREW RESTORATION OVERVIEW
HURRICANE ANDREW RESTORATION OVERVIEW
FLORIDA POWER & LIGHT ISSUES HURRICANE ANDREW RESTORATION OVERVIEW
FPL HURRICANE ANDREW RESTORATION OVERVIEW
FPL HURRICANE ANDREW RESTORATION OVERVIEW

Terms of use | Copyright © 2016 Farlex, Inc. | Feedback | For webmasters