Printer Friendly

GAO: task orders are immune from protest.

The Government Accountability Office has ruled that protests are not allowed over modifications to task orders under IDIQ contracts.

The Federal Acquisition Streamlining Act prohibits protests over the issuance of a task or delivery order, but does not mention modifications. A small business, Global Computer Enterprises Inc., lost a chance at a Coast Guard IT services contract when the agency decided to include those services on a modification of an existing task order. Global Computer argued that the task order modification constituted an illegally bundled contract, so its protest should be permitted.

"We find this position to be inconsistent with both the language of FASA and the underlying congressional intent," GAO said in dismissing the protest. "Moreover, we see no logic in holding that an agency's decision to modify an existing task order could be subject to protest when it is clear that an agency's decision to perform the very same action by means of a new task order would not be subject to protest."

GAO said Congress passed FASA as part of an effort to streamline and simplify federal procurement activities, and one of the act's purposes was to restrict bid protests.

The case is Matter of: Global Computer Enterprises, Inc., File numbers B310823; B-310823.2; B-310823.4.
COPYRIGHT 2008 Business Research Services, Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2008 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Set-Aside Alert
Date:Feb 22, 2008
Words:209
Previous Article:Advocates sue for access to contract data.
Next Article:Back to basics: help your customer help you.
Topics:


Related Articles
GAO faults Army on contract consolidation.
GAO approves defense dept.'s bundled trucking contract.
GAO: agency "unreasonable" in denying site visit.
SBA backs set-asides on GSA schedule orders.
No ruling on GSA schedule set-aside issue.
Ruling on GSA Schedule set-asides due in January.
GAO critiques U.S. fusion program.
DOD official orders restrictions on T&M contracts.
Protests are now permitted on task orders worth more than $10 million.

Terms of use | Privacy policy | Copyright © 2021 Farlex, Inc. | Feedback | For webmasters |