Effect of risk management implementation on productivity improvement.

Abstract: The companies from the naval sector are subject to a strong pressure from competitors and clients; this results in a high level of exigency in the execution of their projects. Within this framework, the application of the existing best practices and the use of worldwide project management standards become key pieces for these companies. This article puts forward the experiences gathered from the adaptation of the PMI methodology to a SME from Galician naval auxiliary industry. It deals with the different risk management implementation stages of a strategic project, showing the advantages and the keys to the project's success.

Key words: adaptation, SME, naval sector, risks, PMI

1. INTRODUCTION

Much has been written about risk management in big companies but there is little bibliography on the use of the PMI methodology in SME. Examples are the studies of Delisle & St-Pierre (2003), Blanc-Alquier & Lagasse-Tignol (2006) and Rosu et al. (2010) but their application is restricted and is usually developed for project-oriented organizations.

The main problem for a SME to implement this kind of methodologies is that the existing standards for project management were intended for large projects. In this project, the client has "guided" the SME in a suitable risk management implementation. The achievement has been to adapt the PMI methodology to create its own one adapted to the company's special characteristics. In addition to delivering the order fulfilling its specifications, this was about implementing a simple, agile risk management, adapted to the nature of the project, organization's sector and company culture that could be applied to future projects. The aim was to find proper indicators for particular processes and to find methodology that would help identify those (Nagyova & Pacaiova, 2009).

2. CASE STUDY

The Project we are about to analyze, "design and manufacture of 8 fender davits, was a significant strategic project in 2010. It began as such at the request of the customer, who follows the guidelines of Project Management Body of Knowledge (PMBok, 2008). This project's success was a milestone: it meant the introduction of the SME into a highly competitive new market.

[FIGURE 1 OMITTED]

2.1 Risk Management Plan (RMP)

Describe the procedure for the identification, analysis, prioritization and monitoring of the risks associated to the project (figure 2).

[FIGURE 2 OMITTED]

2.2 Risk Management Planning

The process covered the following aspects:

Organization: an external auditor was hired by customer; he acted as the project's risk management centre, coordinating the agents implied and integrating the management of the risks identified in the subprojects.

Roles and responsibilities: RMP chart defines three figures and their responsibilities:

--Risk management coordinator: external auditor hired by customer.

--Subproject Manager: responsible for each subproject.

--Member of team project: members of each team assigned.

Activities: actions defined in two process groups: planning and implementation; indicating for each of them which techniques were used, who the responsible is, who takes part in that activity, which deliverable is obtained and how often each activity is conducted (table 2).

Action procedures: course of action was divided into two procedures according to the risk management phase:

--Identification, analysis and action plan

--Monitoring and control.

* Controls: Risk Management Coordinator reviewed actions associated to risks monthly through the Internal Monitoring Report (IMR) and specifically when high exposure risks arose.

* Metrics: measures including enough information to alert on potential harm and help identify all kinds of risks (table 3).

* Records of risks and events: Risk Register Document included all information about Project risks.

2.3 Risk Identification

Risks were identified in the management, execution and closure process using brainstorming and checklist analysis techniques. The main categorized risks of the project planning process are:
Fig. 3. Identification of Categorized Risks

* Poor definition of the project

* Lack of risk analysis according to applicable law, previous
to project execution

* New market situation not assessed.

* Product put into the market hastily.

* No analysis of economic risks to be faced

* Incorrect planning regarding deadline and resources

* Lack of competence analysis within the sector and possible
incorporation.


2.4 Risks analysis, assessment, handling, monitoring and control

The Failure Mode & Effect Analysis (FMEA) was the risk management key tool. A practical document containing the maximum information in the minimum space was sought. Risk assessment was been carried out based on its impact on costs, deadlines and scope, as well as level of possibility of occurrence. Figure 4 shows the scales.

[FIGURE 4 OMITTED]

On the one hand, the FMEA applied includes a list of risks, prioritized once assessment based on impact and probability of occurrence ratings, whose product will provide the Risk Priority Number (RPN). On the other hand, it covered the strategy to be followed to keep or reduce the number. Figure 5 shows the treatment of one of the risks.

3. RESULTS & CONCLUSIONS

Results obtained are shown in table below:

The implementation of the PMI methodology was the milestone in this project's success for a SME motivated to be consolidated in such a competitive sector and to enter a new market; and has set a turning point in its working method.

4. ACKNOWLEDGEMENTS

The authors would like to thank the teachers of the Engineering Projects Area, University of Vigo, and Industrias Ferri, S.A. for their cooperation and interest.

5. REFERENCES

Blanc-Alquier, A.M. & Lagasse-Tignol, M.H. (2006). Risk management in small and medium-sized enterprises, Production Planning et Control. Vol. 17-3 p.273-282.2006

Delisle, S. & St-Pierre, J. (2003). SME Projects: A Software for the Identification, Assessment and Management of Risks, 48th World Conference of the International Council for Small Business (ICSB-2003)

Nagyova, A. & Pacaiova, H. (2009). How to Build Manual for Key Performance Indicators--KPI, Chapter 15 in DAAA International Scientific Book 2009, pp. 135-142, B. Katalinic (Ed.), Published by DAAAM International, ISBN 978-3-901509-69-8, ISSN 1726-9687,Vienna, Austria

Project Management Institute (2008). A Guide to the Project Management Body of Knowledge (PMBOK[R] Guide)--Fourth Edition, Project Management Institute, ISBN 9781933890517, USA

Rosu, S.M.; Dragoi, G.; Guran M. & Dragomirescu, C. (2010). The SMEs Knowledge Management: Professional Risk Assessment Using a KBS, Chapter 62 in DAAAM International Scientific Book 2010, pp. 709-724, B. Katalinic (Ed.), Published by DAAAM International, ISBN 978-3-901509-74-2, ISSN 1726-9687, Vienna, Austria
Tab. 1. Project's initial considerations

DESIGN AND MANUFACTURE OF FENDER DAVITS

Order: 4 pairs of davits for gas extraction platform
Customer: Leading Norwegian multinational company
Deliver: One year from order's acceptance
Price: 1.300.000 [euro] (22% of turnover)
Estimated cost: 800,000 [euro] (38% profit)
Delay records: 30-day average delay
Cost records: 15% increase from-initial budget

Tab. 2. Risk Management Planning Process Activities

When Planning Planning Planning

Action Risk Identification Risk Qualitative
 Identification Risk Analysis

Technique Brainstorming Checklist MEA

Manager Project manager Project Project manager
 manager

Participants Team project Team project Team project

Deliverables Risk Register Risk Risk Register,
 Document Register probability &
 Document impact matrix,
 non-priority
 risks list

Periodicity Once at beginning; Once at Once at
 also at every beginning of beginning of
 monitoring meeting project project; at
 every
 monitoring
 meeting

Tab. 3. Risk Management Plan Metrics

Name of metrics Description/formula

Number of Risks Description: No. of project's risks by
and Impact impact 1,2,3,4
 Formula: no. of risks

Number of Risks Description: No. project's risks by
and Probability probability 1,2,3,4
 Formula: No. of risks

Risk priority Description: RPN assessment
Number (RPN) Formula: criteria

Number of Risks Description: No. of project's risks that
becoming impacts became impacts
 Formula: No. of risks

Table 4. Results obtained

 THEORICAL REAL

Deadline 30-day average delay Within the stipulated
 period; no delays

Price 1.300.000 [euro] 1.300.000 [euro]
 (22% of turnover) 22% of turnover)

Cost 920.000 [euro] (800.000+15%) 864.000E (800.000+8%)

Benefit 29% benefit 33.54% benefit
 cost of 920.000 [euro] cost of 864.000 [euro]

Cost increase 15% increase from budget 8% increase from budget

Customer Survey average rating of 2 Survey average rating
satisfaction (scale 2-5) of 4 (scale 2-5)

Product Medium High
quality

Fig. 5. Failure Mode & Effect Analysis (FMEA)
Source: Sara Marcelino-Sadaba, Amaya-Ezcurdia (Dyna 2010)

RISK IDENTIFICATION AND PRIORITIZATION

PROJECT ASSOCIATED IMPACT
STAGE RISKS
 COST PERIOD SCOPE

Planning Management 3 4 3
 not
 implied

RISK HANDLING

ACTION PEOPLE PERIOD IMPACT
 RESPONS.
 COST PERIOD

Management Management Project's 2 2
assumes length
leadership

RISK IDENTIFICATION AND PRIORITIZATION

PROJECT PROBABILITY RPN
STAGE

Planning 4 5,7

RISK HANDLING

ACTION PROBA- RPN
 BILITY
 SCOPE

Management 2 2 0,6
assumes
leadership
COPYRIGHT 2011 DAAAM International Vienna
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2011 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Author:Fenollera, Maria; Lorenzo, Jaime
Publication:Annals of DAAAM & Proceedings
Date:Jan 1, 2011
Words:1394
Previous Article:Increasing of operational reliability of technical system.