Delivery, Installation, Assembly And Testing Of The 50 Kv Cable Systems.

Invitation to tender:Delivery, installation, assembly and testing of the 50 kV cable systems

Project-related production, delivery, assembly and testing of new 50 kV cable systems.

On behalf of Aare Versorgungs AG (AVAG), Alpiq EnerTrans AG, Niedergsgen plans to cable Olten

the existing 50 kV overhead line between the Unterwerk Flumenthal and Unterwerk

hydroelectric power station Flumenthal and Unterwerk Luterbach.

New pipelines, sockets and shafts were built for the entire cabling project.

The execution can vary depending on the line and can lead to different personnel and material requirements. In particular, work on the Wilihof bridge (pipeline under bridge) must be observed. After successful commissioning of each individual cable system, a detailed final documentation must be submitted.

Major organization : ELEKTRA BIRSECK MNCHENSTEIN (EBM)

Address : Weidenstrasse 27, 4142 Mnchenstein

Attn.:Markus Kuster

Country :Switzerland

Email : m.kuster@ebm.ch

Url : www.ebm.ch

Tender notice number : 990237

Notice type : Tender Notice

Open date : 2017-11-29

Tender documents : T429190755.html

?[c] 2017 Al Bawaba (Albawaba.com) Provided by SyndiGate Media Inc. ( Syndigate.info ).

COPYRIGHT 2017 SyndiGate Media Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2017 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Mena Report
Date:Oct 23, 2017
Words:170
Previous Article:Ep Kirchberg - Kriegstetten, Subproject Bsa. The Mandate Covers The Planning Services (pv) And Local Construction Management For The Subproject Bsa...
Next Article:Replacement Racetrack Dock A.
Topics:

Terms of use | Privacy policy | Copyright © 2020 Farlex, Inc. | Feedback | For webmasters