Delaying DOE's radwaste program.

Delaying DOE's radwaste program

Where to put high-level radioactive waste now accumulatingat nuclear power plants and other nonmilitary nuclear facilities has been a longstanding problem. The latest announcement from the Department of Energy (DOE) puts the answer even farther away. DOE has now concluded that it needs an extra five years before it can begin operating a permanent repository for high-level nuclear waste. That extension would push such a facility's opening date from Jan. 31, 1998, into the year 2003, throwing into disarray the schedule mandated by Congress in the Nuclear Waste Policy Act of 1982 (SN: 1/1/83, p.6).

The department cited delays in the consultation processleading to selection of three candidate sites for the first repository as one of the main reasons for its request for an extension (SN: 1/5/85, p.6). According to DOE's draft amendment to its "mission plan' for the civilian radioactive-waste management program, "additional time is needed . . . to collect needed technical information and to consult with states and affected Indian tribes as well as provide for public participation in the process.'

At the same time, DOE's revised plan reaffirms the department'sintention to postpone site-specific work on a second repository until the mid-1990s or later (SN: 6/7/86, p.359). Furthermore, DOE plans to submit to Congress a proposal for establishing a facility designed for temporary storage of highlevel radioactive waste. That action will occur as soon as legal issues are resolved (SN: 5/4/85, p.277). DOE's preferred site for a "monitored retrievable storage' facility is a cleared area at the Clinch River near Oak Ridge, Tenn., but the state, fearing that the facility may become permanent if it is built, has sued the federal government.

After a 60-day comment period, DOE may, where necessary,revise its draft amendment in response to comments received. Then the department intends to submit the final proposal to Congress. How Congress will react to DOE's change in plans isn't clear yet.
COPYRIGHT 1987 Science Service, Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1987, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:Department of Energy
Publication:Science News
Date:Feb 14, 1987
Previous Article:Changing constants: measuring progress.
Next Article:Flying high on a basement fossil find.

Related Articles
Legislators jump on predicted surplus.
End of the line for kids' free rides?
Renewable energy bill passes.
KUWAIT - Part 2 - Profiles Of The Oilfields.
The Public Policy Conference: MS activists will follow the money trail.
2007 Dance Annual Directory.
Homegrown energy: as America copes with climate change, many see hope in biofuels.
Native American power: Native American tribes are tapping into alternative energy sources with great benefits to themselves and their neighbors.
Washington outlook.

Terms of use | Copyright © 2016 Farlex, Inc. | Feedback | For webmasters