Defense Acquisitions: DOD Has Paid Billions in Award and Incentive Fees Regardless of Acquisition Outcomes.

GAO-06-66 December 19, 2005

Collectively, the Department of Defense (DOD) gives its contractors the opportunity to earn billions of dollars through monetary incentives--known as award fees and incentive fees. These fees are intended to motivate excellent contractor performance in areas deemed critical to an acquisition program's success, with award fees being appropriate when contracting and program officials cannot devise objective incentive fee targets related to cost, technical performance, or schedule. GAO was asked to determine whether award and incentive fees have been used effectively as a tool for achieving DOD's desired acquisition outcomes. To do this, GAO selected a probability sample of 93 contracts from the study population of 597 DOD award- and incentive-fee contracts that were active and had at least one contract action valued at $10 million or more from fiscal year 1999 through 2003.

The power of monetary incentives to motivate excellent contractor performance and improve acquisition outcomes is diluted by the way DOD structures and implements incentives. While there were two examples in our sample in which the Missile Defense Agency attempted to link award fees directly to desired acquisition outcomes, such as demonstrating a capability within an established schedule, award fees are generally not linked to acquisition outcomes. As a result, DOD has paid out an estimated $8 billion in award fees to date on the contracts in our study population, regardless of outcomes. The following selected programs show this disconnect. When DOD programs did not pay all of the available award fee, DOD gave contractors on an estimated 52 percent of award-fee contracts at least a second opportunity to earn an estimated $669 million in initially unearned or deferred fees. GAO believes these practices, along with paying significant amounts of fee for "acceptable, average, expected, good, or satisfactory" performance, undermine the effectiveness of fees as a motivational tool and marginalize their use in holding contractors accountable for acquisition outcomes. They also serve to waste taxpayer funds. Incentive fees provide a clearer link to acquisition outcomes; however, a majority of the 27 contracts with cost incentives that GAO reviewed failed or are projected to fail to complete the acquisition at or below the target price. Despite paying billions in fees, DOD has little evidence to support its belief that these fees improve contractor performance and acquisition outcomes. The department has not compiled data, conducted analyses, or developed performance measures to evaluate the effectiveness of award and incentive fees. In addition, when contracts have utilized different fee strategies to focus the contractor's attention on specific acquisition outcomes, contracting officials have stated that DOD has few mechanisms to share lessons learned and innovative practices outside the local level.
COPYRIGHT 2006 Stonehenge International
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2006 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:General Accounting Office Reports & Testimony
Date:Feb 1, 2006
Words:441
Previous Article:Managerial Cost Accounting Practices: Departments of Education, Transportation, and the Treasury.
Next Article:Federal Motor Carrier Safety Administration: Education and Outreach Programs Target Safety and Consumer Issues, but Gaps in Planning and Evaluation...
Topics:

Terms of use | Privacy policy | Copyright © 2019 Farlex, Inc. | Feedback | For webmasters