CHRYSLER REPORTS U.S. AND CANADIAN ASSEMBLY PLANT SCHEDULE FOR WEEK ENDING JULY 30

 HIGHLAND PARK, Mich., July 22 /PRNewswire/ -- Chrysler Corporation (NYSE: C) reports seven of its eight U.S. assembly plants and two of its three Canadian assembly plants will operate next week.
 St. Louis (Fenton, Mo.) Assembly Plant II will operate three seven- hour shifts each day next week.
 Jefferson North (Detroit), Sterling Heights (Mich.) and Newark (Del.) assembly plants will operate two eight-hour shifts each day next week.
 Dodge City (Warren, Mich.) will operate two eight-hour shifts each day next week.
 Toledo (Ohio) Assembly Plant will operate two nine-hour shifts each day next week.
 New Mack Avenue Viper (Detroit) Assembly Plant will operate one eight-hour shift each day next week.
 In Canada, Bramalea and Windsor (Ontario) assembly plants will operate two eight-hour shifts each day next week.
 As previously announced, Pillette (Ontario) and Belvidere (Ill.) assembly plants will not operate next week because of model changeover. Pillette will resume production the week of Aug. 2. Belvidere will resume production the week of Nov. 29.
 -0- 7/22/93
 /CONTACT: Alan Miller of Chrysler, 313-576-8093/
 (C)


CO: Chrysler Corporation ST: Michigan IN: AUT SU:

JG -- DE030 -- 4804 07/22/93 17:17 EDT
COPYRIGHT 1993 PR Newswire Association LLC
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1993 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:PR Newswire
Article Type:Calendar
Date:Jul 22, 1993
Words:192
Previous Article:WARD'S REPORTS ESTIMATED PRODUCTION
Next Article:McDONNELL DOUGLAS PIONEERS INNOVATIVE PAY PROGRAM
Topics:


Related Articles
CHRYSLER REPORTS ASSEMBLY PLANT SCHEDULE FOR WEEK ENDING JULY 10
CHRYSLER REPORTS ASSEMBLY PLANT SCHEDULE FOR WEEK ENDING JULY 17
CHRYSLER REPORTS U.S. AND CANADIAN ASSEMBLY PLANT SCHEDULE FOR WEEK ENDING OCT. 23
/ C O R R E C T I O N -- Chrysler Corporation /
CHRYSLER REPORTS U.S. AND CANADIAN ASSEMBLY PLANT SCHEDULE FOR WEEK ENDING MAY 28
/ C O R R E C T I O N -- CHRYSLER CORPORATION /
CHRYSLER REPORTS U.S. AND CANADIAN ASSEMBLY PLANT SCHEDULE FOR WEEK ENDING JULY 9
CHRYSLER REPORTS U.S. AND CANADIAN ASSEMBLY PLANTS SCHEDULE FOR WEEK OF MAY 30
CHRYSLER REPORTS U.S. AND CANADIAN ASSEMBLY PLANTS SCHEDULE FOR WEEK OF JUNE 26
CHRYSLER REPORTS U.S. AND CANADIAN ASSEMBLY PLANTS SCHEDULE FOR WEEK OF JULY 3

Terms of use | Copyright © 2016 Farlex, Inc. | Feedback | For webmasters