TULSA, Okla. -- Arena Resources Inc. (AMEX: ARD, ARD.WS) ("Arena") ("company") today announced its operations update for the fourth quarter of 2004 and its capital budget for 2005. In the last three months of 2004, Arena drilled nine wells, six of which were completed and placed in production by year-end. The remaining three wells were completed and placed in production in January 2005. As a result of the newly drilled wells and the property acquisitions made in 2004, production for the quarter ended Dec. 31, 2004, was approximately 70,500 BOEs, as compared to production of 37,900 BOEs for the same quarter 2003, an 86% increase. December 2004 net daily production was approximately 1,000 BOEs, as compared to production of 420 BOEs in December 2003, an increase of 138%. The 2005 capital budget of $15 million reflects the company's plans to immediately expand its operations in its Permian Basin properties acquired in 2004, with approximately 80% ($12 million) being allocated to these core properties. The budget includes the drilling of up to 33 development wells, multiple workovers and re-stimulations of existing wells, infrastructure additions and improvements, as well as initiating one waterflood project, expanding an existing waterflood and preparation work on three additional properties for future secondary recovery by waterflood. Arena does not budget for acquisitions; however, the company will continue to actively pursue future acquisition opportunities.

Fourth Quarter Operations Update/2005 Capital Expenditures

PERMIAN BASIN:

East Hobbs Unit, Lea County, N.M. -- The company drilled seven new infill wells to the San Andres formation in the fourth quarter; five were completed and placed in production, with the remaining two completed in January 2005. Workovers of three existing wells were also completed in the fourth quarter. In 2005, the company plans to drill three new infill wells and finish preparation for the initiation of a perimeter waterflood by mid-year 2005. Since acquiring the lease in May 2004, the company has more than doubled net daily production to more than 450 BOEs.

Fuhrman - Mascho, Andrews County, Texas -- Acquired in December 2004, the company has identified 130 developmental drilling locations on this 11,300-acre property, and will commence a development program in the second quarter that contemplates drilling 27 planned wells in 2005. The company will also begin a re-stimulation program on up to 20 existing wells in the second quarter.

West San Andres, Yoakum County, Texas -- One developmental well was drilled in January 2005 and is awaiting completion. The company plans to commence the workovers of three existing wells in 2005.

Seven Rivers Queen, Lea County, N.M. -- Remedial work on five existing wells and the workover of two existing wells is scheduled to be completed by mid-year 2005.

North Benson Queen, Eddy County, N.M. -- Construction of a water supply line is scheduled for the third quarter of 2005. This is in preparation for a secondary waterflood recovery program.

KANSAS:

Auntie Em Unit, Haskell County, Kan. -- In the fourth quarter of 2004, the company completed an 8 1/2-mile gas transmission line, and successfully drilled and completed a gas well, which, along with two previously drilled wells, was placed in production at a rate of approximately 500 mcf per day. In 2005, two additional developmental wells are planned to be drilled on this lease.

TEXAS:

Dodson Unit, Montague County, Texas -- The company initiated its developmental drilling program on this lease in December 2004. The initial well was drilled to an approximate depth of 5,200 feet (Ellenberger Formation). The well is currently awaiting completion. Core samples were taken to update current available data on the lease. In 2005, the company plans to put in place the necessary infrastructure in anticipation of initiating a secondary recovery program in 2006.

Y6, Fisher County, Texas -- In 2005, the company will expand an existing waterflood program operating in the northern half of the lease by converting three existing wells in the southern half into water injection wells.

OKLAHOMA:

Ona Morrow, Texas County, Okla. -- A water supply well, which will be used to stimulate existing production, will be drilled in the third quarter of 2005.

Eva South, Texas County, Okla. -- One 5,000-foot developmental well is scheduled to be drilled to the Morrow formation in the third quarter of 2005.

Midwell/Hanes, Cimarron County, Okla. -- Existing infrastructure will be improved in 2005 in preparation for a secondary recovery program.

About Arena Resources Inc.

Arena Resources Inc. is an oil and gas exploration, development and production company with current operations in Texas, Oklahoma, Kansas and New Mexico.

This release contains forward-looking statements within the meaning of the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995 that involve a wide variety of risks and uncertainties, including, without limitations, statements with respect to the company's strategy and prospects. Readers and investors are cautioned that the company's actual results may differ materially from those described in the forward-looking statements due to a number of factors, including, but not limited to, the company's ability to acquire productive oil and/or gas properties or to successfully drill and complete oil and/or gas wells on such properties, general economic conditions both domestically and abroad, and the conduct of business by the company, and other factors that may be more fully described in additional documents set forth by the company.
COPYRIGHT 2005 Business Wire
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

Article Details
Printer friendly Cite/link Email Feedback
Publication:Business Wire
Date:Feb 1, 2005
Words:884
Previous Article:Axcelis' New Single-Wafer Implanter Selected by Major European Chip Manufacturer; Versatile Applications Range, Productivity Key Factors in...
Next Article:Webcast Alert: IPAA Announces Its Oil & Gas Investment Symposium Small Cap Conference 2005 Webcast.


Related Articles
Swift Energy: Reports 2004 Record Production, 2004 Reserves and Spending, Updates Operations, and Announces 2005 Capital Budget.
Arena Resources Inc. Provides First Quarter 2005 Operations Update.
Profitable Quarter for Cambior.
Arena Resources Inc. Provides Third Quarter 2005 Operations Update; Third Quarter Production Increases 32% Over Second Quarter.
Arena Resources Increases 2005 Capital Expenditure Budget to $24 Million; Estimates 2006 Budget at $35 Million.
Arena Resources Inc. Provides Fourth Quarter 2005 Operations Update.
Arena Resources Announces Record Financial and Operational Results for Fourth Quarter and Year End 2005.
Arena Resources Inc. Provides First Quarter 2006 Operations Update; First Quarter 2006 Production Increases 111% Over First Quarter 2005.
Arena Resources, Inc. Announces First Quarter 2007 Operations Update.

Terms of use | Copyright © 2018 Farlex, Inc. | Feedback | For webmasters