By carrying out regular conditionmonitoring checks on critical rotating plant and machinery, Corus Northern Engineering Services (CNES), the maintenance, condition monitoring and engineering services company within Corus Group, has helped a limestone quarry in Cumbria maintain its output, efficiency and profitability.

CNES' condition monitoring team has been working closely with Cumbria-based Shapfell Lime Quarry for more than 12 years now, providing regular (monthly) patrol monitoring at the site, using a range of condition monitoring equipment and techniques, including handheld acoustic monitoring devices and vibration monitoring systems.

On a recent patrol monitoring visit, an engineer from CNES discovered unusually high readings on the primary crusher at the site, which raised concerns. Through further investigation using acoustic and vibration analysis systems, the CNES engineer discovered that the unusual noise levels and irregular readings were related to a fault on one of the primary crusher's main bearings, which had been running for more than 30 years. Significant wear and damage were found on the inner raceway of the bearing.

By analysing the results, CNES was able to advise Shapfell's maintenance team when it should plan to replace the bearing. Shapfell's maintenance engineers were mobilised and the bearing replacement took place at a scheduled plant shutdown period, without causing any major disruption to the crushing process.

Ian Taylor, business development engineer, plant condition monitoring at CNES, comments: "By using our extensive knowledge and experience of condition monitoring tools and techniques, our engineers were able to detect the fault on the bearing before it failed. For this particular site, we used handheld acoustic monitoring meters. The bearing was replaced within one week during a shutdown period, so there were no disruptions to production. If we hadn't spotted the bearing problem and it had failed during operation, the plant would have lost at least two weeks' production, while the bearing was replaced and the required manpower and lifting gear were mobilised on site."

At Shapfell, the first stage in the production of lime is the quarrying of the limestone itself. The quarrying of the limestone takes place on a 47-hectare site, one mile east of the Lime Works. Drilling and blasting in the quarry are undertaken by subcontractors, under the strict control of Shapfell Quarry Management. The average face height is 18 metres and blasts of between 10-30,000 tonnes of stone are carried out. The shot stone is loaded and transported by dump trucks through a series of internal roads to the Crushing Plant.

[ILLUSTRATION OMITTED]

In the crushing plant, limestone is crushed in a Primary Jaw Crusher, screened and then transported to the Secondary Roll Crusher. Further screening takes place, with the small material being used primarily in the iron making process or sold locally as stone products. The larger limestone, suitable for the kilns, is transferred to an outdoor stockpile. Limestone from this pile is fed into a washing plant, where scrubbers, screens and thickeners are used to remove contamination and produce a clean raw material for burning in the kilns.

Paul Wright, engineering manager at Shapfell Limestone Quarry comments: "By understanding which condition monitoring technique is appropriate for maintaining each piece of machinery or bearing, we can maintain output, efficiency and profitability of the plant at all times. Our ownmaintenance teamhas also been able to learn from CNES engineers."

* For further information please visit: www.corusnes.co.uk
COPYRIGHT 2007 DFA Media Ltd.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2007 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:MAINTENANCE MATTERS: PROBLEM SOLVER
Publication:Plant & Works Engineering
Date:Sep 1, 2007
Words:558
Previous Article:Trouble shooter.
Next Article:Relieving pressure: pressure is leading many plant engineers to explore ways to reduce boiler house energy consumption. A common idea is to reduce...
Topics:

Terms of use | Privacy policy | Copyright © 2019 Farlex, Inc. | Feedback | For webmasters