Abu Dhabi - The Gas Sector & OGD 1-2 Projects.
Total gas production capacities in Abu Dhabi rose from 1.8 BCF/day
in 1992 to more than 4 BCF/day by August 1996. A major part of the
production is associated gas, which will be fully utilised by 2001
compared to 89% in 1992. Most of the onshore gas supplies go to GASCO which has a major gas liquids complex at Ruwais. Most of the offshore
gas goes to the LNG export complex on Das Island. The SPC, ruling over
the hydrocarbon sector, decided in 1991 to launch ADNOC's Onshore
Gas Development (OGD) programme, to cost about $2 bn, based on
developing Thamama gas at the Bab and Asab fields and ADCO's other
structures close to the Habshan area. This was prompted by rising
demand, both for domestic gas consumption and for export in liquid form.
Development of Bab gas, called OGD-1 or Project 545, has cost $1.35 bn.
It was completed in August 1996. The main contracts were awarded in
March 1993 and June 1994 to a consortium of Technip of France (40%),
Bechtel of the US (30%) and Athens-based Consolidated Contractors Co.
(30%). The project manager was Brown & Root of the US, with
supervision done by a projects unit at ADNOC on ADCO's behalf.
Completed in November 1996, OGD-1 raised output and processing at
Habshan from 540 MCF/day to 1,865 MCF/day. It raised to 131,000 b/d the
condensate recovery rate, from 5,000 b/d, with most of the condensates
to be exported until the condensate units at the Ruwais refinery have
been built (see DT). OGD-1 involved the following: (1) non-associated
gas develop from the Thamama C and F reservoirs, beneath the
field's oil reservoirs, and associated gas from Thamama B; (2) two
new trains at the Habshan gas treatment complex, each with a capacity of
350 MCF/day, to process associated and non- associated gas; (3) another
new train at Habshan, with a capacity of 625 MCF/day, to process
non-associated gas from Thamama F into NGLs and condensates; (4) a new
gas compression station for Thamama B in an area 5 km from Habshan; (5)
two new gas injection trains which raised capacity from 280 MCF/day to
1,100 MCF/day for the dry sour gas for injection into the F reservoir;
(6) facilities for dry gas to be processed into LPG and for power
plants; (7) condensate storage and transfer facilities, consisting of
six 430,000-barrel tanks at Ruwais, 105 km from Bab, and two
195,000-barrel tanks at Habshan; (8) three sulphur recovery units of 600
t/day each; and (9) 245 km of pipelines with diameters ranging from 10
to 30 inches. About 830 MCF/day of the gas goes for domestic
consumption. The second phase, OGD-2, to cost $1.4 bn, was in April 1998
awarded to the Technip/Bechtel partnership, with CCC as sub-contractors.
It calls for the development of Thamama C North & South and Thamama
D of the Bab and Habshan structure and the drilling of 52 wells to
extract 1,100 MCF/day of gas, which will be processed at Habshan for
production of 55,000 b/d of condensate, about 500 t/y of NGL, and 2,100
t/d of sulphur. The project should be completed by late 2000. The
front-end engineering and design contract was awarded in June 1996 to
Technip. In mid-October 1998 Snamprogetti got the $110m contract for
OGD-2's gas gathering system involving 300 km of flowlines and
construction of a receiving terminal. An important part of the gas will
be for domestic consumption. A related $150m gas pipeline from Bab to
Maqta and the new Taweelah-B power station, known as Project 1,204, has
been completed. This involves a 42-inch, 125 km pipe from Bab to Maqta
and a 36-inch, 57 km pipe from Maqta to Taweelah. To increase the
sulphur handling capacity for its OGD system, called Project 1205 and
costing $15m, ADNOC awarded the contract in 1994 for completion before
end-1994. Pritchard Corp. did the front-end engineering design. OGD-2
will turn Habshan into one of the world's largest gas processing
plants with total gas treatment capacity of almost 3 BCF/day. The
related Asab gas development project (AGD), to cost about $700m, was
awarded in July 1997 to Snamprogetti. To be completed by end-1999, this
involves the drilling of wells to extract 856 MCF/day of wet associated
gas from Thamama F and G formations under Asab's oil reservoirs,
plus about 80,000 b/d of condensates to be stripped out and the
remaining dry gas to be reinjected into the reservoirs to maintain field
pressure; a gas gathering and injection pipeline; and related
facilities. Pritchard has done AGD's front-end engineering and
design. Willbros Engineering did the designs for the pipeline under a
sub-contract. ADCO in May 1993 had contracted Babcock Engineering to
install a system to inject gas into the North Shuaiba reservoir by
end-1995, with management and front-end engineering design done by
Bechtel. It also awarded a contract for a gas gathering network from
Thamama C and F to link up with ADNOC's OGD in 1996. This project
cost $150m, with Bechtel as consultant. Brown & Root provided the
front-end engineering and design.
![]() ![]() ![]() ![]() | |
Publication: | APS Review Gas Market Trends |
---|---|
Geographic Code: | 7UNIT |
Date: | Jan 11, 1999 |
Words: | 872 |
Previous Article: | Abu Dhabi - Abu Dhabi Company For Onshore Oil Operations. |
Next Article: | Abu Dhabi - $7.5 Bn For 2,300 MCF/D Gas Stream. |
Topics: |