WESTINGHOUSE AWARDED $40-MILLION CONTRACT FOR POWER GENERATION EQUIPMENT

 WESTINGHOUSE AWARDED $40-MILLION CONTRACT
 FOR POWER GENERATION EQUIPMENT
 ORLANDO, Fla., Nov. 10 /PRNewswire/ -- Westinghouse Electric Corporation (NYSE: WX) today announced it has been awarded a contract for more than $40 million to supply power generating equipment for the Cardinal Cogeneration Plant, which will be owned and operated by Sithe Energies, Inc.
 The Cardinal Cogeneration Plant is under construction in Ontario. The plant will supply electricity to Ontario Hydro and process steam for the Canadian Starch Company's corn products facility in Cardinal, Ontario.
 Westinghouse will supply the power island for the 150-megawatt plant to NEICO Canada, Inc., the turnkey contractor. The Westinghouse equipment includes a 100-megawatt Model 501D5 combustion turbine-generator, a 50-megawatt steam turbine-generator, a heat recovery steam generator and other balance-of-plant equipment.
 "By selecting Westinghouse to supply the entire power island, our customer has taken an approach that will maximize the Cardinal Plant's reliability," said Frank R. Bakos, vice president and general manager of the Westinghouse Power Generation business unit.
 "I'm gratified and honored that the performance of Westinghouse turbines has earned the confidence of Sithe Energies, NEICO and Ontario Hydro," Bakos said.
 During the past five years, the Westinghouse Model 501D5 combustion turbines have achieved a cumulative average availability of 95 percent and an average reliability of 98 percent. Westinghouse steam turbines have achieved an average availability of more than 95 percent.
 The plant will operate in the highly efficient combined cycle configuration, recycling waste heat from the combustion turbine to drive the steam turbine.
 The natural gas-fired plant will meet Ontario's rigorous environmental standards by employing Westinghouse's dry low-NOx combustion system incorporated in the combustion turbine.
 Major combustion turbine components will be produced by the Westinghouse facility in Hamilton, Ontario. Westinghouse facilities in Charlotte and Winston-Salem, N.C., will also manufacture components, and the unit will be assembled at the company's Pensacola, Fla., manufacturing plant. Westinghouse will produce the steam turbine at its Charlotte facility.
 The equipment is scheduled for delivery during the second half of 1993. The Cardinal Cogeneration Plant is scheduled for commercial operation during the summer of 1994.
 NEICO Canada, Inc., is a subsidiary of Northern Engineering, Inc., of Houston. Northern Engineering is a subsidiary of AGRA Industries, Ltd., a diversified engineering and construction company based in Calgary, Alberta.
 Sithe Energies, Inc., of New York, is a growing independent power production company, with over 3,000 megawatts of power generating capacity either in development, under construction or in operation.
 Westinghouse Electric Corporation, a leader in the global power generation business, has supplied more than 280,000 megawatts of power generating capacity, including more than 180 cogeneration plants. Westinghouse is based in Pittsburgh. Its Power Generation business unit is headquartered in Orlando.
 -0- 11/10/92
 /CONTACT: Mimi Limbach of Westinghouse Electric Corporation, 412-642-3341/
 (WX) CO: Westinghouse Electric Corporation ST: Pennsylvania, Florida IN: OIL ARO TLS SU: CON


CD -- PG011 -- 9384 11/10/92 15:10 EST
COPYRIGHT 1992 PR Newswire Association LLC
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1992 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:PR Newswire
Date:Nov 10, 1992
Words:481
Previous Article:BROOKE SHIELDS, HANK AARON AND ST. NICK SHARE HAM & EGGS AND HOLIDAY CHEER WITH TOYS FOR TOTS KIDS
Next Article:AMERICAN FILM POSTS HIGHER REVENUES IN FIFTH CONSECUTIVE PROFITABLE QUARTER
Topics:


Related Articles
WESTINGHOUSE AWARDED $94-MILLION FLORIDA POWER PLANT CONTRACT
WESTINGHOUSE AWARDED $54 MILLION CONTRACT FOR POWER GENERATING EQUIPMENT IN COLOMBIA
WESTINGHOUSE AND PARSONS RECEIVE $39 MILLION EQUIPMENT ORDER FROM TVA
WESTINGHOUSE AWARDED $88 MILLION FOR POWER GENERATION EQUIPMENT IN SPAIN
WESTINGHOUSE AWARDED $30 MILLION CONTRACT TO SUPPLY POWER PLANT IN INDONESIA
WESTINGHOUSE AWARDED CONTRACTS VALUED AT $63 MILLION IN ARGENTINA
WESTINGHOUSE AWARDED CHINA CONTRACTS TOTALING $150 MILLION
WESTINGHOUSE SELECTED FOR $305 MILLION IN POWER GENERATION EQUIPMENT ORDERS IN KOREA
WESTINGHOUSE RECEIVES CONTRACTS TOTALING $228 MILLION FOR POWER PLANT EQUIPMENT AND SERVICES
Westinghouse Receives Orders Totaling More Than $450 Million for Power Generation Equipment

Terms of use | Copyright © 2016 Farlex, Inc. | Feedback | For webmasters