Printer Friendly
The Free Library
22,725,466 articles and books

Uncalibrated building energy simulation modeling results.



Uncalibrated simulations have provided useful data but often with questionable accuracy. For this study, a protocol was developed for performing the uncalibrated simulations and then applied to four buildings for which consumption data were available. The protocol implementation involved using two levels, which allowed a total of 40 hours to survey the building, read the as-built information, and build the DOE-2.1E input file. The consumption data were not available to the simulation engineer until after the uncalibrated simulations were completed. The discrepancies between the simulated and measured total yearly building energy use varied over [+ or -]30% with one outlier outlier /out·li·er/ (out´li-er) an observation so distant from the central mass of the data that it noticeably influences results.

outlier

an extremely high or low value lying beyond the range of the bulk of the data.
. The results show that discrepancies ranged over [+ or -]90% between the simulations and the measured data for individual components such as chilled chill  
n.
1. A moderate but penetrating coldness.

2. A sensation of coldness, often accompanied by shivering and pallor of the skin.

3.
 water, hot water, and electricity consumption. Although the small sample size limits the overall conclusions that can be drawn, this study shows that uncalibrated simulations can have very low accuracy in predicting the energy use in a building. This study shows the need for calibration calibration /cal·i·bra·tion/ (kal?i-bra´shun) determination of the accuracy of an instrument, usually by measurement of its variation from a standard, to ascertain necessary correction factors.  when energy use will be used for financial decisions. Uncalibrated models, however, may be quite useful for determining trade-offs between various equipment or building scenarios.

INTRODUCTION

The use of detailed energy simulation software Simulation software is based on the process of imitating a real phenomenon with a set of mathematical formulas. It is, essentially, a program that allows the user to observe an operation through simulation without actually running the program.  has increased tremendously in the past ten years as applications in energy conservation and efficiency grow. These energy simulations often target energy retrofits, which focus on decreasing the energy use of an operational building by installing high-efficiency equipment, improving envelopes, or optimizing operating conditions. A range of simulation software programs exist, some in the public domain (DOE-2, BLAST) and others as proprietary software from different HVAC (Heating Ventilation Air Conditioning) In the home or small office with a handful of computers, HVAC is more for human comfort than the machines. In large datacenters, a humidity-free room with a steady, cool temperature is essential for the trouble-free  companies such as TRACE from Trane For the Jazz musician known by the nickname "Trane", see John Coltrane

Trane, a business of American Standard Companies, is a global provider of heating, ventilating and air conditioning (HVAC) systems and building management systems and controls.
 and HAP HAP. An old word which signifies to catch; as, "to hap the rent," to hap the deed poll." Techn. Dict. h.t.  from Carrier (Ayres Ayres may refer to:

People:
  • Anne Ayres (1816–1886), U.S. Episcopalian nun
  • William Orville Ayres (1817–1887), U.S. American physician and ichthyologist
  • Romeyn B.
 and Stamper 1995). Some software packages have a Microsoft (Microsoft Corporation, Redmond, WA, www.microsoft.com) The most successful and influential software company. Microsoft's software and Intel's hardware pioneered the PC and revolutionized the computer industry. [TM] Windows-based front end. EnergyGauge (FSEC FSEC Florida Solar Energy Center
FSEC Fire Service Emergency Cover (UK Office of the Deputy Prime Minister Fire Safety - Risk Assessment toolkit)
FSEC Federal Software Exchange Center
FSEC Florida Schools of Excellence Commission
 2005) and VisualDOE (Eley 2005) provide a Windows-based entry so the user does not have to decipher Same as decrypt.  the DOE-2.1E text file. One subtle issue with most front-end front-end
adj.
1. Of or relating to the initial phase of a project: a front-end investment.

2. Of or relating to the forward parts of a vehicle: a front-end alignment.
 programs is that many assumptions, parameters, and defaults are built in and are often not readily available or known by the user. The advantage of programs such as DOE-2 is that the user acquires a clear understanding of the input values, assumptions, parameters, and defaults. The disadvantage In policy debate, a disadvantage (abbreviated as DA, and sometimes referred to as a Disad) is an argument that a team brings up against a policy action that is being considered. Structure
A DA usually has four key elements.
 of programs like DOE-2 is the extensive level of effort required to simulate simulate - simulation  a building. There has been extensive research on sensitivity analysis of simulation variables (Corson Corson, a surname and place name, may refer to: Places
  • Corson County, South Dakota, a county in South Dakota, USA
  • Corson, South Dakota, a town in South Dakota, USA
  • Corson's Inlet State Park, a state park in New Jersey, USA
Persons
 1992; Jones and Hepting 2001; Lam and Hui Hui

Muslim people of western China. They number about nine million. Their ancestors were merchants, soldiers, craftsmen, and scholars who came to China from Islamic Persia and Central Asia from the 7th to the 13th century and intermarried with the Han Chinese and other local
 1996) and calibrated cal·i·brate  
tr.v. cal·i·brat·ed, cal·i·brat·ing, cal·i·brates
1. To check, adjust, or determine by comparison with a standard (the graduations of a quantitative measuring instrument):
 simulations (Bou-Saada and Haberl 1998; Bronson The name Bronson may refer to:

People

  • Bertrand H. Bronson, the author and musicologist
  • Bryan Bronson, American hurdler
  • Charles Bronson, the actor
  • Charles Bronson (prisoner), a British convicted prisoner who renamed himself after the actor
 et al. 1992; Liu and Claridge 1998). Reddy (2006) reviewed and summarized the literature for calibrated simulation procedures and tools.

The use of uncalibrated simulation has become more common in the energy industry to determine and report energy savings from various energy conservation measures. This study was designed to quantify Quantify - A performance analysis tool from Pure Software.  the expected range of discrepancies when uncalibrated simulations are used to calculate energy savings. The procedure followed was to analyze an·a·lyze
v.
1. To examine methodically by separating into parts and studying their interrelations.

2. To separate a chemical substance into its constituent elements to determine their nature or proportions.

3.
 the performance of four uncalibrated simulation models using DOE-2.1E Version 119 (Ayres and Stamper 1995) as the simulation package. The four buildings were randomly selected from a building data base (LoanSTAR 2005). Three of the four buildings selected as the test sample are located on the main and west campuses of a large university. The fourth building, the John B. Connally Building, is located off-campus. The three central campus buildings are supplied by the central chiller chill·er  
n.
1. One that chills.

2. A frightening story, especially one involving violence, evil, or the supernatural; a thriller.


chiller
Noun

1.
 plant, while the John B. Connally Building has its own HVAC plant. The Wisenbaker Engineering Research Center is analyzed an·a·lyze  
tr.v. an·a·lyzed, an·a·lyz·ing, an·a·lyz·es
1. To examine methodically by separating into parts and studying their interrelations.

2. Chemistry To make a chemical analysis of.

3.
 in detail in this paper. Summary data are provided on the other buildings.

METHODOLOGY AND TEST PROTOCOL

As energy prices increase, the interest in saving energy has increased. Simulation provides a mechanism to determine where savings opportunities exist or energy inefficiency occurs in a building. With historical data often not available, uncalibrated simulations allow a method to analyze the energy consumption of a building. A test protocol was developed to put realistic constraints CONSTRAINTS - A language for solving constraints using value inference.

["CONSTRAINTS: A Language for Expressing Almost-Hierarchical Descriptions", G.J. Sussman et al, Artif Intell 14(1):1-39 (Aug 1980)].
 on available resources, including time, simulation skill, and simulation software. This test protocol was designed to be a time-limited, blind, uncalibrated simulation. The intent of this research was to determine what the range of discrepancies would be for various buildings using uncalibrated simulations.

Measurements covering building energy use over several years existed as part of the ongoing monitoring of numerous campus buildings. Each building's energy data were not made available until after the simulations and the analysis of the simulation results were completed. The energy use data were then compared to the simulated energy use.

The test protocol required a simulation engineer with a strong working knowledge (at least one year of experience) with the simulation software used and a publicly available and peer reviewed simulation software. We selected DOE-2.1E because it was created and is maintained by the US Department of Energy and is freely available. The simulation engineer, a graduate student at the time, had more than one year of experience with DOE-2.1E and had taken a graduate-level course on using DOE-2.1E.

In addition, the test protocol was designed with an upper limit on the time allowed to acquire building data and build the simulation input file. Two simulation models were created for each of the four buildings. The two simulation models were designated as Level 1 and Level 2. The time allowed to build the input files for the Level 1 model was constrained con·strain  
tr.v. con·strained, con·strain·ing, con·strains
1. To compel by physical, moral, or circumstantial force; oblige: felt constrained to object. See Synonyms at force.

2.
 to 20 hours, although one crept crept  
v.
Past tense and past participle of creep.


crept
Verb

the past of creep

crept creep
 up to 22 hours. The time limit for the Level 2 model allowed up to an additional 20 hours. Although the time limits were somewhat arbitrary Irrational; capricious.

The term arbitrary describes a course of action or a decision that is not based on reason or judgment but on personal will or discretion without regard to rules or standards.
, these limits keep the time to simulate a building in the realm of usability How easy something is to use. Both software and Web sites can be tested for usability. Considering how difficult applications are to use and Web sites are to navigate, one would wish that more designers took this seriously. See user interface and usability lab.  by industry. The time used for creating the input file for each model was logged. The time consumed con·sume  
v. con·sumed, con·sum·ing, con·sumes

v.tr.
1. To take in as food; eat or drink up. See Synonyms at eat.

2.
a.
 depended upon the effort required to get the building information and the complexity of the building layout. Table 1 summarizes the amount of time spent creating the two simulation models in each of the four buildings.

The emphasis of the Level 1 model was on defining the correct geometry geometry [Gr.,=earth measuring], branch of mathematics concerned with the properties of and relationships between points, lines, planes, and figures and with generalizations of these concepts.  and the as-built HVAC systems. Defining the correct geometry required more than 70% of the total time spent developing the Level 1 model. The four buildings have different layouts, so the time required in creating each Level 1 model also differed. The Wehner Business Administration Building required 17 of the 22 hours to complete just the building layout because of the complex geometry In mathematics, complex geometry is the study of complex manifolds and functions of many complex variables. .

The Level 1 model has the following characteristics:

* No thermal mass Thermal mass, in the most general sense, is any mass that absorbs and holds heat. In the architectural sense, it is any mass that absorbs and stores heat during sunny periods when the heat is not desirable in the living space of a building, and then releases the heat during  

* Physically correct layout and geometry

* Typical values obtained from general observation for occupancy, equipment, and lighting

* As-built definition of primary HVAC equipment

* Assumed typical values for HVAC parameters such as supply airflow and various other set-points

The Level 2 model added the following aspects to the Level 1 model:

* Thermal mass

* Site-specific Site-specific is used in a range of contexts:

In art Site-specific art

In molecular biology Site-specific recombination
 values for occupancy, equipment, and lighting obtained from detailed site surveys

* As-built definition of all the different HVAC systems employed

* As-built information about the HVAC operating parameters from current operating conditions from the maintenance engineers

The time spent creating the Level 2 model focused on detailed building surveys and meeting with the maintenance personnel in order to get the correct as-built drawings and current operation of the buildings and also to add thermal mass into the simulation. This phase required that all of the construction materials be defined for the layers of the walls, floors, and ceilings. In addition, all interior walls used for zoning had to be defined so the weighting factors would be specified correctly. In the system and plants input section of the file, the correct size and supply airflow were entered from the as-built data obtained from maintenance personnel, instead of allowing the simulation model to calculate zone airflow and equipment sizing. This created a simulation model that closely resembled the as-built details of the real building.

Once the simulations were complete, the results from these simulation models were then compared to measured hourly data from the four sample buildings. The three on-campus on-campus adjective Referring to an on-site site of a medical complex with multiple buildings. Cf 'Off campus.'.  buildings, which have chilled and hot water supplied by the central power plant, have logged data for the chilled water and hot water consumption and the whole building electric. Chilled water, hot water, and electrical data were measured in each building to ensure that the measurements captured all energy being supplied to each building. Data were available for the year in which the simulation was performed. The fourth building has a separate HVAC plant. Therefore, the whole building electric included the chiller kWh consumption. The boiler boiler, device for generating steam. It consists of two principal parts: the furnace, which provides heat, usually by burning a fuel, and the boiler proper, a device in which the heat changes water into steam.  gas consumption for this building was not available.

An interesting aspect of this study was to analyze where the simulations had the highest discrepancies in determining energy use from the uncalibrated simulations. For this purpose, a sensitivity analysis was performed by selecting specific variables from the different sections of the simulation input file. Emphasis was placed on the parameters in the systems section of the input file since extensive research in the sensitivity of parameters in the DOE-2.1E simulation program shows that system-based parameters such as outside air fraction and equipment performance and efficiency can change a building's energy use by as much as 30% (Corson 1992; Lam and Hui 1996). Although the window-to-wall ratio and U-factors for the envelope components can also affect the outcome of a simulation, the effect is usually less than 10% on the overall energy consumption (Corson 1992). The following four parameters were studied in the current work:

* Thermal mass

* Outside air fraction

* Fan schedule

* Thermostat thermostat, automatic device that regulates temperature in an enclosed area by controlling heating or refrigerating systems. It is commonly connected to one of these systems, turning it on or off in order to maintain a predetermined temperature.  schedule

In addition to these parameters, exterior wall U-factors, glazing Glazing

The application of finely ground glass, or glass-forming materials, or a mixture of both, to a ceramic body and heating (firing) to a temperature where the material or materials melt, forming a coating of glass on the surface of the ware.
 types, and economizer e·con·o·mize  
v. e·con·o·mized, e·con·o·miz·ing, e·con·o·miz·es

v.intr.
1. To practice economy, as by avoiding waste or reducing expenditures.

2.
 parameters were also analyzed. The effect of these parameters on the simulation result was negligible This article or section is written like a personal reflection or and may require .
Please [ improve this article] by rewriting this article or section in an .
. From the analysis of the impact of these variables on the simulation output, it was found that for internal load-dominated buildings, the effect of thermal mass was less than 10% of the total energy use since the envelope loads for such buildings are a very small percentage of the total loads, which mostly consist of occupancy, lighting, and plug loads. The outside air fraction has a significant impact on the simulation results. A change from 10% outside air to 25% outside air can change the total energy consumption by more than 20%. Major discrepancies with measured data can occur in a simulation model if incorrect assumptions are made for the outside air fraction for a particular system. A detailed analysis of these results is presented in Ahmad Ahmad. For Ottoman sultans thus named, use Ahmed.  (2003).

Discrepancy DISCREPANCY. A difference between one thing and another, between one writing and another; a variance. (q.v.)
     2. Discrepancies are material and immaterial.
 Analysis

The daily averages of the hourly data from the simulated and measured data were used to calculate the percent discrepancy for chilled water, hot water, and electricity consumption. Since the goal was to determine if the simulation predicts the actual consumption, the percent discrepancy was used to show the differences between the measured data and the simulated values. Equation 1 shows the mathematical representation for the percent discrepancy.

%Discrepancy = ([[365.summation summation n. the final argument of an attorney at the close of a trial in which he/she attempts to convince the judge and/or jury of the virtues of the client's case. (See: closing argument)  over (i=1)][y.sub.m,i] - [365.summation over (i=1)][y.sub.s,i]]/[[365.summation over (i=1)][y.sub.m,i]]) x 100 (1)

where

[y.sub.s,i] = set of simulated values (365 average daily energy consumption values)

[y.sub.m,i] = set of measured values (365 average daily energy consumption values)

Researchers have used various statistical parameters A statistical parameter is a parameter that indexes a family of probability distributions.

Among parameterized families of distributions are the normal distributions, the Poisson distributions, the binomial distributions, and the exponential distributions.
 to judge the accuracy of the simulated data against the measured. In an early research project, Torres-Nunci (1989) calibrated a simulation by visually analyzing the differences between the measured and simulated energy consumption through scatter plots See scatter diagram. . Hinchey (1991) created several simulation models ranging from one zone to eighteen zones and found that for an internal-load-dominated building the effect of zoning was negligible. Her annual energy consumption results showed a difference of 3.5% between a one-zone and an eighteen-zone model. This result was obtained by calculating residuals Residuals

(1) Part of stock returns not explained by the explanatory variable (the market index return). Residuals measure the impact of firm-specific events during a particular period.
 of the measured and simulated data. In the current research, averaged hourly consumption values and simple percentage differences were also used.

Bronson et al. (1992) used monthly percentage differences to calibrate To adjust or bring into balance. Scanners, CRTs and similar peripherals may require periodic adjustment. Unlike digital devices, the electronic components within these analog devices may change from their original specification. See color calibration and tweak.  a simulation model to non-weather-dependent loads. The final calibrated model was within approximately 1% of the measured data for the six-month comparison period. However, for weather-dependent loads, the percentage discrepancy increased. Their reported chilled water calculated discrepancy was 1.6%, while the hot water calculated discrepancy was -9.6%. Several other researchers have used this method and have claimed accuracies within 1%.

Bou-Saada and Haberl (1998) and Haberl and Bou-Saada (1998) used coefficient coefficient /co·ef·fi·cient/ (ko?ah-fish´int)
1. an expression of the change or effect produced by variation in certain factors, or of the ratio between two different quantities.

2.
 of variance The discrepancy between what a party to a lawsuit alleges will be proved in pleadings and what the party actually proves at trial.

In Zoning law, an official permit to use property in a manner that departs from the way in which other property in the same locality
 of the root mean square error, CV(RMSE RMSE Root Mean Square Error
RMSE Root Mean Squared Error
), and the mean bias error, MBE MBE (in Britain) Member of the Order of the British Empire

MBE n abbr (BRIT) (= Member of the Order of the British Empire) → título ceremonial

MBE n abbr (Brit) (=
, to define the accuracy of the calibrated model. The above-mentioned A`bove´-men`tioned

a. 1. Mentioned or named before; aforesaid; mentioned or named earlier in the same text (in written documents).

Adj. 1.
 method was first used by Kreider and Haberl (1994). Bou-Saada and Haberl (1998) stated that these indices were more accurate in determining the level of calibration than the simple percentage difference of the residual Residual

See:Residual value
 analysis. Using daily or monthly percentage differences tends to average out the variations that are present in hourly data. For calibrating building simulation models, CV (RMSE) and MBE hourly are widely used. The International Performance Measurement and Verification Protocol (IPMVP IPMVP International Performance Measurement & Verification Protocol ) and ASHRAE ASHRAE American Society of Heating, Refrigerating & Air Conditioning Engineers  Guideline guideline Medtalk A series of recommendations by a body of experts in a particular discipline. See Cancer screening guidelines, Cardiac profile guidelines, Gatekeeper guidelines, Harvard guidelines, Transfusion guidelines.  14 also recommend this analysis to characterize modeling errors for savings verification (Haberl and Bou-Saada 1998; Kreider and Haberl 1994; Haberl and Thamilseran 1994; IPMVP 2002; ASHRAE 2002). Since the current study does not include the calibration of the simulation models, the use of average percentage discrepancy to compare Level 1 and Level 2 models was determined to be sufficient.

Analysis

Daily averages of the measured and simulated chilled water consumption, hot water consumption, and whole building electricity consumption were compared for each of the four buildings. The statistical parameter defined above was then used to define the degree of difference between the simulation models and the actual operation of each building. The results from both the Level 1 and Level 2 simulation models were compared against the measured data. This analysis was performed to check whether entering as-built and design-operating values for the building would reduce the discrepancy in the simulation model when compared with the measured data. The analysis performed on one of the buildings is presented in this paper. A detailed analysis of all the buildings studied is available in Ahmad (2003).

Wisenbaker Engineering Research Center

Wisenbaker Engineering Research Center (WERC WERC Warehousing Education and Research Council
WERC Wisconsin Employment Relations Commission
WERC Western Ecological Research Center
WERC Workforce Education Research Center
WERC Waste-Management, Education, and Research Consortium
) is a 16,450.43 [m.sup.2] (177,071 [ft.sup.2]) building located on the main campus of a university. This is a multipurpose mul·ti·pur·pose  
adj.
Designed or used for several purposes: a multipurpose room; multipurpose software.


multipurpose
Adjective
 building, divided mainly between laboratories and offices. WERC also contains a large material-testing lab. The main difference between the Level 1 model and the Level 2 model for this building is thermal mass and system description. In order to consider thermal mass in DOE-2.1E, the materials used in the construction have to be defined in layers. In addition, all partitions, interior walls, and the ceiling have to be defined with the correct coordinates coordinates

of a point on a graph or grid map, the points on the horizontal and vertical axes which identify the location of the point on the graph/map.
. For the Level 1 input file, the HVAC equipment was entered as a single system that served the complete building. In the Level 2 input file, each different HVAC system in the building had to be entered. For example, WERC uses fan-coil units to condition the basement This article is about the section of a building. For the foundation, see Basement rock.

A basement is one or more floors of a building that are either completely or partially below the ground floor. Slab-on-grade buildings do not have basements.
, single-zone constant-volume reheat Re`heat´   

v. t. 1. To heat again.
2. To revive; to cheer; to cherish.

Verb 1. reheat - heat again; "Please reheat the food from last night"
 supply air to condition the materials laboratory, and variable-volume system supply air to condition the rest of the building. Each of these were entered into the Level 2 input file for the areas served. In addition, the airflow rates through the different air handlers
AHU redirects here. Click on "Ahu ", for the platform of stone used as a base for an Easter Island Moai (Statue) or a group of such statues together.


An air handler, or air handling unit and often abbreviated to AHU
 were obtained from the design data, where assumed values were used in the Level 1 model. In the Level 2 model, lighting and equipment wattage wattage

the output or consumption of an electric device expressed in watts.
 densities were also adjusted according to according to
prep.
1. As stated or indicated by; on the authority of: according to historians.

2. In keeping with: according to instructions.

3.
 observations. Tables 2a and 2b summarize sum·ma·rize  
intr. & tr.v. sum·ma·rized, sum·ma·riz·ing, sum·ma·riz·es
To make a summary or make a summary of.



sum
 the main differences between the Level 1 and Level 2 models. Figure 1 compares daily chilled water consumption for the Level 1 and 2 models with measured data from WERC.

For outside temperatures above 21.1[degrees]C (70[degrees]F), both the Level 1 and Level 2 simulations show chilled water consumption at approximately 25% less than that measured. The measured values were several times higher than the simulated values for temperatures below 12.8[degrees]C (55[degrees]F). The high consumption of measured chilled water at lower temperatures may indicate a mechanical problem. However, since the building was internal-load-dominated, it could also be requiring ~20,515 kWh/day (70 MMBtu/day) of chilled water for the winter months.

During a discussion with the building engineer, it was found that there were numerous maintenance problems associated with the operation of the air-handlers. Most of the problems were related to the controls and the valves. These operational problems had been completely repaired by October October: see month.  2002.

Measured data for both chilled and hot water consumption were available for the post-commissioning period for 2004. These data were compared with the two simulation models, which show that chilled and hot water consumption has been reduced considerably. Chilled water was reduced from an average daily consumption of 28,325 kWh/day (96.65 MMBtu/day) to 23,865 kWh/day (81.43 MMBtu/day). This is a 15.7% reduction in the average daily use. Hot water consumption was reduced from 6,008 kWh/day (20.5 MMBtu/day) to 3,361 kWh/day (11.47 MMBtu/day), a reduction of 44%. Figure 2 shows a comparison between simulated (both Level 1 and Level 2 models) and post-commissioning measured data. The simulations were run using the weather data for 2004. The post-commissioning data indicate that chilled water consumption at low temperatures was between 8,792 kWh/day (30 MMBtu/day) and 14,653 kWh/day (50 MMBtu/day), which shows that the internal load drives the energy consumption. The simulated values show that the simulation models were not taking into account chilled water consumption at low temperatures.

The variation of simulated hot water consumption from the measured data was significant for both simulation models. Discrepancies can arise from incorrectly establishing the values in the input file or from malfunctioning mal·func·tion  
intr.v. mal·func·tioned, mal·func·tion·ing, mal·func·tions
1. To fail to function.

2. To function improperly.

n.
1. Failure to function.

2.
 heating and cooling equipment. Figures 3 and 4 compare simulated values against the measured data sets. During the retrocommissioning, the setpoint Setpoint may refer to:
  • SetPoint (software), the driver suite for Logitech mice
  • Setpoint (control system), the desired value specified for controlling a system
 control of the hot water supply had been reset from 25[degrees]C (77[degrees]F) for 1999 operation to 20[degrees]C (68[degrees]F) for 2004 operation, as shown in the two measured data sets.

[FIGURE 1 OMITTED]

[FIGURE 2 OMITTED]

[FIGURE 3 OMITTED]

[FIGURE 4 OMITTED]

Figure 5 shows the 2004 whole building electrical consumption simulation and illustrates how DOE-2.1E handles electrical loading If an electric circuit has a well-defined output terminal, the circuit connected to this terminal (or its input impedance) is the load. (The term 'load' may also refer to the power consumed by a circuit; that topic is not discussed here.  when the electrical loads do not include the heating or cooling. Note that the fans (all constant speed), lights, and other non-HVAC loads were on a specified schedule. The chilled and hot water were provided from the central plant. The actual use shows more variation than the simulation and also depicts a lower usage than the simulated values. These were about 25% to 30% lower than predicted by using the simulation input file. This unnatural-looking electrical usage occurs in simulations that rely on fixed schedules. Constant usage values are often hidden by HVAC usage when the building has electrically powered HVAC loads. Nonetheless, these inaccurate but constant load profiles remain present.

The total energy consumption for 1999 and 2004 are shown in Figures 6 and 7, respectively. The impact of the commissioning can be seen immediately. Nonetheless, the simulations still show significant discrepancies from the measured data. In the case of the WERC simulation, the measured data were higher than the simulated data.

The total energy consumption shows that the simulated values were less than the actual consumption. In 2004, when the outside temperature was above 23.9[degrees]C (75[degrees]F), the Level 1 simulation results were under the actual consumption by approximately 10%. Once the outside temperature drops below 18.3[degrees]C (65[degrees]F), the difference grows rapidly. Below 12.8[degrees]C (55[degrees]F), the difference is about a factor of two more than the 2004 simulation and over two times the 1999 simulation.

[FIGURE 5 OMITTED]

[FIGURE 6 OMITTED]

[FIGURE 7 OMITTED]

RESULTS

In WERC (177,071 [ft.sup.2] [16,450 [m.sup.2]]), the simulation using 1999 data underestimates the energy use in all categories except the whole building electrical usage. Table 3 identifies the magnitude of these discrepancies for a full year's consumption. The Level 1 model actually performed slightly better, with a net discrepancy for total consumption of about 32%. The Level 2 model performed about the same, with a discrepancy of 34%. The modeled data when compared to the measured 2004 data, shown in Table 4, resulted in a smaller discrepancy than when compared to the 1999 data. This reflects the energy optimization optimization

Field of applied mathematics whose principles and methods are used to solve quantitative problems in disciplines including physics, biology, engineering, and economics.
 done on WERC between 1999 and 2004. In this building, the calculated consumption was less than actual consumption. This may have been due to malfunctioning HVAC equipment (which was later found to be the case) or just mistakes in the parameters in the input files.

Results from the other buildings varied considerably, as is shown in Tables 5 through 7. This summary illustrates the wide variance that can be expected from uncalibrated simulations.

For Harrington Harrington can refer to:

Places in the United Kingdom:
  • Harrington, Cumbria
  • Harrington, Lincolnshire
  • Harrington, Northamptonshire
Places in the United States:
  • Harrington, Delaware
  • Harrington, Maine
  • Harrington, Washington
 Tower (130,844 [ft.sup.2] [12,156 [m.sup.2]]), the Level 1 model was very close and the Level 2 model overestimated the energy use by almost 50%. The chilled water use was substantially overestimated. The hot water use varied considerably between the two modeling methods. The Level 1 model used around 8% of hot water compared to the Level 2 model. This behavior of the Level 1 model was apparent from the other simulation models as well. For the Wehner Business Administration Building, the Level 1 hot water consumption was 243,249 kWh/year (830 MMBtu/year) as compared to 655,307 kWh/year (2,236 MMBtu/year) for the Level 2 model. This very large difference in hot water consumption can be attributed to the use of defaults and assumptions in the Level 1 model as compared to as-built data in the Level 2 simulation. In the case of Harrington Tower, the difference was more obvious because the measured hot water consumption lies between the Level 2 and Level 1 model. This gives a percentage discrepancy ranging from 85% to -98%. The whole building electricity consumption was within about [+ or -]10%.

The uncalibrated simulations performed for the Wehner Business Administration Building (192,000 [ft.sup.2] [17,837 [m.sup.2]]) were closer than those for Harrington Tower. The consumption was overestimated by 14% and 33% for the Level 1 and Level 2 models, respectively.

For the John B. Connally Building (123,961 [ft.sup.2] [11,516 [m.sup.2]]), only the whole building electric data were available. These data include the electrical consumption of the two on-site on-site
adj.
Done or located at the site, as of a particular activity: on-site monitoring of a production run; an on-site film shoot.
 chillers. The simulated whole building electric was overestimated by 15% for the Level 1 model and by 16% for the Level 2 model.

Table 8 summarizes the percentage discrepancy between the measured and simulated data for the electrical, chilled water, hot water, and total energy consumption. For the John B. Connally Building, the percentage discrepancy was for the whole building electric. All other buildings received their chilled and hot water from a central plant. A minus sign indicates that the simulated data consumption was greater than the measured consumption.

CONCLUSIONS

This research presents an initial study to document the performance of uncalibrated simulations. When the total energy for the building was calculated, discrepancies in the range of [+ or -]30% were observed, with occasional outliers. In general, uncalibrated simulations were observed to result in discrepancies from the measured data exceeding [+ or -]90% for individual components such as chilled water or hot water. From this study, we have drawn the following conclusions.

Uncalibrated simulation models may not adequately represent the real operations of buildings. The data in Table 8 show a wide range of predicted results. This initial study illustrates the pitfalls of using uncalibrated simulations.

* The simulation overpredicted the electrical consumption in all cases except one. This could very well arise from lighting and/or and/or  
conj.
Used to indicate that either or both of the items connected by it are involved.

Usage Note: And/or is widely used in legal and business writing.
 motors being turned off more than the scheduled times In rallying, the Scheduled Time of any crew is the time, calculated at the beginning of the event, that they should arrive at any given control. It is different from Due Time in that Due Time is dynamic, ie it can change throughout the event as competitors drop time; whereas . This could also arise from overestimating the plug load in the facility. Without submetering, this information was not available. In all buildings except the John B. Connally Building, chilled and hot water were supplied by a central plant. Figure 6 shows that the WERC predicted electric consumption was higher than the measured values.

* The high consumption in WERC at low outside temperatures indicated that reheat or leaking leak  
v. leaked, leak·ing, leaks

v.intr.
1. To permit the escape, entry, or passage of something through a breach or flaw:
 chilled water/hot water valves may be responsible for the high consumption. Retrocommissioning did reduce the chilled water use for WERC over the full outside air temperature range. This higher actual consumption may also arise from dysfunctional dys·func·tion also dis·func·tion  
n.
Abnormal or impaired functioning, especially of a bodily system or social group.



dys·func
 controls, such as an economizer.

* Hot water use exceeded the simulation predictions in all cases except one. This could have occurred from leaky leak·y  
adj. leak·i·er, leak·i·est
Permitting leaks or leakage: a leaky roof; a leaky defense system.

Adj. 1.
 reheat valves. At WERC, many valves were repaired when the building underwent retrocommissioning in 2003. The post-retrocommissioning consumption decreased by almost half. Harrington Tower had twice the hot water predicted than was measured, which corresponds to the chilled water being higher than predicted. The other buildings had over three to seven times the predicted consumption, indicating leaking valves or dysfunctional controls.

* When a building has electrically powered chillers without submetered energy use, the ability to estimate the operational problems of the building becomes further obscured. For example, when the simulation underestimated chilled water and overestimated electric use as compared to measured data, explanations could be inferred. The John B. Connally Building may or may not have high discrepancy with the chilled water and the non-chiller electric use. This cannot be ascertained as·cer·tain  
tr.v. as·cer·tained, as·cer·tain·ing, as·cer·tains
1. To discover with certainty, as through examination or experimentation. See Synonyms at discover.

2.
 without measuring the chiller consumption. Although the 16% overestimation o·ver·es·ti·mate  
tr.v. o·ver·es·ti·mat·ed, o·ver·es·ti·mat·ing, o·ver·es·ti·mates
1. To estimate too highly.

2. To esteem too greatly.
 of the actual energy use looks close, the simulation may or may not represent the operation of the building.

Creation of the Level 2 simulation models, which incorporated envelope details and basic system information, required an additional level of effort that varied from 10 to 13 hours. The results indicated that noticeable improvements were not obtained with the added effort over the simpler Level 1 modeling effort.

* If the simulations did not adequately represent the real operation of the various buildings, improving the level of detail in the envelope construction, schedules, and mechanical equipment may not improve the basic prediction "Prediction is very difficult, especially if it's about the future." - Niels Bohr

A prediction is a statement or claim that a particular event will occur in the future in more certain terms than a forecast.
 capabilities of the simulation.

Substantial discrepancies exist in the uncalibrated simulations. Inefficient energy use in a building should bias the simulated energy results to be less than the measured energy since the simulations typically do not incorporate large inefficiencies. The results varied with three of the four building simulations, showing that the simulated energy use was greater than the measured energy use.

The next steps need to involve taking a larger sample of buildings to build a statistical basis for conclusions and explaining the differences between the simulation results and the measured results by submetering and more detailed analysis.

REFERENCES

Ahmad, M. 2003. Systematic time-based study for quantifying the uncertainty of uncalibrated models in building energy simulations. Master's mas·ter's  
n.
A master's degree.
 thesis This article or section has multiple issues:
* It may require general cleanup to meet Wikipedia's quality standards.

Please help [ improve the article] or discuss these issues on the talk page.
This article is about the thesis in academia.
, Department of Mechanical Engineering, Texas A & M University, College Station, TX.

ASHRAE. 2002. Guideline 14-2002, Measurement of Energy and Demand Savings. Atlanta Atlanta (ətlăn`tə, ăt–), city (1990 pop. 394,017), state capital and seat of Fulton co., NW Ga., on the Chattahoochee R. and Peachtree Creek, near the Appalachian foothills; inc. 1847. : American American, river, 30 mi (48 km) long, rising in N central Calif. in the Sierra Nevada and flowing SW into the Sacramento River at Sacramento. The discovery of gold at Sutter's Mill (see Sutter, John Augustus) along the river in 1848 led to the California gold rush of  Society of Heating, Refrigerating re·frig·er·ate  
tr.v. re·frig·er·at·ed, re·frig·er·at·ing, re·frig·er·ates
1. To cool or chill (a substance).

2. To preserve (food) by chilling.
 and Air-Conditioning air-conditioning

Control of temperature, humidity, purity, and motion of air in an enclosed space, independent of outside conditions. In a self-contained air-conditioning unit, air is heated in a boiler unit or cooled by being blown across a refrigerant-filled coil and then
 Engineers, Inc.

Ayres, J.M., and E. Stamper. 1995. Historical development of building energy calculations. ASHRAE Journal 37(2):47-55.

Bou-Saada, T.E., and J.S. Haberl. 1998. Improved procedure for calibrated hourly simulation models. DOE-2 User News 18(1):25-30.

Bronson, D.J., S.B. Hinchey, J.S. Haberl, and D.L. O'Neal. 1992. A procedure for calibrating the DOE-2 simulation program to non-weather-dependent loads. ASHRAE Transactions 98(1):636-52.

Corson, G.C. 1992. Input and output sensitivity of building energy simulations. ASHRAE Transactions 98(1):618-26.

Eley. 2005. VisualDOE. Charles Eley Charles Ryves Maxwell Eley (born September 16, 1902 - died January 15, 1983) was a British rower who competed in the 1924 Summer Olympics.

In 1924 he won the gold medal as crew member of the British boat in the coxless fours event. External links
  • profile
 Associates, San Francisco San Francisco (săn frănsĭs`kō), city (1990 pop. 723,959), coextensive with San Francisco co., W Calif., on the tip of a peninsula between the Pacific Ocean and San Francisco Bay, which are connected by the strait known as the Golden , CA.

FSEC. 2005. EnergyGuage. Florida Florida, state, United States
Florida (flôr`ĭdə, flŏr`–), state in the extreme SE United States. A long, low peninsula between the Atlantic Ocean (E) and the Gulf of Mexico (W), Florida is bordered by Georgia and
 Solar Energy solar energy, any form of energy radiated by the sun, including light, radio waves, and X rays, although the term usually refers to the visible light of the sun.  Center, Cocoa Cocoa, city, United States
Cocoa, city (1990 pop. 17,722), Brevard co., E Fla., on the Indian River (a lagoon), a segment of the Intracoastal Waterway; inc. 1895. It is a tourist and arts center in a region where citrus fruits are grown. An 8-mi (12.
, FL.

Haberl, J., and S. Thamilseran. 1994. Predicting hourly building energy use: The Great Energy Predictor Shootout Shootout

Venture capital jargon. Refers to two or more venture capital firms fighting for the startup.
 II, measuring retrofit ret·ro·fit  
v. ret·ro·fit·ted or ret·ro·fit, ret·ro·fit·ting, ret·ro·fits

v.tr.
1. To provide (a jet, automobile, computer, or factory, for example) with parts, devices, or equipment not in
 savings--Overview and discussion of results. ASHRAE Transactions 100(1):1104-18.

Haberl, J.S., and T.E. Bou-Saada. 1998. Procedures for calibrating hourly simulation models to the measured building energy and environmental data. Journal of Solar Energy Engineering 120(8):193-204.

Hinchey, S.B. 1991. Influence of thermal zone assumptions on DOE-2 energy use estimations of a commercial building. Master's thesis, Department of Mechanical Engineering, Texas A & M University, College Station, TX.

IPMVP. 2002. International Performance Measurement and Verification Protocol. Efficiency Valuation Organization, Washington Washington, town, England
Washington, town (1991 pop. 48,856), Sunderland metropolitan district, NE England. Washington was designated one of the new towns in 1964 to alleviate overpopulation in the Tyneside-Wearside area.
, DC.

Jones, C.R., and C. Hepting. 2001. DOE-2.1E geometric modeling A geometric model describes the shape of a physical or mathematical object by means of geometric concepts. Geometric model(l)ing is the construction or use of geometric models. : The basic geometric approach versus the complex XYZ XYZ  
interj. Informal
Used to indicate to someone that the zipper of his or her pants is open.



[ex(amine) y(our) z(ipper).]
 approach. Proceedings from eSim 2001, Session 1-3.

Kreider, J., and J. Haberl. 1994. Predicting hourly building energy use: The result of the 1993 Great Energy Predictor Shootout to identify the most accurate method for making hourly energy use predictions. ASHRAE Journal 36(8):72-81.

Lam, J.C., and S.C.M. Hui. 1996. Sensitivity analysis of energy performance in office buildings. Building and Environment 31(1):27-39.

LoanSTAR. 2005. Hourly data for electric, chilled water, and hot water for the buildings studied. Available from the Energy Systems Laboratory, Texas A & M University, College Station, TX.

Liu, M., and D.E. Claridge. 1998. Use of calibrated HVAC system models to optimize optimize - optimisation  system operation. Journal of Solar Energy Engineering 120(5):108-13.

Reddy, T.A. 2006. Literature review on calibration of building energy simulation programs: Uses, problems, procedures, uncertainty, and tools. ASHRAE Transactions 112(1):226-40.

Torres-Nunci, N. 1989. Simulation modeling of energy consumption in Zachry Engineering Center. Master of Engineering project report, Department of Mechanical Engineering, Texas A & M University, College Station, TX.

Mushtaq Ahmad

Associate Member ASHRAE

Charles Charles, archduke of Austria
Charles, 1771–1847, archduke of Austria; brother of Holy Roman Emperor Francis II. Despite his epilepsy, he was the ablest Austrian commander in the French Revolutionary and Napoleonic wars; however, he was handicapped by
 H. Culp, PhD, PE

Fellow ASHRAE

Received June June: see month.  23, 2005; accepted April 17, 2006

Mushtaq Ahmad is a research engineering associate II in the Energy Systems Laboratory and Charles H. Culp is an associate professor in the Department of Architecture and associate director of the Energy Systems Laboratory, Texas A & M University, College Station, TX.
Table 1. Time Spent Developing the Level 1 and Level 2 Simulation Models

                                                 Additional Time Spent
                           Actual Time Spent     on the Level 2 Model
                           on the Level 1 Model  Up to 20 Additional
Building                   Up to 20 Hours        Hours

Wisenbanker Engineering    18                    13
Research Center (WERC)
Harrington Tower           20                    13
Wehner Business            22                    11
Administration Building
John B. Connally Building  16                    10

Table 2a. Description of the Envelope, Loads, and Space Conditions for
the WERC Models

                            Wisenbaker Engineering Research Center
Sections of the input file  Level 1-18 Hours Total
Loads-Level of Effort       12 Hours Spent on Loads

Envelope                    Quick construction, no thermal mass
                            considered, instantaneous heat gain/loss
                            All floors and exterior details defined
                            according to as-built drawings
                            4 floors, 8 zones
                            Conditioned and glazed area obtained from
                            field measurements and as-built drawings
Schedules                   Typical schedules for an office building
                            with 50% load on weekends to account for
                            graduate students
Shading                     No shading
Space conditions
General space               200 sq ft/person (18.6 sq m/person)
                            1.5 W/sq ft (16.1 W/sq m) for lighting
                            3.0 W/sq ft (32.3 W/sq m) for equipment
Laboratory                  300 sq ft/person (27.9 sq m/person)
                            1.5 W/sq ft (16.1 W/sq m) for lighting
                            3.5 W/sq ft (37.7 W/sq m) for equipment
                            People heat gain is 850 Btu/hr (249.1 W) for
                            slight physical work
Basement                    Treated as general space, with no ground
                            coupling of the exterior walls

                            Wisenbaker Engineering Research Center
Sections of the input file  Level 2-13 Hours Total
Loads-Level of Effort       5 Hours Spent on Loads

Envelope                    Thermal mass considered, detailed
                            construction is defined for all the envelope
                            elements
                            All floors and exterior details defined
                            according to drawings. All the interior
                            floors and ceilings defined with the correct
                            coordinates
                            3 floors + basement, 8 zones
                            Conditioned and glazed area obtained from
                            field measurements and as-built drawings
Schedules                   Typical schedules for an office building
                            with 50% load on weekends to account for
                            graduate students
Shading                     Shading due to adjacent buildings applied
Space conditions
General space               150 sq ft/person(13.9 sq m/person) (survey
                            based)
                            1.5 W/sq ft (16.1 W/sq m) for lighting
                            3.0 W/sq ft (32.3 W/sq m) for equipment
Laboratory                  300 sq ft/person (27.9 sq m/person)
                            2 W/sq ft (21.5 W/sq m) for lighting
                            3.5 W/sq ft (37.7 W/sq m) for equipment
                            People heat gain is 850 Btu/hr (249.1 W) for
                            slight physical work
Basement                    150 sq ft/person (13.9 sq m/person) (survey
                            based)
                            1.5 W/sq ft (16.1 W/sq m) for lighting
                            3.0 W/sq ft (32.3 W/sq m) for equipment

Table 2b. Description of the Schedules, Zone Commands, and System
Specifications for the WERC Models

                            Wisenbaker Engineering Research Center
Sections of the input file  Level 1-18 Hours Total
Systems-Level of Effort     6 Hours Spent on Systems

Type                        Dual Duct VAV
Schedules
Fans                        100% during peak hours, 50%
                            during weekends
Temperature                 Winter set point is 70[degrees]F
                            (21.1[degrees]C)
                            w/setback to 60[degrees]F (15.6[degrees]C),
                            Summer set point is 76[degrees]F
                            (24.4[degrees]C)
                            w/setup to 78[degrees]F (25.6[degrees]C)
Reset                       No reset for heating and cooling
Zone Commands
General space               1.0 cfm/sq ft (5.1 l/s per sq m)
                            20cfm/person (9.44 l/s per person) outside
                            air
                            Inside temperature 72[degrees]F
                            (22.2[degrees]C) for heating and
                            77[degrees]F(25[degrees]C) for cooling
Plenum                      Inside temperature 70[degrees]F
                            (21.1[degrees]C) for heating and
                            95[degrees]F(35[degrees]C)
                            for cooling
Lab                         1.0 cfm/sq ft (5.1 l/s per sq m)
                            25 cfm/person (11.8 l/s per person)outside
                            air
                            Heating design temperature 72[degrees]F
                            (22.2[degrees]C)
                            Cooling design temperature 77[degrees]F
                            (25[degrees]C)
System Specification
                            Max and min supply temperatures
                            105[degrees]F (40.6[degrees]C) and
                            55[degrees]F(12.8[degrees]C)
                            VAV cycling down to 50% of low loads

                            Wisenbaker Engineering Research Center
Sections of the input file  Level 2-13 Hours Total
Systems-Level of Effort     8 Hours Spent on Systems

Type                        7 Single Duct VAV w/terminal reheat,
                            1 Single Zone Constant Volume,
                            40 Fan Coil units
Schedules
Fans                        100% during peak hours,
                            50% during weekends
Temperature                 No setbacks,
                            Summer set point is 78[degrees]F
                            (25.6[degrees]C),
                            Winter set point is 68[degrees]F
                            (20[degrees]C)
Reset                       Only reset for cooling,
                            Supply temperature is 63[degrees]F
                            (17.2[degrees]C) if
                            outside temperature is 65[degrees]F
                            (18.3[degrees]C),
                            Set to 55[degrees]F (12.8[degrees]C) if
                            outside is at 80[degrees]F (26.7[degrees]C)
Zone Commands
General space               Form spec sheets, varies by zone
                            Form spec sheets, varies by zone
                            Inside temperatures are the same as
                            thrmostat setpoints
Plenum                      Inside temperature 70[degrees]F
                            (21.1[degrees]C) and 95[degrees]F
                            (35[degrees]C) for cooling
Lab                         1.0 cfm/sq ft (5.1 l/s per sq m)
                            2000 cfm (944 l/s) (from design spec sheets)
                            Heating design temperature 70[degrees]F
                            (21.1[degrees]C)
                            Cooling design temperature 95[degrees]F
                            (35[degrees]C)
System Specification
                            Max and min supply temperatures
                            105[degrees]F (40.6[degrees]C) and
                            55[degrees]F(12.8[degrees]C)
                            VAV cycling down to 50% of low loads, the
                            temperature rise across the reheat coil is
                            50[degrees]F(10[degrees]C), cool reset is
                            being used with the fan coil units, the rest
                            of the details are from the spec sheets

Table 3. Comparison of Modeled to Measured 1999 Annual Energy
Consumption for WERC

                              Yearly consumption Comparisons
Wisenbaker Engineering                                Measured
Research Center-1999          Level 1     Level 2     Data

Whole Building Electric  kWh   5,618,288   5,813,692   4,414,958
Chilled Water            kWh   5,813,692   5,274,575  10,337,535
Hot Water                kWh      48,448     133,124   2,199,070
Total Energy             kWh  11,480,429  11,199,066  16,951,564

Wisenbaker Engineering        Percent Discrepancy
Research Center-1999          Level 1  Level 2

Whole Building Electric  kWh  -27.3%   -31.2%
Chilled Water            kWh   43.8%    49.0%
Hot Water                kWh   97.8%    93.9%
Total Energy             kWh   32.3%    33.9%

Table 4. Comparison of Modeled to Measured 2004 Annual Energy
Consumption for WERC (2004 Post-Commissioning Data)

                              Yearly Consumption Comparisons
Wisenbaker Engineering                                Measured
Research Center-2004          Level 1     Level 2     Data

Whole Building Electric  kWh   5,618,165   5,783,975   4,213,678
Chilled Water            kWh   5,817,506   5,271,995   8,702,776
Hot Water                kWh      56,170     176,873   1,228,368
Total Energy             kWh  11,491,842  11,235,843  14,144,821

Wisenbaker Engineering        Percent Discrepancy
Research Center-2004          Level 1  Level 2

Whole Building Electric  kWh  -33.3%   -37.3%
Chilled Water            kWh   33.2%    39.4%
Hot Water                kWh   95.4%    85.6%
Total Energy             kWh   18.8%    20.6%

Table 5. Comparison of Modeled to Measured Annual Energy Consumption for
Harrington Tower

                              Yearly Consumption Comparisons
                                                    Measured
Harrington Tower              Level 1    Level 2    Data

Whole Building Electric  kWh  2,248,804  2,706,987  2,515,397
Chilled Water            kWh  2,830,861  3,909,037  2,088,130
Hot Water                kWh     61,220    822,574    415,563
Total Energy             kWh  5,140,886  7,438,598  5,019,091

                               Percent Discrepancy
Harrington Tower               Level 1  Level 2

Whole Building Electric  kWh    10.6%    -7.6%
Chilled Water            kWh   -35.6%   -87.2%
Hot Water                kWh    85.3%   -97.9%
Total Energy             kWh    -2.4%   -48.2%

Table 6. Comparison of Modeled to Measured Annual Energy Consumption for
the Wehner Business Administration Building

                              Yearly Consumption Comparisons
Wehner Business                                      Measured
Administration Building       Level 1    Level 2     Data

Whole Building Electric  kWh  4,231,335   3,481,477  2,439,598
Chilled Water            kWh  4,435,576   6,257,961  3,527,834
Hot Water                kWh    243,156     655,109  1,850,679
Total Energy             kWh  8,910,067  10,394,547  7,818,112

Wehner Business               Percent Discrepancy
Administration Building       Level 1  Level 2

Whole Building Electric  kWh  -73.4%   -42.7%
Chilled Water            kWh  -25.7%   -77.4%
Hot Water                kWh   86.9%    64.6%
Total Energy             kWh  -14.0%   -33.0%

Table 7. Comparison of Modeled to Measured Annual Energy Consumption for
the John B. Connally Building

                              Yearly Consumption Comparisons
                                                    Measured
John B. Connally Building     Level 1    Level 2    Data

Whole Building Electric  kWh  2,840,789  2,872,021  2,470,157

                              Percent Discrepancy
John B. Connally Building     Level 1  Level 2

Whole Building Electric  kWh  -15.0%   -16.3%

Table 8. Percent Discrepancy Comparison

                           Electric          CHW
Sites                      Level 1  Level 2  Level 1  Level 2

Wisenbaker Engineering     -27.3%   -31.2%    43.8%    49.0%
Resear Center (1999)
Wisenbaker Engineering     -33.3%   -37.3%    33.2%    39.4%
Resear Center (2004)
Harrington Tower            10.6%    -7.6%   -35.6%   -87.2%
Wehner Business            -73.4%   -42.7%   -25.7%   -77.4%
Administration Building
John B. Connally Building  -15.0%   -16.3%   N/A      N/A

                           HW                Total
Sites                      Level 1  Level 2  Level 1  Level 2

Wisenbaker Engineering     97.8%     93.9%    32.3%    33.9%
Resear Center (1999)
Wisenbaker Engineering     95.4%     85.6%    18.8%    20.6%
Resear Center (2004)
Harrington Tower           85.3%    -97.9%    -2.4%   -48.2%
Wehner Business            86.9%     64.6%   -41.0%   -33.0%
Administration Building
John B. Connally Building  N/A      N/A      -15.0%   -16.0%
COPYRIGHT 2006 American Society of Heating, Refrigerating, and Air-Conditioning Engineers, Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2006 Gale, Cengage Learning. All rights reserved.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Author:Ahmad, Mushtaq; Culp, Charles H.
Publication:HVAC & R Research
Geographic Code:1USA
Date:Oct 1, 2006
Words:6599
Previous Article:Simulation model of a low-temperature supermarket refrigeration system.
Next Article:Carbon dioxide: blessing or curse?
Topics:



Related Articles
Cosmic computing: simulating the universe.
Introducing molecular life science students to model building using computer simulations.
An empirical validation of modeling solar gains through a glazing nit using building energy simulation programs.
Two-dimensional CFD and conduction simulations of heat transfer in horizontal window frames with internal cavities.
Comparative analysis of CFD [DELTA]P vs. measured [DELTA]P for compressed flexible ducts.
Impact of solar models on building energy analysis for tropical sites.
Calibrating detailed building energy simulation programs with measured data--Part I: general methodology (RP-1051).
Calibrating detailed building energy simulation programs with measured data--Part II: application to three case study office buildings (RP-1051).
Validation of a coupled multizone-CFD program for building airflow and contaminant transport simulations.
Computer simulations and experimental measurements of air distribution in buildings: past, present, and future.

Terms of use | Copyright © 2014 Farlex, Inc. | Feedback | For webmasters