Transitioning an ACTD to an acquisition program: lessons learned from Global Hawk.Earlier this year, the Air Force deployed two production Global Hawk aircraft in support of the global war on terror This article is about U.S. actions, and those of other states, after September 11, 2001. For other conflicts, see Terrorism. The War on Terror (also known as the War on Terrorism . These air vehicles replaced Advanced Concept Technology Demonstration (ACTD ACTD Advanced Concept Technology Demonstration/Demonstrator (US DoD) ACTD A Call to Duty (Star Trek) ACTD Advanced Concept Technical Demonstration ACTD Australian Conference of TAFE Directors ) prototype aircraft that had deployed three different times to Southwest Asia Southwest Asia or Southwestern Asia (largely overlapping with the Middle East) is the southwestern portion of Asia. The term Western Asia is sometimes used in writings about the archeology and the late prehistory of the region, and in the United States subregion in the last five years. Production Global Hawks and associated support In naval air operations, assistance provided by a force or unit to another force or unit that is under independent tactical control, neither being subordinate to the other. See also direct support; support. elements were available to support today's urgent global war on terror needs, less than five years after the start of the acquisition program, because the Department of Defense made the decision in 2001 to transition the program directly from the ACTD phase into simultaneous development and production. The positive reports on the performance and contribution of the production hardware validate the decision to rapidly transition the program into production. In executing this nontraditional acquisition model, we've learned a number of lessons that should be applied to future programs following a similar path. [ILLUSTRATION OMITTED] Early Days of the Global Hawk Program The Defense Advanced Research Projects Agency Defense Advanced Research Projects Agency (DARPA), U.S. government agency administered by the Department of Defense (see Defense, United States Department of). (DARPA DARPA: see Defense Advanced Research Projects Agency. (Defense Advanced Research Projects Agency) The name given to the U.S. Advanced Research Projects Agency during the 1980s. It was later renamed back to ARPA. ) initiated the Global Hawk ACTD program in 1995. The objective was to rapidly develop a high-altitude, long-endurance unmanned aerial vehicle A powered, aerial vehicle that does not carry a human operator, uses aerodynamic forces to provide vehicle lift, can fly autonomously or be piloted remotely, can be expendable or recoverable, and can carry a lethal or nonlethal payload. system capable of providing broad-area surveillance. The contractor team, led by Teledyne Ryan, developed the concept of a Global Hawk system consisting of three primary hardware elements: the Global Hawk air vehicle, the mission control element, and the launch and recovery element. The system architecture provided for command and control and transmission of surveillance information via a line-of-site data link or a satellite communication link. After a successful first flight in 1998, DARPA transferred program management responsibility to the Air Force. Over the next two years, the Years, The the seven decades of Eleanor Pargiter’s life. [Br. Lit.: Benét, 1109] See : Time Air Force employed Global Hawk in a series of exercises, demonstrations, and deployments, culminating in a military utility assessment (MUA (Mail User Agent) An e-mail client program. See messaging system. MUA - Mail User Agent ) report that recommended expeditious ex·pe·di·tious adj. Acting or done with speed and efficiency. See Synonyms at fast1. ex fielding of an operationalized version of the ACTD hardware. This resulted in DoD's establishing an acquisition category (ACAT ACAT See: Automated Customer Account Transfer ) ID program and approving the simultaneous start of engineering and manufacturing development (EMD EMD Electromechanical dissociation, see there ) and low rate initial production (LRIP LRIP Low Rate Initial Production LRIP Limited Rate Initial Production LRIP Logistics Readiness Improvement Program ) in March 2001. In November 2001, the Air Force deployed Global Hawk ACTD hardware to Southwest Asia to meet an urgent Central Command request for persistent, broad-area reconnaissance and surveillance for Operation Enduring Freedom. The system deployed two subsequent times over the next four years and received rave reviews for its role in CENTCOM CENTCOM US Central Command CENTCOM Coalition Central Command operations. Global Hawk proved especially effective during the Iraq invasion (see imagery on page 11). With just one air vehicle deployed, the system was credited with identifying 38 percent of Iraq's armor and 55 percent of the time-sensitive air defense targets using electro-optical (EO), infrared (IR), and synthetic aperture radar Synthetic aperture radar (SAR) Radar, airborne or satellite-borne, that uses special signal processing to produce high-resolution images of the surface of the Earth (or another object) while traversing a considerable flight path. (SAR (Segmentation And Reassembly) The protocol that converts data to cells for transmission over an ATM network. It is the lower part of the ATM Adaption Layer (AAL), which is responsible for the entire operation. See AAL. SAR - segmentation and reassembly ) images to target Iraqi forces. These early combat deployments demonstrated the effectiveness of carrying multiple sensor capabilities on the same platform. When the production air vehicles deployed earlier this year, the ACTD hardware had accumulated more than 5,000 hours of combat time and had built a reputation for effectively meeting unique global war on terror challenges. The capability of the air vehicle to fly unrefueled for more than 30 hours allowed it to remain airborne for extended periods and eliminate sanctuary for terrorists attempting to rapidly blend in Verb 1. blend in - blend or harmonize; "This flavor will blend with those in your dish"; "This sofa won't go with the chairs" blend, go fit, go - be the right size or shape; fit correctly or as desired; "This piece won't fit into the puzzle" with the local population. The ability of the system to operate at 65,000 feet along with its long-range sensors allowed a single air vehicle to provide surveillance over a wide area. These system attributes convinced leadership to divert the first production hardware from a training unit to replace the ACTD hardware that was approaching the end of its useful life. The production hardware has already accumulated more than 1,000 hours of successful combat time. Lessons Learned While supporting three combat deployments with ACTD hardware, we have now accumulated more than five years' experience executing the formal acquisition program. The nontraditional acquisition strategy that resulted from transitioning an ACTD into combined EMD/LRIP has created several challenges for the government/contractor team. Our hope is that future programs will benefit from what we've learned the hard way. Revise Operational Test Approach and Definitions Current Title 10 requirements and guidelines don't align well with the Global Hawk acquisition strategy. Traditional guidelines call for remaining in an LRIP status and recommend limiting quantities to 10 percent of the planned production buy until completion of initial operational test and evaluation (testing) Initial Operational Test and Evaluation - (IOT&E) The first phase of operational test and evaluation conducted on pre-protectional items, prototypes, or pilot production items and normally completed prior to the first major production decision. (IOT IOT In Order To IOT Index-Organized Table IOT British Indian Ocean Territory (ISO 3-letter country code) IOT Interoperability Testing IOT Initial Operational Test IOT In-Orbit Test & E). This approach works reasonably well for a sequential acquisition strategy, but becomes problematic when EMD and LRIP run simultaneously. With Global Hawk, this dilemma is further aggravated ag·gra·vate tr.v. ag·gra·vat·ed, ag·gra·vat·ing, ag·gra·vates 1. To make worse or more troublesome. 2. To rouse to exasperation or anger; provoke. See Synonyms at annoy. by the relatively small production run. In the first two production lots, the Air Force committed to six air vehicles, already exceeding 10 percent of the planned buy of 54. The current program plan projects an IOT & E event in 2008-2009 when the Air Force will have already committed to more than 50 percent of production. The critical path elements driving the IOT & E schedule are not production hardware deliveries, but the process of putting in place the support elements intended for long-term system operation. [ILLUSTRATION OMITTED] The Global Hawk acquisition strategy calls for a different approach to execute the important role of operational test. Programs like Global Hawk need to place greater reliance on "seamless verification," the term coined to describe the merging of developmental and operational test (DT and OT) requirements. We need to leverage each test event to accomplish both DT and OT objectives, while protecting the right of operational testers to report independently. These combined test activities could be supplemented with small, dedicated OT events as meaningful increments of technology are spiraled into production hardware. In the case of deployed systems like Global Hawk, these dedicated OT events should leverage deployed activity as much as possible. Why try to simulate the combat environment if we can assess the system in actual combat? Finally, this revised OT concept must accommodate a build-up approach to the mature support concept. In a traditional program, the support concept is defined during the development phase. With simultaneous development and production, the support concept will mature as the system is fielded. As technology is spiraled into the production hardware, we must spiral the support concept and not wait until the desired end state to conduct operational testing (testing) operational testing - A US DoD term for testing performed by the end-user on software in its normal operating environment. . Accelerate Logistics Planning During the Global Hawk ACTD phase, neither DARPA nor the Air Force made significant investments in logistics planning. This corresponded with the ACTD philosophy of rapidly developing prototype hardware and putting it in the hands of operators to assess the system's military utility. Program investment was intentionally limited until the system's value had been assessed. This was a reasonable approach but created logistics challenges when the program quickly transitioned into production. [GRAPHIC OMITTED] In a more traditional acquisition strategy, logistics planning occurs during the EMD phase, typically in a logistics support analysis Logistics Support Analysis (LSA) is an activity within Integrated Logistics Support which generates a Logistics Support Analysis Record (LSAR) External References
In retrospect, we should have started logistics planning much sooner. In fact, we missed a great opportunity to jump-start the process in 1999. When initial MUA results made it clear that DoD would be transitioning the ACTD into an acquisition program, the Air Force awarded a "pre-EMD" contract. This was a bridge contract to resolve limited technical issues while we completed the MUA and the milestone decision process. The pre-EMD contract would have been a useful mechanism to start logistics planning that would include defining support equipment requirements and using ACTD test data to populate To plug in chips or components into a printed circuit board. A fully populated board is one that contains all the devices it can hold. a spares planning model. This approach would have provided a basis for defining early logistics strategies and applying them to the first production lot contracts. Assess ACTD Contractor Ability to Execute Large Acquisition Program DARPA awarded the original Global Hawk ACTD contract in 1995 to a contractor team led by Teledyne Ryan, who had a rich history with unmanned aerial vehicles
[ILLUSTRATION OMITTED] The program management tools and personnel skills sufficient to manage a smaller effort were not adequate to run a large ACAT ID program. One example is the lack of an overarching integrated master schedule (IMS (1) See IP Multimedia Subsystem. (2) (Information Management System) An early IBM hierarchical DBMS for IBM mainframes. IMS was widely implemented throughout the 1970s under MVS and continues to be used under z/OS. ) that linked all aspects of the program, including the different EMD spirals, production lots, and deployment activities. An ad hoc For this purpose. Meaning "to this" in Latin, it refers to dealing with special situations as they occur rather than functions that are repeated on a regular basis. See ad hoc query and ad hoc mode. process of individual IMSs for distinct program elements was sufficient to execute the smaller ACTD program but was not adequate to identify bottlenecks in the more complex program. Two other important processes that were not sufficiently mature were the risk management process and the earned value management Earned Value Management (commonly abbreviated and referred to just as EVM) is a project management technique that seeks to measure forward progress in an objective manner. EVM is touted as having a unique ability to combine measurements of technical performance (i.e. system. Northrop Grumman has now tapped expertise from across the corporation and put more robust processes in place, but the transition did not occur fast enough to prevent program perturbations. In fact, the program is currently completing a Nunn-McCurdy certification process for breaching program cost targets, in part because we did not have the proper tools in place early in the program. There is no doubt Teledyne Ryan was an excellent choice to run the ACTD program. However, the Air Force faced a crossroad when transitioning the program into EMD/LRIP. We should have considered two options: first, re-competing the program to select a team better equipped to manage a larger effort; or second, working aggressively with the existing contractor team to put the proper tools and skills in place. In reality, we didn't execute either option. The Air Force awarded the follow-on contract to Northrop Grumman to keep the program moving forward, but we didn't adequately evaluate the contractor team's readiness to handle the larger program. At this point we have conducted a government-contractor assessment and corrected most of the identified tools/skills deficiencies. In retrospect we should have completed this step much earlier, as we were transitioning the program out of the ACTD phase. Pursue More Measured Approach to Capability Improvements In transitioning the program into EMD/LRIP, DoD's goal was to field an operationalized version of the ACTD hardware while using spiral development to add incremental capability enhancements. One of our major challenges was defining which enhancements were absolutely required to achieve an operationalized system, and which could be deferred for later delivery. Our extensive deployment and combat experience with ACTD hardware added fuel to the debate. To reflect many of the lessons learned in combat, we modified existing contracts and incorporated enhancements into the first production hardware as it was being built. There has been a cost and schedule impact, but most of these capabilities are essential for mission accomplishment. In some cases we should have deferred desired enhancements through a more measured development process. One example is a capability known as automatic contingency generation (ACG ACG American College of Gastroenterology; angiocardiography; apexcardiogram. AcG accelerator globulin (coagulation factor V). AcG accelerator globulin (clotting factor V). ). In an in-flight emergency, ACG enables an air vehicle to autonomously determine the optimum flight path to divert to an alternative airfield while avoiding predetermined pre·de·ter·mine v. pre·de·ter·mined, pre·de·ter·min·ing, pre·de·ter·mines v.tr. 1. To determine, decide, or establish in advance: no-fly zones. The current approach is to rely on manual re-routing by the pilot during a mission. ACG would eliminate multiple steps in building a mission plan and shrink mission-planning cycle time below the requirement threshold. This requirement was documented after we negotiated early production lots, but we decided to add it to the first production baseline. In retrospect, we did not fully understand the complexity of ACG, and it quickly became the critical-path item in fielding the first production hardware. We have now deferred this capability to a future software release, but the time spent trying to field ACG in the first baseline delayed delivery delayed delivery Delivery of a certificate after the day on which delivery would occur with a regular-way contract. Delayed delivery is sometimes specified by the seller when the order to sell is entered. See also seller's option contract. of the first production hardware and training courses. While fielding production hardware in combat within five years of program start is noteworthy, we could have achieved this milestone even earlier had we tackled only those capability enhancements absolutely required for the first production baseline. Accelerate Manufacturing Planning In a traditional acquisition strategy, manufacturing planning and process development are important elements of EMD, representing the "M" in EMD. When we launched Global Hawk into simultaneous EMD/LRIP, we had done little production planning Production planning The function of a manufacturing enterprise responsible for the efficient planning, scheduling, and coordination of all production activities. ; we simply continued ACTD processes. This worked reasonably well for the first production lot, but we quickly ran into trouble on Lot 2. With the addition of Navy requirements for a maritime demonstration, the second lot grew to six air vehicles and multiple ground stations. This required a production rate the program was not ready to handle. [ILLUSTRATION OMITTED] One pacing item became delivery of the primary air vehicle payload, the Integrated Sensor Suite (ISS ISS See Institutional Shareholder Services (ISS). ) shown on page 9. During the ACTD phase, Raytheon built the ISS in a laboratory using a labor-intensive process. This approach was appropriate for the limited ACTD purchase but was not efficient for a longer production run. In the rapid transition to production, we allocated neither the time nor funding to plan for efficient production. This became painfully obvious as Raytheon struggled to apply ACTD processes and meet the steep ramp-up for Lot 2 ISS deliveries. We have now recovered from this early challenge. In the case of the ISS, Raytheon has laid out a state-of-the-art, lean manufacturing Lean manufacturing is the production of goods using less of everything compared to mass production: less human effort, less manufacturing space, less investment in tools, and less engineering time to develop a new product. process made possible by a $30 million Air Force investment in specialized test equipment (STE STE Saint (French) STE Suite (US Postal Service) STE Societe (French: Society) STE Spanning Tree Explorer STE Software Test Engineer ). Looking back, we needed to start manufacturing planning much earlier than we did. We could have used the pre-EMD contract described earlier to start planning an ACTD-to-LRIP production transition. In addition the Air Force should have included funding in the first production estimates for STE. In our rush to accelerate Global Hawk into production, we budgeted for hardware but didn't include estimates for STE needed to implement efficient production processes. We now know some amount of STE would have paid for itself with reduced production cost and was essential as we increased quantities. Putting It Together The rapid transition of Global Hawk from the ACTD phase into formal acquisition has achieved its primary objective: breaking the historical paradigm of lengthy acquisition cycle time. The Air Force deployed Global Hawk production hardware to Southwest Asia less than five years into the acquisition program, and the system is making a major contribution in CENTCOM combat operations. We did not have a template to follow in executing the nontraditional acquisition strategy that achieved this milestone, and we have encountered several challenges along the way. With careful planning and early commitment of resources, we believe programs that follow us can overcome these challenges and yield the same cycle time reduction achieved in the Global Hawk experience. The authors welcome comments and questions. Contact them at scott.coale@wpafb.af.mil and george.guerra@ngc.com. Col. G. Scott Coale, USAF * George Guerra Coale is the commander of the Reconnaissance Systems Wing, responsible for managing the development, production, and fielding of Air Force airborne reconnaissance systems. Guerra is the Northrop Grumman program manager for the Air Force Global Hawk program. |
|
||||||||||||||||||||

Printer friendly
Cite/link
Email
Feedback
Reader Opinion