The cultural sources of acquisition risk: Part II.


In Part I of this article (Defense AT & L, September-October 2005), I argued that acquisition risks can be perceived through multiple lenses and that a cultural lens can often expose the underlying root causes of program risks. To substantiate my argument, I explored the first three of seven features of acquisition culture that are implicated im·pli·cate  
tr.v. im·pli·cat·ed, im·pli·cat·ing, im·pli·cates
1. To involve or connect intimately or incriminatingly: evidence that implicates others in the plot.

2.
 in program risk: the reification re·i·fy  
tr.v. re·i·fied, re·i·fy·ing, re·i·fies
To regard or treat (an abstraction) as if it had concrete or material existence.



[Latin r
 of risk, the unreality of schedule, and the pretense of a stable requirements baseline. In Part II, I discuss the remaining four culprits. The consideration of all seven aspects is a starting point Noun 1. starting point - earliest limiting point
terminus a quo

commencement, get-go, offset, outset, showtime, starting time, beginning, start, kickoff, first - the time at which something is supposed to begin; "they got an early start"; "she knew from the
 for cultivating a keener cultural viewpoint of the system in which we must work and succeed.

The Avoidance of Adequate Reserve

Norman Augustine, the former CEO (1) (Chief Executive Officer) The highest individual in command of an organization. Typically the president of the company, the CEO reports to the Chairman of the Board.  of Lockheed Martin For the former company, see .

Lockheed Martin (NYSE: LMT) is a leading multinational aerospace manufacturer and advanced technology company formed in 1995 by the merger of Lockheed Corporation with Martin Marietta.
, observed in his 1996 Woodruff Lecture:
  The difference between a great manager and a good manager is reserves.
  With virtually all of the problems I've discussed, we find people who
  are operating under pressures related to time or money or both. Under
  such circumstances, there is a tendency to err on the side of
  whatever keeps the project on time or on budget--and this can be
  disastrous, as demonstrated by the Kansas City hotel walkways and the
  Challenger events.... It seems clear that managing under uncertainty
  means managing with reserves. Financial reserves, schedule reserves,
  and performance reserves.


A lot of us agree with Augustine, yet our acquisition culture is designed to severely limit reserves. Industry students in DAU's PMT See photomultiplier tube. 401 course consistently report that a management reserve of 10 percent is the upper limit that their corporate management will tolerate; there seems to be a belief that higher reserves would render them uncompetitive. Yet it seems clear that the amount of management reserve should reflect perceived uncertainties and risks, which may justify more than 10 percent.

Government PMT401 students report that they can't keep any reserve at their end. If they are fortunate enough to have a reserve--for example, when the amount of contract award is less than what was budgeted--it is quickly swept away by other, under-funded programs.

One reported response is, "Build reserve in"--that is, design the work breakdown structure (project) Work Breakdown Structure - (WBS) A division of a project into tasks and subtasks. The tasks are numbered to indicate their relationship to each other. WBSs are indespensible for project planning, particularly when estimating time and resource requirements.  and the constituent work packages with sufficient funds to address contingencies, should they occur. The problem with this approach is that the reserve is implicit, scattered, and, therefore, difficult to access, allocate, and control.

Numerous classroom discussions on this topic have suggested to me that program reserves actually take four distinct guises:

1. Confidence Reserve. An 80 percent confidence level dictates significantly longer schedule and higher cost than a 50 percent confidence. The higher confidence is a kind of reserve. The higher the required confidence, the more contingency time and contingency dollars are factored in.

2. Reserve between threshold and objective. As long as the plan is to fund and schedule for objectives, then the difference between threshold and objective is a reserve available to the PM.

3. Government PM's reserve--funded versus obligated ob·li·gate  
tr.v. ob·li·gat·ed, ob·li·gat·ing, ob·li·gates
1. To bind, compel, or constrain by a social, legal, or moral tie. See Synonyms at force.

2. To cause to be grateful or indebted; oblige.
. When the winning bid is less than the government budgeted for, the difference is a potential reserve, but only if the PM can hold on to this excess money.

4. Contractor's management reserve. The contractor will set aside, from the money that the government obligates, a certain amount for reserve.

The problem is that all four kinds of reserve seem to be in chronically short supply.

1. Confidence levels tend to be overstated o·ver·state  
tr.v. o·ver·stat·ed, o·ver·stat·ing, o·ver·states
To state in exaggerated terms. See Synonyms at exaggerate.



o
 at program inception, and when confidence in schedule declines, rather than replanning for higher confidence, the program may limp along with little chance of making its commitments.

2. Thresholds may be substituted for objectives early in the program, erasing the reserve.

[ILLUSTRATION OMITTED]

3. Funds not obligated are taken away.

4. The contractor uses its reserve to solve problems early in the program.

It is a seeming dysfunction of our acquisition culture that we can all agree with Augustine on the one hand, but cannot follow his advice on the other.

One avenue for future research is to compare the use of reserves between the United States United States, officially United States of America, republic (2005 est. pop. 295,734,000), 3,539,227 sq mi (9,166,598 sq km), North America. The United States is the world's third largest country in population and the fourth largest country in area.  defense acquisition system and that of Australia. In Australia, program managers are entitled to build a 20 percent level of reserve into their acquisition budgets, and the culture is such that that reserve is quarantined against other use. Research might reveal quantifiable benefits of the Australian system that would suggest useful changes in the U.S. system.

Substantial Overtime as Standard Practice

Visit any high-visibility, ACAT ACAT

See: Automated Customer Account Transfer
 I or II program office, and you will see the staff working extraordinarily long days. For many, a 50- to 60-hour week has become an established routine. The thinking often goes, "The office is understaffed, and the workload is growing. There's no alternative but to roll up our sleeves, brew some more coffee, and work late." This work ethic work ethic
n.
A set of values based on the moral virtues of hard work and diligence.


work ethic
Noun

a belief in the moral value of work
 goes largely unchallenged. There appears to be a widespread belief in the acquisition culture that long hours go with the territory.

The cultural subtlety that may be overlooked is the extent to which this belief becomes self-fulfilling. Over time, schedules may implicitly assume 50-hour weeks. Over time, people may become accustomed to forfeiting use-or-lose vacations. And over time, it may become routine for people to think, at 10 a.m., "I don't need to work on that task right now. After all, I'll still be here at seven tonight, and I can work on it then, when things are quieter."

It seems to me reasonable to ask to what extent the 50-hour week is a cultural convention rather than a requisite reality? One avenue for future research would be to experiment with 40-hour offices--offices where the lights are turned out at 6 p.m., and the people forcibly forc·i·ble  
adj.
1. Effected against resistance through the use of force: The police used forcible restraint in order to subdue the assailant.

2. Characterized by force; powerful.
 ejected. Would such an office necessarily underperform its 50-hour brethren? Or is it possible the 40-hour office would adapt and get the work done anyway?

If a formal experiment is infeasible, researchers might identify acquisition programs (in other nations or industries) that discourage overtime then perform cross-cultural comparisons with U.S. defense acquisition. If such comparison revealed little difference in success, it might suggest that overtime in our culture is more of a self-fulfilling belief than a necessity.

Denunciation DENUNCIATION, crim. law. This term is used by the civilians to signify the act by which au individual informs a public officer, whose duty it is to prosecute offenders, that a crime has been committed. It differs from a complaint. (q.v.) Vide 1 Bro. C. L. 447; 2 Id. 389; Ayl. Parer.  of Pessimists

It's clear from both our PMT401 case studies and the spirited student discussions that ensue en·sue  
intr.v. en·sued, en·su·ing, en·sues
1. To follow as a consequence or result. See Synonyms at follow.

2. To take place subsequently.
, that the ACAT I or II program office is no place for a pessimist. Perhaps more than any other quality, a can-do attitude is prized in such milieux. The problem is that a pervasive can-do attitude feeds people's tendency for optimistic op·ti·mist  
n.
1. One who usually expects a favorable outcome.

2. A believer in philosophical optimism.



op
 estimation. In Smart Choices: A Practical Guide to Making Better Decisions, Hammond, Keeney, and Raiffa demonstrate that people habitually harbor exaggerated confidence in their own abilities to estimate and to perform. This phenomenon explains, for example, why 90 percent of the workforce considers itself to be in the top 10 percent of performance.

When the same bias enters acquisition plans and schedules, it can be toxic. The problem is that an optimistic bias is so ingrained in the culture and into human nature itself, that it is hard to recognize and remove. A credible pessimist is perhaps the best antidote.

One class of projects seems to self-correct against optimistic bias. I call them "drop-dead projects." Projects that have an absolute drop-dead date that it is logically impossible to extend (spacecraft launch windows and repair of Y2K See Y2K problem and Y2K compliant.

Y2K - Year 2000
 software bugs A problem that causes a program to produce invalid output or to crash (lock up). The problem is either insufficient logic or erroneous logic. For example, a program can crash if there are not enough validity checks performed on the input or on the calculations themselves, and the computer  are two that come to mind) will temper optimism and trigger a sober, realistic appraisal.

An avenue for future research might be to compare dropdead programs to conventional ones, especially with respect to how pessimistic views are tolerated. Does tolerance of pessimism result in more accurate plans and schedules?

Slipping in Chunks

Our tolerance for unreal schedules (see Part I) seems to guarantee that when reality finally does catch up, we won't slip the program schedule slightly but will restructure the program and delay delivery by six months or more. At the same time, it seems a matter of simple logic that a defense acquisition program gets six months behind by slipping a week at a time.

In the PMT401 cases that deal with restructuring of programs, the slips in schedule and the overruns in budget come in large, tectonic tectonic /tec·ton·ic/ (tek-ton´ik) pertaining to construction. , earth-trembling chunks. Why is it that the defense acquisition culture seems to accommodate large quantum slips but won't acknowledge the week-long slips of which they are composed?

Our acquisition culture often admonishes PMs not to hide bad news but raise it quickly to the attention of higher management and other stakeholders Stakeholders

All parties that have an interest, financial or otherwise, in a firm-stockholders, creditors, bondholders, employees, customers, management, the community, and the government.
. Yet at the same time, a week's slip (or two or three) in schedule doesn't seem to meet a culturally implicit threshold for replanning and advising program stakeholders. Six (or eight or 10) months rise to the occasion and will trigger the reporting of bad news to all concerned.

This phenomenon also relates to the prevalent spirit of optimism within a program office, which may lead the people to conclude that a delay of a week or two can be overcome during the months ahead (even though historically it rarely is). Only when the weeks add up to a substantial slip and it's extremely unlikely, if not impossible, to overcome the cumulative delay, does the bad news come out.

This might just be a harmless peculiarity of our culture, except that as we embrace systems-of-systems as the backbone of network-centric warfare Network-centric warfare (NCW), now commonly called network-centric operations (NCO), is a new military doctrine or theory of war pioneered by the United States Department of Defense. , slippages in one program are the concern of many other programs. The Joint Tactical Radio System (JTRS JTRS Joint Tactical Radio System
JtRS Just The Right Shoe
JTRS Just the Right Size
JTRS Johnson Technical Reports Server
JTRS Joint Tenancy with Right of Survivorship
JTRS Jefferson Township Rescue Squad
) stands at the nexus of many weapon systems' implementation plans. So a slip in the delivery schedule for JTRS has long-reaching ripple effects ripple effect Epidemiology See Signal event. . When a program's slippages emerge only in large chunks, it is severely disruptive to other programs that depend on it.

Researchers might consider finding and studying acquisition programs in other venues, such as foreign nations or commercial industry, that allow for replanning in smaller increments (slipping a week or two at a time). What benefits (if any) arise for the visibility and control of such projects? What detriments (if any) emerge?

It's the Culture

"It's the culture, stupid." Bumper-sticker wisdom, perhaps, but that phrase may synthesize To create a whole or complete unit from parts or components. See synthesis.  a key learning outcome of DAU's case-based course in defense acquisition.

I think one reason that students value their 10-week experience in PMT401 is that our cases expose sometimes subtle inconsistencies, foibles, fallacies This is a list of fallacies. Formal fallacies
Formal fallacies are arguments that are fallacious due to an error in their form or technical structure.
  • Argument from fallacy
, and other dysfunctions that lace the cultural landscape of defense acquisition. A case may expose a cultural assumption that has gone largely unquestioned and serve it up for questioning. Or it may highlight a practice that people undertake automatically and ask if there is a better way. Or it may describe a decision maker's tough call and ask if there was a way to reframe Re`frame´   

v. t. 1. To frame again or anew.
 the problem so that a different option would emerge. In each instance, the culture of the acquisition system is under the microscope. In the process, our students learn to prepare for the potholes of defense acquisition culture before driving into them. They also learn how to adapt to cultural shocks as they occur and how to influence positive change in the acquisition culture over time.

I've also concluded that as long as important acquisition risks are rooted in the culture of defense acquisition, program management will remain largely an art. Navigating through the vagaries of a complex and sometimes dysfunctional culture requires a lot of walking around, relationship-building, bargaining, compromising, and imagination. Part of our job as educators at DAU DAU - /dow/ [German Fidonet] D"ummster Anzunehmender User. A German acronym for stupidest imaginable user. From the engineering-slang GAU for Gr"osster Anzunehmender Unfall (worst foreseeable accident), especially of a LNG tank farm plant or something with similarly disastrous  is to help students master this art.

The author welcomes comments and questions. He can be contacted at chris.roman@dau.mil.

Roman is a professor of acquisition management at the Defense Acquisition University. He has held a succession of acquisition jobs in the information technology career field. He holds a doctorate in information and decision systems from The George Washington University George Washington University, at Washington, D.C.; coeducational; chartered 1821 as Columbian College (one of the first nonsectarian colleges), opened 1822, became a university in 1873, renamed 1904. .
COPYRIGHT 2005 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:RISK MANAGEMENT
Author:Roman, Christopher S.
Publication:Defense AT & L
Geographic Code:1USA
Date:Nov 1, 2005
Words:1953
Previous Article:Global cooperation: from idea to reality.(INTERNATIONAL DEFENSE COOPERATION)
Next Article:The simplicity cycle: simplicity and complexity in design.(SYSTEM DESIGN)
Topics:



Related Articles
A global blueprint for midsize companies.
What a Blessing She Had Chloroform: The Medical and Social Response to the Pain of Childbirth from 1800 to the Present.(Review)
Developing Cross-cultural Competence: A Guide for Working with Children and Their Families.
Cross-cultural challenges when doing business in China.(Research Note)
Parts repair ordering system.(Education And Training)
Best value source selection: the Air Force approach, Part II.(BEST PRACTICES)
Managing risk: a skeptic's view of Basel II.
The cultural sources of acquisition risk: Part I.(RISK MANAGEMENT)
Fall 2006 PEO/SYSCOM Commanders' Conference: the will to change.(Conferences, Workshops & Symposia)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles