Subject: Revision to DoD Earned Value Management Policy.


THE UNDER SECRETARY OF DEFENSE

3010 DEFENSE PENTAGON

WASHINGTON, DC 20301-3010

MAR 7 2005

[ILLUSTRATION OMITTED]

MEMORANDUM FOR: SEE DISTRIBUTION

SUBJECT: Revision to DoD Earned Value Management Earned Value Management (commonly abbreviated and referred to just as EVM) is a project management technique that seeks to measure forward progress in an objective manner. EVM is touted as having a unique ability to combine measurements of technical performance (i.e.  Policy

Earned Value Management (EVM EVM Earned Value Management
EVM Evaluation Module
EVM Error Vector Magnitude
EVM Electronic Voting Machine
EVM Expert Group on Vitamins and Minerals
EVM Economic Value Management
EVM Extraneous Vegetable Matter
EVM Extra-Value Meal
EVM Electronic Voltmeter
) has been an effective management control tool in the Department for the past 37 years. In order to streamline, improve, and increase consistency in EVM implementation and application, I am revising the policy to include the following changes, effective immediately.

1. Cost or incentive contracts, subcontracts, intra-government work agreements, and other agreements valued at or greater than $20 million in then-year dollars shall implement the American National Standards (standard) American National Standard - (ANS) A common prefix for ANSI documents or standards, e.g.: "ANS Forth", or "American National Standard X3.215-1994".  Institute/Electronic Industries Alliance Standard 748, Earned Value Management Systems (ANSI/EIA-748). Cost or incentive contracts, subcontracts, and other agreements valued at or greater than $50 million in then-year dollars shall have an EVM system that has been formally validated and accepted by the cognizant contracting officer A US military officer or civilian employee who has a valid appointment as a contracting officer under the provisions of the Federal Acquisition Regulation. The individual has the authority to enter into and administer contracts and determinations as well as findings about such contracts. . I intend to review these dollar thresholds, and revise them if necessary, at least every five years.

2. A Contract Performance Report (CPR Cardiopulmonary Resuscitation (CPR) Definition

Cardiopulmonary resuscitation (CPR) is a procedure to support and maintain breathing and circulation for a person who has stopped breathing (respiratory arrest) and/or whose heart has stopped (cardiac
) (Data Item Description (DID) number DI-MGMT-81466) (previously called the Cost Performance Report) and an Integrated Master Schedule (IMS (1) See IP Multimedia Subsystem.

(2) (Information Management System) An early IBM hierarchical DBMS for IBM mainframes. IMS was widely implemented throughout the 1970s under MVS and continues to be used under z/OS.
) (DID number DI-MGMT-86150) shall be required whenever EVM (compliance with ANSI/EIA-748) is required, that is, for cost or incentive contracts, subcontracts, intra-government work agreements, and other agreements valued at or greater than $20 million in then-year dollars. However, CPR and IMS reporting for cost or incentive contracts, subcontracts, intra-government work agreements, and other agreements valued at less than $50 million in then-year dollars may be tailored (refer to the DoD Earned Value Management Implementation Guide (EVMIG EVMIG Earned Value Management Implementation Guide ) for guidance on tailoring reporting). A common work breakdown structure (project) Work Breakdown Structure - (WBS) A division of a project into tasks and subtasks. The tasks are numbered to indicate their relationship to each other. WBSs are indespensible for project planning, particularly when estimating time and resource requirements.  that follows the DoD Work Breakdown Structure Handbook (MIL-HDBK-881) shall be used for the CPR, IMS, and Contractor Cost Data Report (CCDR CCDR Comissão de Coordenação e Desenvolvimento Regional (Portugal)
CCDR Canada Communicable Disease Report (Relevé des maladies transmissibles au Canada)
CCDR Canadian Customer Debt Relief
CCDR Combatant Commander
). The Cost/Schedule Status Report (C/SSR C/SSR Cost/Schedule Status Report ) is rescinded effective immediately (except to the extent that it is required under current contracts) and shall not be used to satisfy the EVM reporting requirement on future contract awards.

3. Integrated Baseline Reviews (IBRs) shall be required whenever EVM (compliance with ANSI/EIA-748) is required, that is, for cost or incentive contracts, subcontracts, intra-government work agreements, and other agreements valued at or greater than $20 million in then-year dollars.

4. The responsibility and requirement for government surveillance of contracts remains unchanged and shall be based on the effectiveness of the contractor's implementation of internal management controls. Guidance on surveillance activity can be found in the DoD EVMIG.

5. EVM is discouraged on firm-fixed price, level of effort, and time and materials labor and materials (time and materials) n. what some builders or repair people contract to provide and be paid for, rather than a fixed price or a percentage of the costs.  efforts, including contracts, subcontracts, intra-government work agreements, and other agreements, regardless of dollar value. If knowledge by both parties requires access to cost/schedule data, the first action is to re-examine re·ex·am·ine also re-ex·am·ine  
tr.v. re·ex·am·ined, re·ex·am·in·ing, re·ex·am·ines
1. To examine again or anew; review.

2. Law To question (a witness) again after cross-examination.
 the contract type (e.g., fixed price incentive). However, in extraordinary cases where cost/schedule visibility is required and cannot be obtained using the Truth in Negotiations Act, the program manager shall obtain a waiver for individual contracts from the Milestone Decision Authority. In these cases the program manager will conduct a business case that includes rationale for why a cost or fixed price incentive contract was not an appropriate contracting vehicle.

6. The application of EVM on cost or incentive efforts, including contracts, subcontracts, intragovernment work agreements, and other agreements valued at less than $20 million is optional and is a risk-based decision that is at the discretion of the program manager. A cost-benefit analysis cost-benefit analysis

In governmental planning and budgeting, the attempt to measure the social benefits of a proposed project in monetary terms and compare them with its costs.
 shall be conducted before deciding to implement EVM in these situations. Considerations for determining the efficacy of applying EVM in these situations and guidance for tailoring reporting can be found in the DoD EVMIG.

These changes to EVM policy are not retroactive but shall be implemented on all applicable future contracts that are awarded based on solicitations or requests for proposal issued on or after 30 days from the date of this memorandum. These changes will be included in the next revision of the DoD 5000 series and other acquisition-related documents. While there is no prohibition on negotiating the revised policy into current contracts, the costs associated with changing the EVM requirements on existing contracts shall be borne by the government.

In support of the above policy changes, the Director, Acquisition Resources and Analysis, shall update all pertinent documents, to include DoD Instruction 5000.2, the Defense Acquisition Guidebook, and the CPR and IMS DIDs. The Director, Acquisition Resources and Analysis, shall work with the Director, Defense Procurement and Acquisition Policy, to update the Defense Federal Acquisition Regulation Supplement (DFARS DFARS Defense Federal Acquisition Regulation Supplement
DFARS DoD Federal Acquisition Regulation Supplement
) clauses. The Defense Contract Management Agency shall lead the efforts to update the DoD EVMIG. The Defense Acquisition University shall update its EVM curriculum.

Until the updated DFARS clauses are coordinated and approved, the existing clauses (252.234-7000 for solicitations and 252.234-7001 for contracts) shall be used. For contracts valued at or greater than $50 million, these clauses shall be applied directly. For contracts valued at or greater than $20 million but less than $50 million, the following paragraph shall be included in the statement of work: "In regard to DFARS 252.234-7000 and 252.234-7001, the contractor is required to have an Earned Value Management System that complies with ANSI/EIA-748; however, the government will not formally validate/accept the contractor's management system (no formal review)." While not required, if a risk-based decision is made to require EVM on cost or incentive contracts valued at less than $20 million, the above paragraph shall also be included in the statement of work.

While it is preferred that Project Management/Earned Value Management costs be charged direct to the contract, the contractor shall follow their accounting policies and procedures Policies and Procedures are a set of documents that describe an organization's policies for operation and the procedures necessary to fulfill the policies. They are often initiated because of some external requirement, such as environmental compliance or other governmental .

Questions regarding the revised EVM policy should be directed to Ms. Debbie Tomsic (deborah/tomsic@osd.mil) or Mr. Larry Axtell (larry.axtell@osd.mil) at (703) 695-0707.

Editor's note Editor's Note (foaled in 1993 in Kentucky) is an American thoroughbred Stallion racehorse. He was sired by 1992 U.S. Champion 2 YO Colt Forty Niner, who in turn was a son of Champion sire Mr. Prospector and out of the mare, Beware Of The Cat.

Trained by D.
: View the distribution to this memorandum at <http://akss.dau.mil/docs>.

Michael W. Wynne
COPYRIGHT 2005 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:Department of Defense
Author:Wynne, Michael W.
Publication:Defense AT & L
Geographic Code:1USA
Date:Jul 1, 2005
Words:987
Previous Article:Subject: Implementation Guidance on the Realignment of the Department of Defense (DoD) Business Transformation Program Management Office.(Department...
Next Article:Department of Defense news release (March 18, 2005): DoD implements Earned Value Management policy improvements.
Topics:



Related Articles
Major revision to AR 70-1, Army Acquisition Policy (Jan. 30, 2004).(Policy & Legislation)(Army Regulation)(Brief Article)
Subject: Policy for Systems Engineering in DoD.(Policy & Legislation)(Department of Defense)
Subject: Radio Frequency Identification (RFID) Policy.(POLICY & LEGISLATION)
Department of Defense news release (March 18, 2005): DoD implements Earned Value Management policy improvements.
Department of Defense press release (June 1, 2005): inspector general accountability report completed.(Brief Article)
Subject: Proper Use of Non-DoD Contracts.(Policy & Legislation)
Pentagon revises program performance regulations.(GOVERNMENT POLICY NOTES)
Subject: Proper Use of Non-DoD Contracts.(Policy & Legislation)
Subject: Terms of Reference--Defense Science Board Task Force on Defense Industrial Structure for Transformation.(Policy & Legislation)
Subject: Designation of Mr. Frank J. Anderson, Jr., as OUSD(AT & L) Director, Human Capital Initiatives.(Brief article)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles