STANDARD Missile value engineering (VE) program: a best practices role model.


In mid 2002, the Office of Naval Research's Best Manufacturing Practices Center of Excellence (BMPCOE BMPCOE Best Manufacturing Practices Center of Excellence ) reported a survey of best practices being used in the Navy's STANDARD Missile The Standard Missile is a type of surface-to-air missile (SAM) originally developed for the United States Navy (USN). The SM-1 was developed as a replacement for the RIM-2 Terrier and RIM-24 Tartar systems deployed in the 1950s on a variety of USN ships.  Program Office, currently a part of the Surface Weapons Systems/Launchers division of the Program Executive Office for Integrated Warfare The conduct of military operations in any combat environment wherein opposing forces employ non-conventional weapons in combination with conventional weapons.  Systems (PEO IWS PEO IWS Program Executive Office Integrated Warfare Systems  3A).

One of the areas highlighted in the STANDARD Missile Program Office survey was its use of a Value Engineering (VE) program that implements a highly successful VE change process with its STANDARD Missile production lines. The nominal return-on-investment (ROI (Return On Investment) The monetary benefits derived from having spent money on developing or revising a system. In the IT world, there are more ways to compute ROI than Carter has liver pills (and for those of you who never heard of that expression, it means a lot). ) from the VE program was substantial when compared to others in the federal government.

This article recounts how the VE program arose, was nurtured in a team environment, and was implemented. It points to a number of lessons learned that have earned this program the label of "best practice" and illustrates why the Navy's STANDARD Missile Program Office has become a role model for similar VE programs in industry and government.

Tough Defense Budget Years Pose Missile Affordability Problems

By the mid 1990s, defense budget cutbacks--as much as 40 percent--were beginning to have a major impact on many government weapon procurement efforts. At the same time, mandated acquisition reform changes were beginning to be implemented within the Department of Defense (DoD). These reforms were intended to transform DoD into a more responsive and efficient buyer of best-value goods and services In economics, economic output is divided into physical goods and intangible services. Consumption of goods and services is assumed to produce utility (unless the "good" is a "bad"). It is often used when referring to a Goods and Services Tax.  by focusing on a number of critical issues that included establishing total ownership cost reduction discipline and bringing cost engineering tools into play.

At the grass roots grass roots
pl.n. (used with a sing. or pl. verb)
1. People or society at a local level rather than at the center of major political activity. Often used with the.

2. The groundwork or source of something.
 level, officials in the Navy's STANDARD Missile Program Office were beginning to see the unit price of missiles increase as the defense budgets decreased, yet they saw little change in the requirement for providing air defense missiles to the U.S. Navy Fleet.

Program Office Initiative Gets The VE Change Proposal (VECP VECP Value Engineering Change Proposal
VECP Vertical Eye Closure Penalty (Agilent)
VECP Visually Evoked Cortical Potential
) Process Rolling

By addressing missile unit cost reduction as a total ownership cost goal, the program office began designating cost as part of their engineering discipline. Program office leaders empowered an integrated product team (IPT IPT - IP Telephony ) to work on three areas where they thought missile cost could be controlled: production, development, and logistics support. Of these three areas, production buys seemed to be the major cost driver. The team also concentrated on having the capability to trade performance for cost, as well as considering cost as a goal in evaluating new technology for the missile program. Realizing that engineering change was an integral and normative part of the acquisition process, the program office considered a strategy for using engineering changes as a cost reduction tool in missile production lines. The leaders reasoned that by establishing incentive in this process, both the government and its industry partners would benefit. They also reasoned that incremental Additional or increased growth, bulk, quantity, number, or value; enlarged.

Incremental cost is additional or increased cost of an item or service apart from its actual cost.
 performance improvements in block upgrades would reduce program risks, testing costs, and qualification requirements. At the same time, streamlining the process by relaxing detailed design control with the prime contractor would simplify the change process and help accomplish acquisition reform goals. The results of these strategy considerations became a highly successful VE change proposal (VECP) process--so successful, in fact, that the program office was able to save over $85 million through FY03, establishing the STANDARD Missile Program as a leader in federal VE efforts.

Flushing Out Successful Strategies for VECPs

The program office was faced with how to structure successful VECP strategies that were realistic and achievable from both a technical and a contracting process perspective. The program office determined that the most important strategies were to make optimum use of personnel resources, to streamline the procurement process, and to ensure well-designed technical improvements.

To optimize personnel resources, the program office focused on the important benefits that could be derived from a good government/industry partnering. This involved not only getting the program office and field activities to work together, but also integrating the contractor, Raytheon, into the team as a full partner. To streamline procurement, the program office ensured that the VECP process/approval cycle was well defined and understood at the start. In the technical arena, the program office had to consider a number of development/production impacts resulting from the potential VECPs.

Optimizing Development and Production Capabilities

VECPs are engineering changes to an existing design. The value part of the engineering change is any technical, material, or support change that has been proposed to the design to obtain its cost and performance value. The technical changes that the STANDARD Missile Program Office considered for missiles in production included replacing obsolete parts, designing changes for both new and back-fitted missiles, and missile performance enhancements. Technical considerations also had to be made for ensuring the continued use of manufacturing sources, testability, incorporation of new technology enhancements, improved reliability, and commonality com·mon·al·i·ty  
n. pl. com·mon·al·i·ties
1.
a. The possession, along with another or others, of a certain attribute or set of attributes: a political movement's commonality of purpose.
 with other missile variants in production. These technical considerations were aided by design strategies that included not only product architectures across the STANDARD Missile family, re-use of proven designs, and controlled parts selections, but also considerations for use and mission applications by 13 foreign military sales That portion of United States security assistance authorized by the Foreign Assistance Act of 1961, as amended, and the Arms Export Control Act of 1976, as amended. This assistance differs from the Military Assistance Program and the International Military Education and Training Program  (FMS FMS - Flexible Manufacturing System (factory automation). ) countries.

Government and Industry Partnering: A Win/Win Deal

According to according to
prep.
1. As stated or indicated by; on the authority of: according to historians.

2. In keeping with: according to instructions.

3.
 Scott Reiter, then production manager for the STANDARD Missile Program Office, the key to achieving cost reductions using the VECP process was the concept of close government/industry partnering. Reiter emphasizes that the government must have a strong willingness to invest in long-term relationships with industry partners, working issues together and building trust. He cautions, however, that doing this doesn't mean giving away the store. Once the process was initiated, ideas for VECPs began to generate excitement as the process matured and showed return on investment. Reiter states that the government just couldn't have afforded the burden of going down this path by itself. Rich Leonard, the Raytheon business manager for STANDARD Missile Programs, agrees completely, saying that "the success of the VECP program has in large part been due to the close partnership Raytheon has had with NAVSEA NAVSEA Naval Sea Systems Command
NAVSEA Naval Avionics Support Equipment Appraisal
 [Naval Sea Systems Command The Naval Sea Systems Command (NAVSEA) is the largest of the U.S. Navy's five "systems commands," or materiel organizations. NAVSEA consists of four shipyards, eight "warfare centers" (two undersea and six surface), four major shipbuilding locations and the NAVSEA headquarters, ] during the program."

A Streamlined VECP Process

Structuring and controlling the VECP process was one of the keys to success. Written ground rules and streamlining the approval chain and contracting process were extremely important. Nailing down share lines and agreeing with the prime contractor on contractual details were critical. Cost goals included splitting the share line 50/50 for a specified number of years, then structuring incentives for cost savings. The government didn't want to get into a share line negotiation cycle. Both the government and the contractor had a win/win situation.

Raytheon agrees that maintaining a formal process was key to the success of the partnership. Leonard comments that the communication of project process and expectations in the early stages of the VECP process was critical.

Program office relationships with the contracting officer A US military officer or civilian employee who has a valid appointment as a contracting officer under the provisions of the Federal Acquisition Regulation. The individual has the authority to enter into and administer contracts and determinations as well as findings about such contracts.  were also a necessary part of the VECP process, according to Reiter. The contracting officer had to be on board with the details and not be a stumbling block stum·bling block
n.
An obstacle or impediment.


stumbling block
Noun

any obstacle that prevents something from taking place or progressing

Noun 1.
 to the process implementation, yet ensure that all the i's were dotted and t's crossed from a regulatory standpoint. The approval process needed to be streamlined but auditable. The timeline activities in the VECP process (proposal development, selection board cycle, contracting procedures, for example) had to be well known to all players. Cost proposals needed to be clear and able to be put under contract quickly .

Elements in the Structure of a Good VECP

A long, mature production line had already been established and was operating for the STANDARD Missile. When VE incentives were announced, it was not difficult for contractor personnel to produce viable VECP candidates. Ideas for VECPs were abundant. However, to be a good VECP candidate and a benefit to the Navy, the terms of cost savings and performance enhancement had to be well articulated, the engineering impacts had to be known at the beginning, and production schedules had to be well-managed to minimize overall cost impacts in the budgeting and contracting processes. Each of these elements required considerable organization as well as the formulation of metrics by which to evaluate the effort's success.

Referring to the importance of handling personnel resources in a successful VECP process, Leonard says, "We have been able to retain some of the most respected engineers within our division on STANDARD." He further notes that when mature programs don't offer such challenges as the successful STANDARD Missile VECP program, the project tends to lose critical engineering and operations personnel to new and more exciting programs.

The Metrics Tell the Story

Over the course of several years, the Years, The

the seven decades of Eleanor Pargiter’s life. [Br. Lit.: Benét, 1109]

See : Time
 STANDARD Missile Program Office VE IPT evaluated many ideas for all the major subsystems of the STANDARD Missile. They ranged in scope from component/unit redesign and modified production processes to commercial off-the-shelf Commercial off-the-shelf (COTS) is a term for software or hardware, generally technology or computer products, that are ready-made and available for sale, lease, or license to the general public.  (COTS) implementation and new vendor selection to address parts obsolescence ob·so·les·cent  
adj.
1. Being in the process of passing out of use or usefulness; becoming obsolete.

2. Biology Gradually disappearing; imperfectly or only slightly developed.
 issues. The cost reduction in individual VECPs ranged from $ 0.5 million to over $56 million. The chart on page 42 shows the VECP portfolio through FY03 illustrating the net reduction for the STANDARD Missile Program acquisitions.

Examples of Successful VECP Implementation

Three examples of successful STANDARD Missile VECPs tell the story: the Plate 3A AEGIS Transceiver Producibility VECP; the Warhead Compatible Telemeter tel·e·me·ter  
n.
A measuring, transmitting, and receiving device used in telemetry.

tr.v. tel·e·me·tered, tel·e·me·ter·ing, tel·e·me·ters
 (WCT WCT World Championship Tour (surfing competition)
WCT WIPO Copyright Treaty
WCT Wind Chill Temperature
WCT Wide Complex Tachycardia
WCT Wavefront Conduction Time
WCT Wright's Computer Technology (England) 
) Transmitter (AN/DKT-71A); and the Autopilot Battery Section Inertial Instrument Unit and Electronics Assemblies (APBS APBS Automated PEMA Budget System
APBS Automated Property Book System
 IIU IIU International Islamic University (Terengganu, Malaysia)
IIU Inertial Instrument Unit (US Navy)
IIU Imagery Interpretation Unit (USMC) 
 and APBS EA). But first, a few words are needed to understand these changes in terms of the weapon in which they were implemented. The STANDARD Missile, the Navy's premier surface-to-air, ship-based weapon, is a highly complex system composed of multiple modules, some of which control evolutions such as guidance and navigation, propulsion, staging, steering control, and warhead control. Module interfaces are highly defined, and module/component design is tightly controlled to produce this extremely compact and complex weapon. In addition, members of the STANDARD Missile family are usually variants of a well-honed design process that is upgraded in blocks and increments to add new performance capabilities or missile functionality. These features mean that any change to a missile variant can ripple through the production lines to other variants.

VECP Example #1: Plate 3A AEGIS Transceiver Assembly

The design link allowing communication from the missile to the AEGIS weapons system, implemented in the Navy's CG-47 Ticonderoga and DDG-51 Arleigh Burke Arleigh Albert Burke (October 19, 1901–January 1, 1996) was an admiral of the United States Navy who distinguished himself during World War II and the Korean War, and who served as Chief of Naval Operations during the Eisenhower administration.  cruiser cruiser, large, fast, moderately armed warship, intermediate in type between the aircraft carrier and the destroyer. During World War II, battle cruisers operated as small battleships, combining in one vessel maximum qualities of gun caliber, armor protection, and  and destroyer destroyer, class of warship very fast relative to its length, generally equipped with torpedos, antisubmarine equipment, and medium-caliber and antiaircraft guns. The newest destroyers are equipped with guided missiles as their chief offensive weapon.  ship classes, was modified to include a higher component level of integration. The results of the modifications added new functionality, link sensitivity, improved reliability, nuclear hardening hardening, in metallurgy, treatment of metals to increase their resistance to penetration. A metal is harder when it has small grains, which result when the metal is cooled rapidly. , and other performance enhancements. The higher scale integration implementation directly reduced the number of testable assembly test levels from 11 to seven. The overall contract saved the government $34 million in immediate and projected procurement costs.

VECP Example #2: Warhead Compatible Telemeter (WCT) Transmitter (AN/DKT-71A)

The AN/DKT-71A Warhead Compatible Telemeter Transmitter that controls telemetry telemetry

Highly automated communications process by which data are collected from instruments located at remote or inaccessible points and transmitted to receiving equipment for measurement, monitoring, display, and recording.
 signals to the warhead was a unique military design. The VECP for this assembly was replaced by a COTS transmitter that met or exceeded the performance capabilities required. The VECP eliminated hybrid designs and obsolete parts to improve performance. Implementing this type of change illustrates to the contractor the value of stipulating performance goals and not design. The VECP has saved over $3.6 million.

VCEP VCEP Vanguard Charitable Endowment Program
VCEP Video Compression/Expansion Processor
 Example #3: Autopilot Battery Section Inertial Instrument Unit (APBS IIU) and Electronics Assemblies (EAs)

This VECP leveraged two APBS IIU efforts to save costs and time. The VECP facilitated an upgrade to the IIU in conjunction with funding from a Navy manufacturing technology program demonstration on the APBS electronics assembly (APBS EA). The higher level of electronics integration implemented on the EA allowed a redesign of the inertial instrument unit improving overall missile reliability and commonality over the missile product line. The resulting savings from the government/Raytheon shared investments were about $50 million.

Lessons Learned from the VECP Process

The major lessons learned from the VECP work accomplished by the daring and innovative personnel of the Navy's STANDARD Missile organization and its prime missile contractor, Raytheon, are recognized as examples of acquisition best practices. Their implementation presents the program office's success as a best practices role model. The lessons are not rocket science rocket science
n.
1. Rocketry.

2. Informal An endeavor requiring great intelligence or technical ability.
, nor are they difficult to implement. They are merely wise implementation of time-tested and logical steps and processes that management can take to ensure that innovative and resourceful re·source·ful  
adj.
Able to act effectively or imaginatively, especially in difficult situations.



re·sourceful·ly adv.
 people deliver high-quality products to the military user on time and within budget. These lessons also reflect the implementation of the principles embodied in total ownership cost and good risk management techniques.

Government/Industry Partnering Fosters a Win/Win Situation

The successful VECP work carried out by the STANDARD Missile Program Office and Raytheon was a direct result of conscious decisions to build a government/industry partnering relationship. Both partners were willing to trust each other, to jointly invest their resources, and to commit to a long-term relationship whose keystone key·stone  
n.
1. Architecture The central wedge-shaped stone of an arch that locks its parts together. Also called headstone.

2. The central supporting element of a whole.
 was the ability to jointly solve problems. The Navy's STANDARD Missile Program Office and Raytheon were, and continue to be, able to achieve this partnership.

Incentives are Good for Performance

A contract forms a basis for expectations and compensation. As dictated by the Federal Acquisition Regulation (FAR), contracts between the government and industry that exceed $100,000 must contain VE clauses for possible use when the contract is executed. However, if the government does not play a major role in motivating the contractor, the VE clause provisions may never be exercised. The government must take the initiative. Once implemented, the incentives attract the best performance from the personnel.

Write Down the Ground Rules

If the VECP process is to work smoothly, ground rules must be written early. Written expectations help the parties focus on how share lines will be structured, what investments are required by each party, how cost proposals are to be written and evaluated, how the approval process will proceed, and other key expectations and procedures. The Navy recognized at the beginning that they did not want to play games with share line negotiations and that good work warranted reward. The latter was well-recognized by the contractor as a good thing, and the result became a win/win situation. Knowing how to structure an effective proposal and having the process streamlined helps to get the program on the road.

Change is Continuous: Be Flexible

Even though long-term relationships exist, people, organizations, and processes change. The best practices business models developed for VECPs must be flexible enough to address these inevitable changes. Key to success are flexibility, innovative thinking, and good problem-solving skills by all parties on the team. Sometimes efforts just don't succeed, and return on investment is sometimes hard to predict. In all these efforts Scott Reiter cautions, "Stay away from the blame game."

A Role Model for Others

Through its highly successful and innovative Value Engineering Program, the STANDARD Missile Program Office has implemented the spirit and letter of Public Law 104-106 in "improving performance, reliability, quality, safety, and life cycle costs" and has distinguished itself as a role model and best practices leader in the federal government.

STANDARD Missile

The STANDARD Missile is among the most reliable and effective weapon systems in the Department of the Navy's tactical inventory. It offers primary air defense support for the AEGIS Ticonderoga-class cruisers, the Arleigh Burke-class destroyers, and the navies of allied countries throughout the world. The evolving STANDARD Missile family provides a robust anti-air warfare capability--a defense against high altitude Conventionally, an altitude above 10,000 meters (33,000 feet). See also altitude. , long-range, high crossing, and maneuvering threats. The STANDARD Missile Program Office (IWS See iPlanet Web Server.  3A) is responsible for the cradle-to-grave management of the STANDARD Missile. IWS 3A oversees all variants of the program, inclusive of inclusive of
prep.
Taking into consideration or account; including.
 concept formulation, design, development, integration, acquisition, test and evaluation, fleet introduction, modernization modernization

Transformation of a society from a rural and agrarian condition to a secular, urban, and industrial one. It is closely linked with industrialization. As societies modernize, the individual becomes increasingly important, gradually replacing the family,
, and life-cycle maintenance. Photograph courtesy of BMPCOE

Editor's note Editor's Note (foaled in 1993 in Kentucky) is an American thoroughbred Stallion racehorse. He was sired by 1992 U.S. Champion 2 YO Colt Forty Niner, who in turn was a son of Champion sire Mr. Prospector and out of the mare, Beware Of The Cat.

Trained by D.
: The author welcomes questions and comments. Contact him at roland@bmpcoe.org.

Blocksom is a retired Navy commander and currently a technical risk manager with WILLCOR, Inc., supporting the Navy's Best Manufacturing Practices Center of Excellence (BMPCOE).
COPYRIGHT 2004 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2004, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:BEST PRACTICES
Author:Blocksom, Roland
Publication:Defense AT & L
Geographic Code:1USA
Date:Sep 1, 2004
Words:2643
Previous Article:Heroes II: attack of the process clones.(PROFESSIONAL GROWTH)
Next Article:The art of the article: how to write words and influence people.(PROFESSIONAL DEVELOPMENT)
Topics:



Related Articles
Value analysis/engineering cuts costs by weighing alternatives.
The journey to strengthen our profession.(Best Practices)
The directorate of Defense Systems: expanded mission and focus.(Organization)
Four new continuous learning modules added to DAU Web site.(Career Development)(Defense Acquisition University)
Software architecture for a Virtual Environment for Nano Scale Assembly (VENSA).
Unisys to support software factories with 3D visible enterprise blueprints.
A new systems engineering model and an old, familiar friend.(SYSTEMS ENGINEERING)
Electric press for LSR.(Injection Molding)