Recommendations on coaching strategies for implementing lean.


The U.S. defense industry has more than a decade of experience implementing Lean process improvement methodologies to create value and eliminate waste in manufacturing and operations. While Lean implementation approaches differ, commercial companies and military commands consistently use highly skilled sensei sen·sei  
n. pl. sen·seis
1. A judo or karate teacher.

2. A teacher or mentor.

3. Used as a form of address for such a person.
, or coaches to help provide the discipline and structure needed to implement rapid and continuous change. This report documents key elements of coaching strategies from Lean implementations at 13 U.S. defense companies and military commands. The research indicates that differences in coaching strategies impact whether an organization will succeed in implementing Lean.

**********

The U.S. defense industry has more than a decade of experience implementing Lean process improvement methodologies to create value and eliminate waste. Since the late 1990s, over a dozen Department of Defense (DoD) organizations have introduced Lean to systematically streamline operations and reduce costs. While Lean implementation approaches differ, private companies and military commands consistently use highly skilled sensei, or coaches to help provide the discipline and structure needed to implement rapid and continuous process improvement. Ten specific recommendations concerning coaching strategies to effectively implement Lean in defense organizations are included here.

The five fundamental principles of Lean listed below are described in the book titled Lean Thinking, by James Womack and Daniel Jones Noun 1. Daniel Jones - English phonetician (1881-1967)
Jones
 (Womack & Jones, 1996).

1. Specify Value in the Terms of the Customer.

2. Identify the Value Stream.

3. Make the Process Flow.

4. Pull Value from the Customer.

5. Pursue Perfection.

These Lean principles originated in Japan with automobile production practices developed at Toyota in the 1950s. Decades later commercial manufacturing companies around the world began adopting these five principles. More recently, U.S. defense industry began introducing Lean in their production and maintenance facilities. While shop floor operations continue to be the initial focus of commercial Lean implementations, some companies have extended the application of these Lean principles to additional processes. The U.S. defense aerospace industry has numerous examples of applying Lean structured improvement methodology to system life-cycle processes including design, material management, repair, and overhaul.

While DoD primarily relies on contractors to design and produce defense systems, many DoD organizations are responsible for system life-cycle processes such as material management, repair, and overhaul. Management of defense system acquisition and sustainment processes is a core competency A core competency is something that a firm can do well and that meets the following three conditions specified by Hamel and Prahalad (1990):
  1. It provides customer benefits
  2. It is hard for competitors to imitate
  3. It can be leveraged widely to many products and markets.
 of the material commands within each of the military services and several defense agencies. Figure 1 highlights how Lean principles have migrated from Japanese automobile manufacturing to defense system life-cycle processes to integrated defense system management.

[FIGURE 1 OMITTED]

Among the first DoD aerospace system management organizations to experiment with implementing Lean on a large scale was Warner Robins Warner Robins, city (1990 pop. 43,726), Houston co., central Ga., in an agricultural region; inc. 1943. The surrounding area yields peanuts, grain, fruit, and livestock.  Air Logistics Center (WR-ALC WR-ALC Warner-Robins Air Logistics Center ). Air Force Major General Haines, then Commander of WR-ALC, highlighted that the center saved millions of dollars on labor, material, and tools by applying Lean to depot-level repair of aircraft components. His successor, Major General Wetekam, expanded the centers Lean implementation to other weapon system sustainment processes. WR-ALC has significantly reduced the time to overhaul fighter and cargo aircraft A cargo aircraft is an airplane designed and used for the carriage of goods, rather than passengers. This role demands a number of features that makes a cargo aircraft instantly identifiable; a "fat" looking fuselage, a high-wing to allow the cargo area to sit near the ground, a . The other logistics centers within Air Force Materiel Command Air Force Materiel Command (AFMC) is a major command of the United States Air Force.  have also enhanced organizational performance Organizational performance comprises the actual output or results of an organization as measured against its intended outputs (or goals and objectives).

Specialists in many fields are concerned with organizational performance including strategic planners, operations,
 by introducing Lean structured process improvement methodology (McCormack, 2002a).

Army Material Command (AMC (Advanced Mezzanine Card) See AdvancedTCA. ) has also demonstrated improvements by introducing Lean to sustainment processes including maintenance and supply. In 2002, General Kern Kern, river, 155 mi (249 km) long, rising in the S Sierra Nevada Mts., E Calif., and flowing south, then southwest to a reservoir in the extreme southern part of the San Joaquin valley. The river has Isabella Dam as its chief facility. , Commander of AMC, expanded upon the Lean implementation at Red River Army Depot (RRAD RRAD Red River Army Depot (Texarkana, TX)
RRAD Reusable and Rapid Application Development
). He launched a campaign to educate and train the AMC workforce about Lean principles and practices and provided funding for coaches at Army depots throughout the country (Hermes, 2002; McCormack, 2002a).

The U.S. Navy has applied Lean to the Intermediate Aircraft Maintenance Division at Naval Air Station Lemoore Naval Air Station Lemoore or NAS Lemoore (IATA: NLC, ICAO: KNLC, FAA LID: NLC) is a United States Navy base, located in Kings County, California. Lemoore Station, California, a census-designated place, is located inside the base's borders. . The organization reduced the number of F-18 aircraft without engines from 26-28 per month to zero, and now a balance of engines is on hand to support the fleet (Jaynes, 2002).

In 2003, Air Force Materiel Command (AFMC AFMC Air Force Materiel Command
AFMC Arkansas Foundation for Medical Care
AFMC Armed Forces Medical College (Pune, India)
AFMC Armed Forces of America Motorcycle Club
AFMC Auxiliary Fuel Management Computer
) piloted the application of the Lean principles to joint DoD and defense processes. Three AFMC program offices within the Aeronautical aer·o·nau·tic   also aer·o·nau·ti·cal
adj.
Of or relating to aeronautics.



aero·nau
 Systems Center collaborated with their prime contractors to use Lean tools and practices to reduce time to accomplish flight-testing, contract modifications, and contract closeout closeout, closure

the finalization of a feeding program in a feedlot. The cattle are sold and a balance sheet is struck which includes the costs of feeding and housing or confining them.
. Defense systems management organizations are applying Lean structured, disciplined methodology for team-based process improvement to significantly boost performance.

Each of these early Lean implementations by military commands share common traits and continue to expand. All DoD organizations employed external coaches to help introduce Lean principles and practices. During the same period, other organizations, including a military command, have attempted to implement Lean using only internal coaches and failed. This poses a key question concerning coaches. Richard McCormack asked military leaders involved with implementing Lean the question, "Can an organization like yours initiate a Lean implementation on its own or do you need help doing it?" Their answers are published in his book titled Lean Machines: Learning From the Leaders of The Next Industrial Revolution (Hermes, 2002; McCormack, 2002a).
    Major General Haines, Commander, WR-ALC: "You need help doing
    it and we have one of the best, we're using ... Consultants.
    This was one of our learning experiences.... Our objective is
    to let them teach us for a year or so and by then we should
    have our own people who are ready to start running with it
    internally."

    Lieutenant Colonel Frank Hart, Commander RRAD: "You need to read
    "Lean Thinking", then find yourself a firm like ... that is on site
    on the ground and part of your team. If you think you can read the
    book and attend the seminar and do it yourself, you won't achieve
    it. You have to hire experienced mentors who have truly walked the
    walk--been in an organization that has implemented it."


During 2003, the Defense Acquisition University (DAU DAU - /dow/ [German Fidonet] D"ummster Anzunehmender User. A German acronym for stupidest imaginable user. From the engineering-slang GAU for Gr"osster Anzunehmender Unfall (worst foreseeable accident), especially of a LNG tank farm plant or something with similarly disastrous ) Research Fellows investigated key elements of coaching strategy needed to successfully implement Lean in defense systems management organizations. While Lean principles and tools are fairly consistently defined, we found that coaching strategies for implementing Lean varied, and were not as well documented. Our study compared coaching strategies by organization size, mission, domain, and implementation phase. Through our research, we distilled that defense system management organizations should address the following six questions when building a coaching strategy for implementing Lean.

1. What is the scope of responsibilities for coaching staff to implement Lean?

2. What are the credentials needed to select coaches to implement Lean?

3. What is the mix of external and internal coaches needed to implement Lean?

4. What tools do coaches need to have knowledge/experience of to implement Lean?

5. What performance measures are needed to manage coaches implementing Lean?

6. What are the incentives coaches need to implement Lean?

Our research indicates that Lean--a structured, disciplined methodology for process improvement--can be applied to defense life-cycle system management activities. Although the Lean principles and tools are fairly formalized for·mal·ize  
tr.v. for·mal·ized, for·mal·iz·ing, for·mal·iz·es
1. To give a definite form or shape to.

2.
a. To make formal.

b.
 and straight forward, the strategies for implementing Lean vary. We analyzed and compared coaching strategies that companies and military services have employed to implement Lean in their organizations. The focus of the research was primarily on U.S. defense aerospace organizations. We found that different coaching strategies are needed during Introduction, Growth, and Sustainment phases of a Lean implementation.

DEFINITIONS AND SCOPE OF STUDY

Defense system management organizations were categorized cat·e·go·rize  
tr.v. cat·e·go·rized, cat·e·go·riz·ing, cat·e·go·riz·es
To put into a category or categories; classify.



cat
 by three dimensions: size, domain, and mission, which are independent variables in this study. The specific measures used to determine these domains are described below.

Size: The number of people in an organization implementing Lean. For the purpose of this research, a Small organization has less than 1,000 employees, Medium has between 1,000 and 5,000 employees, and Large has over 5,000 employees.

Domain: The organization's primary business (DoD, Defense, or Other).

Mission: The primary emphasis of the organization with regard to the spectrum of defense system management activities. For this research, the term acquisition refers to system development and demonstration work efforts plus production & deployment work efforts. Figure 2 depicts the life-cycle of systems management activities, as defined in DoD Instruction 5000.2, "Operation of the Defense Acquisition System."

[FIGURE 2 OMITTED]

People Interviewed: We interviewed over 50 people in organizations who were implementing or who had implemented Lean in organizations. Table 1 summarizes the organizations interviewed and their characteristics in terms of size, domain, and mission.

In addition to these formal interviews, we interviewed and observed other Lean practitioners form the following organizations or at the listed events.

* Lean Aerospace Initiative (LAI LAI Leaf Area Index
LAI Lean Advancement Initiative (MIT)
LAI Lean Aerospace Initiative
LAI Long-Acting Injection
LAI Lambda Alpha International (honorary land economics society) 
) is a non-profit consortium that provided coaches for introduction of Lean in three Aeronautical System Center (ASC ASC Ambulatory surgery center, see there ) program offices. The LAI coaches were observed during program training of the Global Hawk program members in Rancho ran·cho  
n. pl. ran·chos Southwestern U.S.
1. A hut or group of huts for housing ranch workers.

2. A ranch.
 Bernardo, California in January 2003, and Value-Stream Mapping of the Global Hawk and F-22 aircraft programs in Dayton, Ohio Dayton is a city in southwestern Ohio, United States. It is the county seat and largest city of Montgomery County. As of the 2005 census estimate, the population of Dayton was 158,873.  in February 2003.

* Simpler Consulting Inc. is a private company that currently provides coaches to numerous DoD organizations including the Army, Navy, Air Force, and DoD headquarters staff. Simpler coaches were directly observed at Warner Robins Air Logistics Center and Corpus Christi Corpus Christi, in Christianity
Corpus Christi [Lat.,=body of Christ], feast of the Western Church, observed on the Thursday after Trinity Sunday (or on the following Sunday).
 Army Depot.

* Lockheed Martin For the former company, see .

Lockheed Martin (NYSE: LMT) is a leading multinational aerospace manufacturer and advanced technology company formed in 1995 by the merger of Lockheed Corporation with Martin Marietta.
 Commercial Systems Engineering is a private company that provides coaches and training for Lockheed Martin companies located in the eastern United States United States, officially United States of America, republic (2005 est. pop. 295,734,000), 3,539,227 sq mi (9,166,598 sq km), North America. The United States is the world's third largest country in population and the fourth largest country in area.  plus other American industries American Industries is a large real estate development company based in Chihuahua, Mexico. They also have offices in Monterrey, Cd. Juarez, and El Paso.

It provides various industrial real estate services, including built-to-suit, sale-lease-back, shared leases programs, and
 and government agencies. Lockheed Martin coaches were directly observed during training conducted at the companies training facility in Mount Laurel, New Jersey in June 2003.

* Raytheon Learning Institute is a training organization within Raytheon Corporation that provides Six Sigma Not to be confused with Sigma 6.
Six Sigma is a set of practices originally developed by Motorola to systematically improve processes by eliminating defects.[1] A defect is defined as nonconformity of a product or service to its specifications.
 Expert training within the organization. Raytheon coaches were directly observed during training conducted at Babson College Babson College, located in Wellesley, Massachusetts (zoned as "Babson Park," ZIP code 02457),[1] is a private business school that grants all undergraduates a Bachelor of Science in Business Administration. The F. W. , Massachusetts from July through September 2003.

* MainStream Management LLC (Logical Link Control) See "LANs" under data link protocol.

LLC - Logical Link Control
, is a private company that provides coaches to guide Lean culture change activities currently supporting depot activities at Hill Air Force Base, Utah. MainStream coaches were interviewed in June 2003 and directly observed at Hill Air Force Base in October 2003.

* Lean Shipbuilding and Repair Forum 2, Seattle, Washington This page is protected from moves until disputes have been resolved on the .
The reason for its protection is listed on the protection policy page.
, April 2003.

* LAI Annual Plenary plenary adj. full, complete, covering all matters, usually referring to an order, hearing or trial.


PLENARY. Full, complete.
     2.
 Conference, Dayton, Ohio, March 2003.

* International Lean Manufacturing Lean manufacturing is the production of goods using less of everything compared to mass production: less human effort, less manufacturing space, less investment in tools, and less engineering time to develop a new product.  Conference, Lexington, Kentucky Lexington, Kentucky, United States, known as the "Horse Capital of the World," is located in the heart of the Bluegrass region. It is the second-largest city in Kentucky, after Louisville, Kentucky,[1] and the 68th largest in the United States. , May 2003.

* Lean Enterprise Institute (LEI) Value Stream Mapping Value Stream Mapping is a Lean technique used to analyse the flow of materials and information currently required to bring a product or service to a consumer. At Toyota, where the technique originated, it is known as "Material and Information Flow Mapping" [1].  training, Philadelphia, Pennsylvania, May 2003.

* Georgia International Lean Symposium, Warner Robins, Georgia Warner Robins is the 9th largest city in Georgia, located in Houston County, Georgia and Peach County. The city is in the Macon metropolitan area. As of the 2000 census, the city had a total population of 48,804. , June 2003.

Lean Implementation Phase: Just as the defense system management spectrum is divided in to several phases, Lean implementation can be divided into different phases based on workforce participation in Lean Events. While many leadership activities (like building and maintaining employee interest) are vital throughout an implementation, others require special attention during a specific phase. We used a 3-phase framework for implementing Lean to describe the application of the six coaching strategy elements. Figure 3 depicts these Lean Implementation Phases based on workforce participation in Lean events as we describe them in our research.

[FIGURE 3 OMITTED]

Research Hypothesis: If implementation of Lean is to be successfully introduced, grown, and sustained in defense system management organizations, then a robust coaching strategy is required.

Recommendations: The following are our top ten recommendations concerning coaching strategies to effectively implement Lean in defense organizations. These recommendations are based upon over 50 interviews with U.S. defense industry and DoD organizations that are implementing Lean. Findings are included from direct observation of 13 companies and military commands that are introducing, growing, or sustaining Lean. We believe these distilled experiences can help increase the probability that defense organizations can successfully implement Lean in system acquisition and sustainment processes.

COACH RESPONSIBILITIES

Establish several levels of coaches with different degrees of responsibilities. Organizations should also define the responsibilities and time commitment expected for both internal and external coaches to support Lean Implementations. The following three levels of coach responsibilities were used by several defense contractors Noun 1. defense contractor - a contractor concerned with the development and manufacture of systems of defense
armed forces, armed services, military, military machine, war machine - the military forces of a nation; "their military is the largest in the region";
 and are suggested for medium and large organizations.

* Level I Coach: Serve part-time. Facilitate discrete, narrowly focused, Lean process improvement events.

* Level II Coach: Serve full-time. Scope, plan, conduct, follow-up, and assess Lean process improvement events. Lead multiple events or more complex projects. Train and mentor Level I coaches. Develop specialized tools and techniques that target organization's priority needs.

* Level III Coach: Serve full-time. Scope, plan, conduct, follow-up, and assess multiple or integrated Lean process improvement events and events of greater complexity. Train and mentor Level I and Level II coaches. Provide training in specialized tools and techniques. Advise senior leadership on alignment of projects with organization's strategic objectives.

COACH CREDENTIALS

Require minimum Lean coaching credentials when hiring external coaches. All of the organizations studied that succeeded in maturing beyond the Introduction Phase used external coaches. Credential standards should include combination of relevant experience coaching Lean implementations in organizations within a similar environment (such as commercial, government, or non-profit) and mission area (such as such as manufacturing, maintenance/repair/overhaul, or supply-chain management). The credential standards should also specify minimum depth of Lean coaching experience (such as number of process improvement events or projects) and proof of results in improving performance of organizations (such as cost or time reduction).

A Defense organization, with over 8 years experience implementing Lean, has created evaluation criteria for qualification of external coaches. The rating system is available to dozens of subordinate companies, including many with defense system acquisition and sustainment missions. Individual companies or business units within this corporation are expected to hire their external coaches from the approved list Approved list

A list of equities and other investments that a financial institution or mutual fund is allowed to invest in. See: Legal list.


approved list

See legal list.
 of consulting companies Noun 1. consulting company - a firm of experts providing professional advice to an organization for a fee
consulting firm

business firm, firm, house - the members of a business organization that owns or operates one or more establishments; "he worked for a
. Primary coaching credentials monitored are experience, results, and cost. Experience in specific environments, including manufacturing, material management, supply-chain management, and administrative domains (networking) Administrative Domain - (AD) A collection of hosts and routers, and the interconnecting network(s), managed by a single administrative authority.  highlighted. The Website describes experience and indicates relative cost for consultant services. Monetary savings are tracked for each external consultant or consultant's company, but not available on the Website.

A large DoD organization has established minimum qualifications for personnel hired as external coaches. The contract they issued states these minimum qualification standards.

The following six criteria are documented as required for Sensei's providing services in the Statement of Work used by this organization.

1. General Manager with profit and loss responsibilities leading a Lean conversion.

2. Demonstrated World Class results while leading the conversion.

3. Ability to communicate--lead and teach at all levels of organization.

4. In depth knowledge of Toyota Production System The Toyota Production System (TPS) is the philosophy which organizes manufacturing and logistics at Toyota, including the interaction with suppliers and customers. The TPS is a major part of the more generic "Lean manufacturing".  tools.

5. Change management skills.

6. Twenty (20) full cycles of Lean implementation, including value stream analysis, Kaizen This article is about a continual improvement philosophy. For Kaizen ($K), a fantasy currency invented by Kaizen Games, see Priston Tale.

“Red tag” redirects here. For designation of damaged structures, see Red-tagged structure.
, formal Lean training and alignment/assessments.

Select and Certify internal coaches to an organizational standard. This coach selection standard should include previous job performance, participation in Lean activities, and personal traits (such as confidence, communication skills and inclination toward innovation). The internal coach certification standard should include a combination of formal training, experience coaching Lean activities, and auditable results. Medium and large organizations should consider establishing formal certification standards for multiple levels of internal coaches. Suggested certification standards for three coach levels are described below.

* Level I Coach: 2-5 days of classroom training and experience facilitating at least one rapid process improvement event that achieves measurable results.

* Level II Coach: 2-6 weeks of additional formal training. 1-2 years experience planning and executing Lean process improvement events and completion of at least one complex project. Experience mentoring Level I coaches is also highly desirable. Review of credentials by board of Level III coaches may include an interview or exam.

* Level III Coach: Extensive experience planning and executing Lean implementations at multiple levels within multiple organizations. Experience should include breadth of Lean activities to introduction, growth, and sustainment phases, including coaching of highly complex projects. Additional specialized training and experience mentoring Level II coaches is also highly desirable. Review of credentials by senior leaders may include interviews.

COACH MIX

Match mix of internal and external coaches to the Lean Implementation phase. Organizations should employ both internal and external coaches in all three Lean Implementation Phases. Figure 4 depicts a recommended mix of external and internal coaches by Lean implementation phase. Both coach mix and roles should be modified as the implementation progresses from introduction to growth and sustainment phases.

[FIGURE 4 OMITTED]

* Introduction Phase: Focus on using highly experienced coaches that can provide quick and visible successes. Highly experienced coaches increase the probability of achieving early successes by ensuring events are properly scoped and planned and involve the correct people. Typically, highly experienced coaches do not reside in an organization that is just beginning to implement Lean; therefore, they must be obtained from external sources. Leverage the credibility of experienced coaches in having "been there and done that" in a similar organization to help overcome resistance implementing continuous process improvement.

* Growth Phase: Focus on using highly experienced coaches to build and develop an organization's internal coaching capability. During the early Growth Phase, the majority of will probably be external resources; however, in this phase, emphasize the capacity to train and develop coaches using internal resources.

* Sustainment Phase: Focus on conducting the majority of Lean activities using internal coaches but continue to employ external coaches to provide specialized support or an outside source of observation.

Assign coaches to the appropriate reporting chain based on the Lean Implementation Phase. During the Implementation Phase coaches should report directly to the corporate Lean champion (a senior executive or leader with a vested interest Vested Interest

A financial or personal stake one entity has in an asset, security, or transaction.

Notes:
For example, if you have a mortgage, your bank has a vested interest on the sale of your house.
See also: Right
 in the success of the Lean Transformation activities). During the growth and sustainment phases, maintain this reporting relationship as a training center for Lean experts within the parent organization, but move experienced coaches into the line organizations.

COACH TOOLS

Select a standard set of primary tools for coaches to use for planning, executing and evaluating routine process improvement events. This set of tools can be augmented with highly specialized tools such as Six Sigma statistical process control when required.

Each of the following primary coaching tools is a key ingredient to enable Lean teams to systematically achieve rapid and continuous process improvement.

* Planning tools: Sign formal Change Contracts that describe desired outcomes, resources and specific roles (see Figure 5). The absence of change contracts in large organizations reduces the likelihood of implementations continuing beyond the introduction phase. After initial successes, organizations should employ more rigorous method to select and prioritize pri·or·i·tize  
v. pri·or·i·tized, pri·or·i·tiz·ing, pri·or·i·tiz·es Usage Problem

v.tr.
To arrange or deal with in order of importance.

v.intr.
 processes to apply Lean.

[FIGURE 5 OMITTED]

During event preparation, coaches worked closely with process managers and event leaders to develop a change contract. In medium and large organizations, coaches frequently used change contracts to clarify management expectations and secure commitment of needed resources.

Change contracts served as charters for process improvement teams by clarifying expected outcomes, resources and establishing responsibilities for event leaders and participants. Change contracts in larger organizations were often signed by senior management to help communicate commitment to employees. In smaller organizations, the use of change contracts and other formal communication tools was less frequently observed.

* Execution tools: Use Value Stream Mapping (VSM VSM Value Stream Mapping (manufacturing process evaluation technique)
VSM Vibrating Sample Magnetometer
VSM Vascular Smooth Muscle
VSM Visual Studio Magazine
VSM Vietnam Service Medal
VSM Virtual Shared Memory
VSM Viable Systems Model
) to help organizations make fact-based decisions throughout process improvement activities in each implementation phase. VSM can also help with selection and prioritization of process improvement events and more complex improvement projects. VSM is described in the book titled Learning to See by Mike Rother and John Shook (1999). The photo below (Figure 6) illustrates a Value Stream Map created by the Global Hawk System Program Office detailing their Tier I Enterprise.

[FIGURE 6 OMITTED]

* Evaluation tools: Asses benefits and costs of implementing Lean during all three phases. Larger organizations should establish a common method for determining Return On Investment (ROI (Return On Investment) The monetary benefits derived from having spent money on developing or revising a system. In the IT world, there are more ways to compute ROI than Carter has liver pills (and for those of you who never heard of that expression, it means a lot). ) and cost savings for Lean events. While commercial industry may be able to link ROI directly to profit, DoD can compare investment with savings in resources including budget, manpower, material, and schedule.

* ROI was tracked in nearly all organizations implementing Lean. This was a consistent overarching o·ver·arch·ing  
adj.
1. Forming an arch overhead or above: overarching branches.

2. Extending over or throughout: "I am not sure whether the missing ingredient . . .
 objective for beginning and continuing a Lean journey. Investment cost was the cost hiring any external coaches plus the cost of time and materials labor and materials (time and materials) n. what some builders or repair people contract to provide and be paid for, rather than a fixed price or a percentage of the costs.  for participants in an event from within the organization. The return was the amount that was booked to the bottom line (additional profit) as the result of the event. In most organizations, this bottom line saving was only the amount that could be booked during the fiscal year that the costs were incurred. Cost avoidances Cost avoidance is a management accounting term referring to an expense one has avoided incurring. It is commonly used in the field of energy management to describe the energy costs you avoided due to energy management initiatives. , both near--and long-term were tracked, but were not always credited as a true savings as a result of a Lean activity.

* External coaches were often measured based on return on investment. Expectations for booked savings were set for many internal coaches, but were not found to consistently be used as a measure of individual coach's performance. ROI was often used as an overall organization incentive, linking team rewards and recognition to the organization's contribution to the bottom line.

Communicate, Communicate, and Communicate with employees, managers, unions, and other process stakeholders Stakeholders

All parties that have an interest, financial or otherwise, in a firm-stockholders, creditors, bondholders, employees, customers, management, the community, and the government.
. Medium and large size organizations have a stronger need to employ more sophisticated communication tools.

The following example is a powerful communication tool, from a worldwide defense industry leader, that highlights leadership vision, workforce incentive, and action plan. The corporate Lean champion published a letter to employees that clearly described why the organization was implementing Lean and a timed phased strategy. The threepage color letter described 20 building blocks for changing the company's culture to continuous process improvement. Included were targets for full-time Lean managers, minimum annual participation in 5-day process improvement events, and Value Stream Mapping requirement for investments over $250K. The letter was signed by the organizations Chief Operating Officer Chief Operating Officer (COO)

The officer of a firm responsible for day-to-day management, usually the president or an executive vice-president.
 and mailed to the home of every employee.

COACH PERFORMANCE MEASURES

Measure key processes that support an organizations capability to implement Lean. For example, during growth phase, matching the number of coaches available to targets for number of process improvement events is critical. A generally employed rule of thumb is that 1 percent of an organization's workforce serves full-time Lean coaches during the transition from Growth to Sustainment. Other coach support processes that organizations may want to measure include selection/assignment, training/certification, employment/rotation, and retention/promotion of coaches. Tailor Lean coach measurements to motivate key strategic outcomes. Measurements should be continually reviewed and updated to ensure the outcomes being measured are motivating desired behaviors in the coaches, workforce, and managers being evaluated.

Assess coaches' effectiveness based upon a combination of measurable performance (such as planning and executing process improvement activities) and feedback from participants and organizational leaders. Supervisors of coaches should focus their assessment on those responsibilities relevant to the level of performance and on expected outcomes of Lean activities. Coaches should be provided feedback on their effectiveness and value to the organization systematically following milestones, such as the completion of large complex projects.

CONCLUSION

We have highlighted the following nine important areas dealing with coaching strategies.

* Establish several levels of coaches with different degrees responsibilities.

* Require minimum Lean coaching credentials when hiring external coaches.

* Select and Certify internal coaches to an organizational standard.

* Match mix of internal and external coaches to the Lean Implementation phase.

* Assign coaches to appropriate reporting chain.

* Select a standard set of primary tools for coaches to use.

* Communicate, Communicate, and Communicate.

* Measure key processes that support Lean Implementation.

* Assess coaches' effectiveness.

As you continue through this special edition of the Acquisition Review Journal, bear in mind our Number One Recommendation that goes beyond coaching to encompass overall Lean Implementation Strategy: Recognize that implementing Lean methodology is an enabler for continuously improving organizational performance, not for achieving a one-time increase in performance. Organizations should not try to become Lean, but plan, execute, and evaluate Lean activities to continuously improve and provide stakeholders ever-increasing value.

DAU offers a variety of courses in our continuous learning center dealing with Lean and Six Sigma. These are available through the DAU Web site at www.dau.mil under continuous learning.

ACKNOWLEDGMENTS

The authors wish to thank Dr. Beryl beryl (bĕr`ĭl), mineral, a silicate of beryllium and aluminum, Be3Al2Si6O18, extremely hard, occurring in hexagonal crystals that may be of enormous size and are usually white, yellow, green, blue,  Harman and Mr. William Motley from DAU, and Dr. Eric Rebentisch from MIT MIT - Massachusetts Institute of Technology  for guidance and advice during our research project.

REFERENCES

Hermes, C. D. (2002, September-October). Exclusive interview with Gen Paul Gen Paul (July 2, 1895-April 30, 1975), was a French painter and engraver. Biography
Born as Eugène Paul in a house in Montmartre on the Rue Lepic painted by Van Gogh, he began drawing and painting as a child.
 J. Kern Commanding General, U.S. Army Materiel Command Army Materiel Command can refer to:
  • Army Materiel Command (Denmark)
  • United States Army Materiel Command
  • Air Force Materiel Command
  • United States Army Aviation and Missile Command
 (AMC). Army AL&T, PB70-02-5, 2-4.

Jaynes, C. C. (2002). Annual report of lean implementation CY2001. Naval Air Station Lemoore, CA: Aviation Intermediate Maintenance Division.

McCormack, R. A. (2002a). Army Materiel Command. In R. A. McCormack (Ed.), Lean machines--Learning from the leaders of the next industrial revolution (pp. 145-150). Annandale, VA: Publishers & Producers.

McCormack, R. A. (2002b, July 31). U.S. Army embraces lean manufacturing. Manufacturing News, 9, 7-10.

Womack, J. P., Jones, D. T., & Roos, D. T. (1991). The machine that changed the world. New York New York, state, United States
New York, Middle Atlantic state of the United States. It is bordered by Vermont, Massachusetts, Connecticut, and the Atlantic Ocean (E), New Jersey and Pennsylvania (S), Lakes Erie and Ontario and the Canadian province of
: HarperPerennial.

Womack, J. P., & Jones, D. T. (1996). Lean thinking. New York: Simon & Schuster Simon & Schuster

U.S. publishing company. It was founded in 1924 by Richard L. Simon (1899–1960) and M. Lincoln Schuster (1897–1970), whose initial project, the original crossword-puzzle book, was a best-seller.
.

AUTHOR BIOGRAPHIES

Lieutenant Colonel Steve Brown Steve Brown is the name of more than one person of note:
  • Steve Brown (musician) (born 1942), American jazz guitarist, composer, and educator.
  • Steve Brown (actor)
  • Steve Brown (athlete), Trinidad and Tobago sprint athlete
, USAF, is a Professor of Life-Cycle Logistics Management Logistics Management is that part of Supply Chain Management that plans, implements, and controls the efficient, effective, forward, and reverse flow and storage of goods, services, and related information between the point of origin and the point of consumption in order to meet  at the Defense Acquisition University. He is a Certified Professional Logistician lo·gis·tic   also lo·gis·ti·cal
adj.
1. Of or relating to symbolic logic.

2. Of or relating to logistics.



[Medieval Latin logisticus, of calculation
 with more than 20 years experience in operational, acquisition, and sustainment logistics. He served as a squadron commander and in key acquisition positions on aircraft programs including the F-22. His master's degree master's degree
n.
An academic degree conferred by a college or university upon those who complete at least one year of prescribed study beyond the bachelor's degree.

Noun 1.
 in systems engineering is complimented by postgraduate education
See also: Postgraduate Training in Education


Postgraduate education (often known in North America as graduate education, and sometimes described as quaternary education
 at Massachusetts Institute of Technology Massachusetts Institute of Technology, at Cambridge; coeducational; chartered 1861, opened 1865 in Boston, moved 1916. It has long been recognized as an outstanding technological institute and its Sloan School of Management has notable programs in business,  and Harvard. The DoD and the International Society of Logistics (SOLE) have recognized his numerous contributions to training logisticians and improving supportability of defense systems.

(E-mail address See Internet address.

e-mail address - electronic mail address
: steve.brown@dau.mil)

Lieutenant Colonel Scott Miller Scott Miller may refer to:
  • Scott Miller, musical theatre scholar, writer, composer, and director; also founder of New Line Theatre, an alternative musical theatre company in St.
, USAF, is a Professor of Systems Engineering and Program Management at the Defense Acquisition University. He recently completed Six Sigma Expert Training at the Raytheon Learning Institute and is a DAWIA DAWIA Defense Acquisition Workforce Improvement Act of 1990  Level III Program Manager. He worked on Acquisition Policy and Strategic Business Planning for the Secretary of the Air Force, Acquisition. Miller managed two classified programs and an advanced concept study for the Air Force. He holds a Bachelor's Degree in Mechanical Engineering from the U.S. Air Force Academy and a master's degree in systems management from the Air Force Institute of Technology The Naval Postgraduate School serves a similar purpose for the U.S. Navy and U.S. Marine Corps. The U.S. Army does not have a comparable school; Army officers study at the Naval Postgraduate School or AFIT.  complimented by postgraduate studies at Harvard and Massachusetts Institute of Technology.

(E-mail address: scott.miller@dau.mil)

Lieutenant Colonel Kent Schvaneveldt, USA, is the Military Deputy for Unmanned Aerial Vehicle A powered, aerial vehicle that does not carry a human operator, uses aerodynamic forces to provide vehicle lift, can fly autonomously or be piloted remotely, can be expendable or recoverable, and can carry a lethal or nonlethal payload.  Systems Air Sensors in the System Manager's Office, Ft. Huachuca, AZ. He is DAWIA certified in program management and contracting. Schvaneveldt commanded multiple commands in the Defense Contracting Management Agency, was a warranted contracting officer A US military officer or civilian employee who has a valid appointment as a contracting officer under the provisions of the Federal Acquisition Regulation. The individual has the authority to enter into and administer contracts and determinations as well as findings about such contracts.  in the Balkans and Central America Central America, narrow, southernmost region (c.202,200 sq mi/523,698 sq km) of North America, linked to South America at Colombia. It separates the Caribbean from the Pacific. , and worked international defense cooperation/security assistance in Turkey. As an Army aviator, he is dual rated in fixed wing and helicopter. His master of business administration (MBA MBA
abbr.
Master of Business Administration

Noun 1. MBA - a master's degree in business
Master in Business, Master in Business Administration
) from the University of New Mexico The University of New Mexico (UNM) is a public university in Albuquerque, New Mexico. It was founded in 1889. It also offers multiple bachelor's, master's, doctoral, and professional degree programs in all areas of the arts, sciences, and engineering.  is complimented by cooperative research with Massachusetts Institute of Technology and completion of the Defense Acquisition University Research Fellowship and Harvard Senior Executive Fellowship The Executive Fellowship Program is sponsored by the California State Center for California Studies and the Office of the Governor to provide an experiential learning opportunity in California state government.  Program.

(E-mail address: kent.schvaneveldt@hua.army.mil)
TABLE 1. ORGANIZATIONS INTERVIEWED

 Organizations Interviewed      Parent Organization     Size

 Corpus Christi Army Depot     Army Materiel Command    2,900

Aeronautical Systems Center     Air Force Materiel
                                      Command           9,300

      F-18 Engine AIMD          Strike Fighter Wing
                                U.S. Pacific Fleet       700

   Talley Defense System       Talley Defense System     200

      Metronics-Xomed                Medtonix            275

    Northrop Grumman Air         Northrop Grumman
       Combat Systems                                   3,000

      Textron Systems              Textron Inc.         2,100

     Warner Robins Air          Air Force Materiel
      Logistics Center                Command          13,000

 Boeing Integrated Systems      The Boeing Company      4,000
(Army Systems - LongbowApach

Lockheed Martin Aeronautics       Lockheed Martin
                                    Corporation        26,000

      Parker Aerospace            Parker-Hannifan
                                    Corporation         3,600

 Raytheon, Space & Airborne          Raytheon           9,300
          Systems

    Air Mobility Command          U.S. Air Force       147,000

 Organizations Interviewed      Domain       Mission

 Corpus Christi Army Depot       DoD       Sustainment

Aeronautical Systems Center                  Systems
                                 DoD       Acquisition

      F-18 Engine AIMD
                                 DoD       Sustainment

   Talley Defense System       Defense    Acquisition &
                               Industry    Sustainment

      Metronics-Xomed           Other     Acquisition &
                               Industry    Sustainment

    Northrop Grumman Air       Defense    Acquisition &
       Combat Systems          Industry    Sustainment

      Textron Systems          Defense    Acquisition &
                               Industry    Sustainment

     Warner Robins Air
      Logistics Center           DoD       Sustainment

 Boeing Integrated Systems     Defense    Acquisition &
(Army Systems - LongbowApach   Industry    Sustainment

Lockheed Martin Aeronautics
                               Defense    Acquisition &
                               Industry    Sustainment
      Parker Aerospace
                               Defense    Acquisition &
                               Industry    Sustainment

 Raytheon, Space & Airborne    Defense    Acquisition &
          Systems              Industry    Sustainment

    Air Mobility Command         DoD       Sustainment
COPYRIGHT 2004 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2004, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:RESEARCH
Author:Schvaneveldt, Kent
Publication:Defense A R Journal
Geographic Code:1USA
Date:Aug 1, 2004
Words:4584
Previous Article:Surveying cost growth.(TUTORIAL)
Next Article:Applying theory of constraints principles and lean thinking at the Marine Corps Maintenance Center.(RESEARCH)
Topics:



Related Articles
Lean markets: a necessity in today's competitive environment. (Technology).(operating strategies )(Brief Article)
Management books for a changing world.(System Approach is strategy for industrial organizations' demands)
Transforming DFAS: generating value and eliminating waste in the world's largest finance and accounting operation.
Taking stock of the lean rough mill: a new study by Virginia Tech finds lean manufacturing is gradually finding its place in North American rough...
How to implement a 'Lean Strategy': it's more than simply a goal to be achieved.
Events.(Happenings)(Calendar)
Events.(HAPPENINGS)(Calendar)
Lean now--using a research community to understand change in the acquisition enterprise.(RESEARCH)(Lean Aerospace Initiative)
T-38C transition to lean.(TUTORIAL)