Prime-power considerations for engineer planners.

Recent experiences in Iraq, Afghanistan, East Timor East Timor (tē`môr) or Timor-Leste (–lĕsht), Tetum Timor Lorosae, republic, officially Democratic Republic of Timor-Leste (2002 est. pop. , and other global hot spots hot spots

acute moist dermatitis.
 have shown that most eater or Joint Task Force-level engineer staffs are largely unfamiliar with the capabilities, limitations, and employment of prime-power assets. Because the 249th Engineer Battalion (Prime Power) is the only unit of its kind in the Army, staff planners simply lack exposure to the unit and training in the employment of its assets. Furthermore, the current doctrinal guidance in Field Manual (FM) 5-422, Engineer Prime-Power Operations, frequently comes up short in bridging the gap between theory and practice because the manual was written before prime power was reorganized into the 249th Engineer Battalion in 1994. (FM 5-422 is being revised and will be published as FM 3-34.483, Engineer Prime-Power Operations.)

The following four lessons have proven to be the most important and most repeated comments over the course of the past two years of operations.

"All Things Electrical"

Often, engineer planners pigeonhole pi·geon·hole  
n.
1. A small compartment or recess, as in a desk, for holding papers; a cubbyhole.

2. A specific, often oversimplified category.

3. The small hole or holes in a pigeon loft for nesting.

tr.
 prime-power soldiers into one or two specific missions rather than capitalizing on the full range of their capabilities. In fact, the prime-power production specialist (military occupational specialty A Military Occupational Specialty (MOS) is a job classification in use in the United States Army and Marine Corps. The occupational specialty system uses a system of letters and numbers to identify general and specific jobs of military personnel.  [MOS (1) (Metal Oxide Semiconductor) See MOSFET.

(2) (Mean Opinion Score) The quality of a digitized voice line. It is a subjective measurement that is derived entirely by people listening to the calls and scoring the results from
] 52E [21P as of October 2003]) is the most versatile and best educated of the "green-suit" electrical specialties in the Department of Defense. Having completed an academically rigorous 50-week course and several technically challenging missions each year since entering the field, each prime-power soldier is capable of expertly accomplishing virtually any electrical mission, including technical assessments and design of power systems; installation, operation, and maintenance of power plants and distribution systems; maintenance and repair of circuit breakers and protective relays; and quality assurance on electrical contractors.

Recent missions which have showcased the versatility of prime-power soldiers include--

* Civil reconstruction efforts in Iraq.

* Installation and operation of four power plants in the Afghanistan theater.

* Base camp planning and design in Iraq.

* Technical reconnaissance of dozens of potential bases in Turkey.

* Construction of an overhead electrical-distribution system at Baghram Airfield.

* Electrical assessments in the Philippines.

* Maintenance of the backup power An additional power source that can be used in the event of power failure. See UPS and backup.


A Half Minute of Backup
This roomful of lead acid batteries stands ready to drain itself entirely in less than a minute.
 plant at Incirlik Air Base The Incirlik Air Base (Turkish: İncirlik Hava Üssü), an important air base in NATO's Southern Region, is located in İncirlik, 12 km east of Adana, Turkey's fifth largest city, and 56 km from the Mediterranean Sea ( , Turkey.

* Acting as the contracting officer's technical representative on U.S. Army Corps of Engineers (USACE USACE United States Army Corps of Engineers ) power contracts.

Engineer planners who recognize the full spectrum of prime power's capabilities and use prime power accordingly will not only improve the quality of support that engineers can provide but will concurrently realize great time and cost savings.

Long Logistical Tail

In general, prime-power units lack the capability to self-sustain below the company level. Since the prime-power platoon is the basic building block in terms of capability (and the company headquarters' current deployment to Baghdad is its first for any operation since prime power was reorganized as a battalion in 1994), this means that most often, deployed prime-power units will need administrative, supply, maintenance, and other support.

The prime-power platoon will require help in ordering and receiving parts and supplies since it has neither an organic supply noncommissioned officer nor a parts clerk. Lacking any mechanics other than for its generators, the platoon requires assistance with wheeled-vehicle and engineer equipment maintenance. With no personnel section, it needs support in processing finance and administrative actions. Finally, a prime-power platoon will require engineer support for excavation or trenching for installation of a distribution system.

If the company headquarters were to deploy (for instance, if two or more platoons simultaneously deployed to the same area), it would bring some of the support capability that the platoon lacks. However, prime power would still lack vehicle maintenance capability and the ability to provide its own dig support.

Although doctrine in this area is fuzzy at best, recent lessons learned have shown that an individual platoon is best tied in with a colocated engineer battalion (combat)(heavy) or a similarly organized construction task force. The company headquarters, being a theater asset, would report directly to the senior engineer unit, whether an engineer command, an engineer brigade (theater Army), or another engineer unit proportional in size to the theater headquarters. In cases where there is no local engineer headquarters of sufficient size, the best command-support relationship is to keep prime power attached to the nearest large engineer headquarters but make the platoon in general support of the local command. While the actual task organization will vary from mission to mission, the rule of thumb is to control prime-power assets at the highest level possible, since their capabilities will be required theaterwide and the soldiers will end up literally all over the battlefield conducting assessments, providing design expertise, offering technical assistance, and executing other missions.

Managing Expectations

Deploying prime power to support base camp development can be expensive, complex, and time-consuming, but it still offers the most responsive, efficient, and cost-effective means of providing reliable, utility-grade power to large military facilities during contingency operations. The timeline for procuring the bill of materials The list of components that make up a system. For example, a bill of materials for a house would include the cement block, lumber, shingles, doors, windows, plumbing, electric, heating and so on.  (BOM) required to construct an electrical-distribution system can be quite lengthy, since most industry has converted to lean manufacturing Lean manufacturing is the production of goods using less of everything compared to mass production: less human effort, less manufacturing space, less investment in tools, and less engineering time to develop a new product.  techniques and small inventories, meaning that most materials are built to order. This can result in delivery schedules of 60 days or longer for materials. However, the procurement timeline for BOM can be significantly shortened by involving prime power in planning early, by anticipating mission requirements, and by using an "off-the-shelf' USACE IAP (Internet Access Provider) See ISP.

IAP - Internet Access Provider
 Worldwide Services Power Contract to streamline the contracting process.

As the 249th Engineer Battalion continues its force modernization process through fiscal year 2004, more platoons will he outfitted with the Deployable Power-Generation and Distribution System, which includes a great deal of "plug-and-play" materials that are compatible with Force Provider and the Air Force's Harvest Eagle/Harvest Falcon bare-base packages. Also, a good portion of the BOM for a base camp electrical system can be found in the Prime-Power Connection Kit, which is available with many Force Provider sets.

The BOM required for most prime-power missions, especially for nonstandard non·stan·dard  
adj.
1. Varying from or not adhering to the standard: nonstandard lengths of board.

2.
 base camp construction, can be expensive, often resulting in initial sticker shock for the customer. For example, the material procurement cost for the 10,000-soldier base camp at Balad Airfield in Iraq was less than $10 million, but that cost will continue to grow (along with all other construction costs) as the standard of living in the theater improves. The high material cost is inherent in the significantly higher level of service and greater reliability afforded by prime-power over unit tactical generators. Engineer staff officers should anticipate the high cost and prepare the customer early to help mitigate sticker shock and manage expectations.

Another customer expectation that needs to be carefully managed is the time required to install a power plant and construct an electrical-distribution system. Once the power plant and associated equipment have been moved to their desired location (often a Herculean effort in itself due to the size and weight of the equipment, special material-handling requirements, and other factors), setting up the plant and delivering electricity to the customer is not an overnight process. Often customers perceive that once the generators are on the ground, prime-power engineers simply and quickly runs a big extension cord to all of the facilities on a base camp. On the contrary, the process of installing a grounding grid, switchgear The term switchgear, used in association with the electric power system, or grid, refers to the combination of electrical disconnects, fuses and/or circuit breakers used to isolate electrical equipment. , miles of cable, and dozens of transformers is a time- and labor-intensive process that requires clear guidance from the customer and prioritization to ensure that the most critical loads A critical load is defined as

”A quantitative estimate of an exposure to one or more pollutants below which significant harmful effects on specified sensitive elements of the environment do not occur according to present knowledge” (Nilsson and Grennfelt 1988)
 are serviced first.

Early In, Early Out

With only eight power-generation platoons on active duty and two more in the Reserve Component (see article on page 55), the 249th Engineer Battalion (Prime Power) is extremely small to be shouldering the U.S. Army's entire prime-power mission. Executing multiple rotations to support combat operations while honoring standing commitments in Korea, Hawaii, and Europe has proven to be a delicate balancing act. In September 2002, the battalion's soldiers were simultaneously engaging in missions in the combat zones of Operation Enduring Freedom, preparing for combat operations in Operation Iraqi Freedom, and conducting disaster relief in Guam, which stretched the unit's members to the breaking point. Consequently, prime power has evolved into an early-entry, contingency solution for filling military power requirements, with each deploying platoon capable of installing and operating a power plant, constructing an electrical-distribution system, and providing technical assistance and planning to fill follow-on power needs.

Power during the first 30 to 90 days of an operation should be provided by unit tactical generators. Prime power provides a transition from 30 to 180 days into an operation and would ideally be relieved by either commercial or contract power. Sources for contracted follow-on power include the Logistics Civil Augmentation Program Standing, long-term contacts designed to augment Service logistic capabilities with contract support in both preplanned and short notice contingencies. Examples include US Army Logistics Civilian Augmentation Program, US Air Force Contract Augmentation Program, and US Navy Construction , Air Force Contract Augmentation Program, (Navy) Emergency Construction Capabilities Contract, and the USACE IAP Worldwide Services Power Contract. Whatever the source, planning for follow-on power should begin early--ideally as soon as the requirement for prime power is identified--to allow for detailed planning and mobilization and the smoothest possible transition from prime power to its successor.

Captain Van Epps commands Bravo Company, 249th Engineer Battalion (Prime Power), Fort Bragg, North Carolina
The article is about the US Army post in North Carolina. For the City in California with the same name, see Fort Bragg, California


Fort Bragg is a major United States Army installation, in Cumberland and Hoke Counties, North Carolina, U.S.
. His previous assignments include service with the 52d Engineer Battalion (Combat)(Heavy) and the 27th Engineer Battalion (Combat)(Airborne).
COPYRIGHT 2003 U.S. Army Maneuver Support Center
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2003 Gale, Cengage Learning. All rights reserved.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Author:Van Epps, Geoff
Publication:Engineer: The Professional Bulletin for Army Engineers
Date:Jul 1, 2003
Words:1512
Previous Article:NCO roles and responsibilities in C2 nodes.
Next Article:Live from Baghdad: its Prime Power.
Topics:



Related Articles
Deputy PM to consider Bank expansion plans.
Base camp infrastructure development and C2 in Afghanistan.
Green ruling changes focus.
Three new TEA pamphlets help transporters with strategic mobility and deployment planning.
Responses sought to new town centres guidance.
Transportation Planning: State and Metropolitan Planning Agencies Report Using Varied Methods to Consider Ecosystem Conservation.
Engineer modularity.

Terms of use | Copyright © 2013 Farlex, Inc. | Feedback | For webmasters | Submit articles