PERRY POWER PLANT RETURNS TO SERVICE; ENDS RECORD YEAR

 PERRY POWER PLANT RETURNS TO SERVICE; ENDS RECORD YEAR
 CLEVELAND, Jan. 5 /PRNewswire/ -- The Perry Power Plant returned to


service following a two-week shutdown.
 The plant restarted on Jan. 3 and began producing electricity for customers today (Sunday, Jan. 5).
 The plant was shut down on Dec. 22 when a fiberglass pipe carrying non-radioactive water broke. The fiberglass pipe has been replaced and its steel support has been redesigned.
 Despite this year-end outage, the Perry Power Plant had its best year since it began commercial operation in 1987. During 1991, the plant:
 -- produced more electricity for customers than any other year, 8,988,755,000 kilowatthours. That's enough electricity to power nearly 1.5 million average homes for the entire year;
 -- was available to generate electricity 90.8 percent of the time;
 -- operated at 86.5 percent of the plant's capacity; and
 -- received high marks for plant performance from the Nuclear Regulatory Commission in its Systematic Assessment of Licensee Performance (SALP) report for the period Aug. 1, 1990 - Oct. 31, 1991.
 The Cleveland Electric Illuminating Company, a subsidiary of Centerior Energy Corporation (NYSE: CX) operates the Perry Power Plant for a consortium of five electric utilities.
 -0- 1/5/92 R
 /CONTACT: Kathy Phyfer of CEI, 216-623-1060/ CO: The Cleveland Electric Illuminating Co. ST: Ohio IN: UTI SU:


JP -- CLSU001 -- 6701 01/06/92 07:10 EST
COPYRIGHT 1992 PR Newswire Association LLC
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1992 Gale, Cengage Learning. All rights reserved.

Article Details
Printer friendly Cite/link Email Feedback
Publication:PR Newswire
Date:Jan 6, 1992
Words:227
Previous Article:SPRINT FILES FOR OPERATING LICENSE IN THE UNITED KINGDOM
Next Article:FEDERAL HOME LOAN BANK OF NEW YORK: LOW IN RATES CLOSE AT HAND
Topics:


Related Articles
PERRY POWER PLANT: A CLEAN AIR INVESTMENT PAYING BIG DIVIDENDS
PERRY POWER PLANT RETURNS TO SERVICE; ENDS RECORD YEAR
PERRY POWER PLANT TO SHUT DOWN FOR THIRD REFUELING/MAINTENANCE OUTAGE
PERRY POWER PLANT CONCLUDES REFUELING AND MAINTENANCE OUTAGE; SHORTEST OUTAGE IN PLANT HISTORY
Perry Plant Turns in Strong Performance.
Perry Plant Begins Refueling Following Successful Operations.
FirstEnergy Adds 425 Megawatts of Generating Capacity at its West Lorain Plant.
FirstEnergy Nuclear Operating Company Announces Senior Management Changes.
Perry Plant Returns to Service After Refueling.
Perry Plant Expected to Return to Service Next Week.

Terms of use | Copyright © 2016 Farlex, Inc. | Feedback | For webmasters