Oriel Resources plc Announces Positive Feasibility Study For The Shevchenko Nickel Laterite Project, Kazakhstan.


LONDON -- Oriel Resources (TSX TSX Toronto Stock Exchange (TSE before April, 2002)
TSX Transfer from Stack Pointer to Index
TSX True Space Extension
:ORL ORL Oto-Rhino Laryngologie (France)
ORL Orlando Executive Airport (Airport Code)
ORL Optical Return Loss
ORL Journal for Oto-Rhino-Laryngology and its related specialties
)(AIM:ORI) is pleased to announce that Bateman Minerals and Metals Ltd (Bateman) has completed the Shevchenko Nickel Project The Nickel Project is a nickname for a transportation funding package enacted by the 2003 Washington State Legislature. The slogan for the package is "It’s your Nickel, Watch it Work."

The $3.
 Feasibility Study The analysis of a problem to determine if it can be solved effectively. The operational (will it work?), economical (costs and benefits) and technical (can it be built?) aspects are part of the study. Results of the study determine whether the solution should be implemented.  and has issued a comprehensive Executive Summary report. The complete detailed report comprising all the relevant appendices is in preparation for release early in 2006. The study was carried out by Bateman as the lead contractor with consultancy support from Wardell Armstrong International (WAI WAI Web Accessibility Initiative (W3C)
WAI Where Am I?
WAI Wales Arts International (UK)
WAI Women in Aviation, International
WAI Warm Air Intake
WAI Web Application Interface
) (UK), Mintek (South Africa South Africa, Afrikaans Suid-Afrika, officially Republic of South Africa, republic (2005 est. pop. 44,344,000), 471,442 sq mi (1,221,037 sq km), S Africa. ) and Polysius (part of the ThyssenKrupp group of companies, Germany) for the resource modelling, mining plan and environmental studies, smelting technology and ore pre-treatment processing aspects respectively.

Highlights of the study, include:

- 47 year project operating life

- Nickel production in first 10 years peaks at an annual 23,765t nickel in 109,000t of ferronickel after an 18 month ramp up Ramp Up

To increase a company's operations in anticipation of increased demand.

Notes:
A company might 'ramp up' operations if they just signed a contract creating substantially more demand for their product.
See also: Demand, Economies of Scale
 period.

- NI43-101 compliant Proven and Probable nickel laterite laterite

Soil layer rich in iron oxide and sometimes aluminum, derived from a wide variety of rocks by leaching. It forms in tropical and subtropical regions where the climate is humid.
 ore reserves of 104.4 million tonnes at 0.79% nickel.

- Capital direct field cost for process plant, infrastructure and mine of $448 million and $594 million including indirect field costs, EPCM EPCM Engineering, Procurement, Construction Management
EPCM Essential Procedures for Clinical Microbiology
EPCM Enhanced Planning Control Message
EPCM Enterprise Portal Content Management
EPCM European Project & Change Management (The Netherlands) 
, insurances and owner's costs.

- Average operating costs operating costs nplgastos mpl operacionales  of $1.91/lb Ni for initial 10 years and $2.12/lb Ni for the first 25 years. Industry average cash cost is $3.42/lb Ni.

- 25 year project NPV NPV

See: Net present value
 (at 8% discount rate) is $275 million and $328 million for full 47 year project life with IRR's of 13.55% and 13.82% respectively, pre-tax at $4.25/lb nickel price (current price $6.50/lb).

The Shevchenko deposit is located within the Kostanai District of Kazakhstan, some 50km southwest of the town of Zhitiqara. The deposit is accessed by a part bitumen bitumen (bĭty`mən) a generic term referring to flammable, brown or black mixtures of tarlike hydrocarbons, derived naturally or by distillation from petroleum. , part hardcore road across the steppe steppe (stĕp), temperate grassland of Eurasia, consisting of level, generally treeless plains. It extends over the lower regions of the Danube and in a broad belt over S and SE European and Central Asian Russia, stretching E to the Altai and S to  from Zhitiqara to the village of Shevchenko which lies a few kilometres to the west of the deposit. Oriel owns 90% of the project and has a Mining Contract with the Government of the Republic of Kazakhstan which allows for full exploitation of the deposit.

The resource infill drilling, geological modelling and mine optimisation plan has increased the overall project life considerably and it is projected to be 47 years based on mining the resource in 24 years. The AusIMM JORC JORC Joint Ore Reserves Committee  (1999) and NI 43-101 compliant reserve is estimated as follows:
Proven - 21.392 million tons @ 0.85% Ni
Probable - 83.023 million tons @ 0.77% Ni.



The Shevchenko resource and this reserve statement have been prepared using Datamine(R) and NPV Scheduler(R) by Dr P Newall and Mr A Wheeler of WAI. Dr. Newall is a qualified competent person in accordance with definitions set out in National Instrument 43-101 and is a chartered engineer In many countries, professional engineers are called Chartered Engineers. The details of registration vary from country to country.

Chartered Engineer may refer to:
  • A Chartered Engineer registered with Engineering Council UK.
 (CEng) and Fellow of the Institute of Materials, Minerals and Mining The Institute of Materials, Minerals and Mining (IOM3) is a major UK engineering institution whose activities encompass the whole materials cycle, from exploration and extraction, through characterisation, processing, forming, finishing and application, to product recycling and  (FIMMM FIMMM Fellow of the Institute of Materials, Minerals and Mining ).

The mine production schedule will produce approximately 2.5Mtpa direct feed ore running at 1.04% Ni in the first ten years of operations with ferronickel production from the furnaces scheduled to start by the end of 2008. Mining of the orebodies is completed in 24 years and direct feed to the furnaces averages 0.95% Ni over this period. Mining produces substantial quantities of lower grade material which will be stockpiled for smelting beyond this 24 year mining period and an overall project life of 47 years is envisaged.

The process plant is based on flash drying and calcining of the ore and uses DC (direct current) arc furnace smelting technology to produce the ferronickel alloy. This technology offers the most economical solution for extracting the nickel, due to comparatively low capital costs, high thermal energy efficiency and high Ni recovery. DC furnace technology has also been shown by Mintek to be well suited to processing the fine Shevchenko ores over the range of compositions expected. Falconbridge has selected a very similar process flowsheet and DC arc technology for their Koniambo project in New Caledonia.

The process flow sheet described below was developed by Bateman, based on the results of comprehensive smelting and ore pre-treatment test work. It consists of ore milling, drying and upgrading in a single Polysius Aerofall(TM) mill, calcining in two Polysius Polcal(TM) suspension calcining systems, smelting in twin-electrode DC arc furnaces and a ladle refining station to remove impurities from the molten ferronickel. This is followed by a shotting station where the molten ferronickel alloy is granulated gran·u·late  
v. gran·u·lat·ed, gran·u·lat·ing, gran·u·lates

v.tr.
1. To form into grains or granules.

2. To make rough and grainy.

v.intr.
, dewatered and stored ready for shipment. Slag from the furnaces will be granulated and disposed on a dump at site, but can also be used as a construction aggregate.

The mined ore is upgraded by screening of the dried product in the drying plant by 6% for a mass loss of some 15% prior to calcining. Accordingly, the average grade of calcined feed to the furnaces in the initial 10 years is 1.2% nickel from which recoveries across the furnace and after refining is estimated at 92.3%. The low grade screened ore will be stockpiled for treatment later in the project life.

The smelting plant is based on two 80 MW DC arc furnaces designed by Bateman that are capable of smelting approximately 2.16Mtpa of upgraded, dried and calcined ore. The average annual production over the initial 10 years (after the 18 month ramp up) of ferronickel alloy is approximately 86,500 tons at a nickel grade of 24% for 20,600t of saleable nickel. The 25 year ferroalloy ferroalloy

Alloy of iron (less than 50%) and one or more other metals, important as a source of various metallic elements in the production of alloy steels. The principal ferroalloys are ferromanganese, ferrochromium, ferromolybdenum, ferrotitanium, ferrovanadium,
 production will average 74,000t with saleable nickel of 18,125t per annum Per annum

Yearly.
.

The ex-works operating cost for the first 10 years is projected as $1.91/lb Ni and $2.12/lb Ni for 25 years. The average cash operating cost for the life of the project is expected to be $2.36/lb Ni. The ferronickel industry average cash cost of production in 2005 was $3.42/lb of nickel.

Capital direct field costs for the plant, infrastructure and mine is $448 million and $504 million including indirect field costs. The total EPCM project capital including insurances and owner's costs, excluding contingency is $594 million.

The NPV (@ 8%) is $275 million for the first 25 years with an un-geared IRR IRR

In currencies, this is the abbreviation for the Iranian Rial.

Notes:
The currency market, also known as the Foreign Exchange market, is the largest financial market in the world, with a daily average volume of over US $1 trillion.
 of 13.55% and the NPV over the life of the project is $328 million with an IRR of 13.82 % based on a nickel price of $4.25/lb, pre -tax.

The project economics at a nickel price of $4.25/lb, pre-tax, are shown in the table below.
---------------------------------------------------------------------
Project Life                        10 Years    25 Years     47 Years
---------------------------------------------------------------------
Operating Costs (ex-works), $/lb Ni     1.91        2.12         2.36
---------------------------------------------------------------------
NPV (at 8% discount rate), $M             -          275          328
---------------------------------------------------------------------
IRR (ungeared), %                         -        13.55        13.82
---------------------------------------------------------------------



Oriel has implemented a tax efficient corporate structure in which to operate the project. However, the project economics have been analysed on a pre-tax basis as Oriel is currently negotiating agreement to have amended taxation legislation applied to the project which may offer relief from corporate income tax for up to 10 years.

Oriel is at an advanced stage with the negotiations for an exclusive off take agreement with ThyssenKrupp Metallurgie that covers worldwide sales of the ferronickel. At this stage of the project development costs associated with the transportation to market have not been factored into the cash cost of production.

The project is extremely well served with main utilities such as power (500kV transmission lines), gas (pipeline linking Russia and Kazakhstan) and main rail line linked to the extensive rail system available throughout CIS Cis (sĭs), same as Kish (1.)


(1) (CompuServe Information Service) See CompuServe.

(2) (Card Information S
, Russia and into China from the nearby town of Zhitiqara. The main infrastructure elements in the capital estimate, include:

- a new 110 kV power line and gas pipeline from Zhitiqara,

- a new rail siding and handling facilities at Zhitiqara,

- a new access road linking the site with existing national road and some limited upgrading of the existing national is also provided in the capital cost, and

- repairs to an existing water reservoir and the construction of a water supply line.

This infrastructure has been designed to be suitable for three 80 MW DC arc furnaces, should an additional furnace be constructed at a later date.

When constructed and in full production the operation will directly employ 752 personnel in a region that suffers from low industrial activity. Socio-economic studies show that the project will bring much needed employment to the region and will be welcomed by the local population.

Dr Sergey V. Kurzin, Executive Chairman, said "I am pleased that this major milestone has been successfully reached on the Shevchenko Project. Oriel is now working with Endeavour Financial, its financial advisers, to look at the best way to advance the project in order to unlock the maximum value for the shareholders. We are therefore considering various options as to how to progress the project including financing and strategic partnerships. The long term sustainable supply of nickel to the growing markets in Asia, Russia and Europe is the main objective of the Shevchenko nickel project and we have reached the stage where it is much closer to becoming a reality. "

Oriel Resources plc (TSX:ORL) (AIM:ORI)
COPYRIGHT 2005 Business Wire
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Publication:Business Wire
Date:Dec 16, 2005
Words:1495
Previous Article:Tokyo District Court Denies Intel K.K. Argument to Keep Evidence Obtained by JFTC of Illegal Business Practices from the Public Record.
Next Article:Enova Enters into a School Bus Program with Major N.A. Truck and Bus Manufacturer.
Topics:



Related Articles
Altai acquires nickel-cobalt property in the Phillipines.
The Nevada Star Resource Corp. Update on The MAN Alaska Canwell Complex: Fundamental Ingredients for World-Class Discovery.
Weda Bay Minerals Reports on Preparations for Definitive Feasibility Study at the Halmahera Nickel/Cobalt Project.
Weda Bay Minerals Awards Pre-Feasibility Update Contract to Aker-Kvaerner.
CVRD Increases its All Cash Offer to Acquire Canico Shares and Enters into Support and Lock-Up Agreements.
Weda Bay Minerals Inc. Releases Third Quarter Report.
Weda Bay Minerals Announces Completion of $17.6 Million Private Placement.
Falconbridge Responds to French High Court of Justice Ruling.
Falconbridge Provides Update and Preliminary Resource Estimate for the Araguaia Nickel Project, Para State, Brazil.
Junior eyes copper-nickel mine near Agnew Lake.(URSA Major Minerals Inc)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles