NORTHEASTERN ONTARIO REGION--Capital Plan 2006-07

Carry Over Highway Construction

                               County/Region/
Hwy #  Description             District          Contractor

144    Bridge replacement      Sudbury           Teranorth Construction
                                                 & Engineering Ltd.
101    Resurfacing             Sudbury           Leo Alarie and Sons
                                                 Ltd
 17    Bridge replacement      Algoma            Teranorth Construction
                                                 & Engineering Ltd.
  6    Bridge Rehabilitation   Manitoulin        Dupont Painting
                                                 Contracting Limited
  6    Reconstruction          Manitoulin        Pioneer Construction
                                                 Inc
 11    Reconstruction,         Nipissing         Miller Paving Limited
       Commercial, Vehicle
       inspection station,
       Bridge Rehabilitations
534    Bridge replacement      Parry Sound       Nor Eng Construction &
                                                 Engineering Inc.
 11    Reconstruction/Passing  Cochrane          M J Labelle Co. Ltd
       lanes
 17E   New 4 lane highway/     Sault Ste. Marie  Teranorth Construction
       advance clearing                          & Engineering Ltd.
 17E   New 4 lane highway      Sault Ste. Marie  Garden River
                                                 Constructors
 17E   New 4 lane highway      Sault Ste. Marie  Carillion Canada Inc
 69    Four laning/new         Parry Sound       Bot Construction
       highway

New 2006-07 Highway Construction

                               County/Region/
Hwy #  Description             District          Contractor

 17    Reconstruction/         Nipissing         Miller Paving Limited
       Culvert
       rehabilitation
 11    Bridge Rehabilitation   Cochrane          Miller Paving Limited
 69    Reconstruction          Sudbury           Pioneer Construction
                                                 Inc
 63    Resurfacing/Culvert     Nipissing         Aecon Construction and
       rehabilitation                            Materials Ltd
 11    Resurfacing/            Cochrane          Miller Paving Limited
       intersection
       improvements/culvert
       rehab.
129    Reconstruction          Algoma            Pioneer Construction
                                                 Inc
624    Culvert replacements    Timiskaming       Belanger Construction
                                                 (1981) Inc
 17    Culvert replacements    Algoma            Belanger Construction
       Culvert                                   (1981) Inc
       Rehabilitation
655    Reconstruction,         Cochrane          M J Labelle Co. Ltd
       Culvert
       rehabilitation
 17    Culvert replacements    Algoma            Teranorth Construction
                                                 & Engineering Ltd.
 69    Four-laning             Sudbury           Pioneer Construction
                                                 Inc

Carry Over Highway Construction

                                                   Target Completion
Hwy #  Description             Value   Start Date  Date

144    Bridge replacement       $3.9M  2005        2006
101    Resurfacing               7.8M  2004        2006
 17    Bridge replacement       $6.4M  2005        2006
  6    Bridge Rehabilitation    $1.4M  2005        2006
  6    Reconstruction           $5.2M  2005        2006
 11    Reconstruction,         $25M    2006        2007
       Commercial, Vehicle
       inspection station,
       Bridge Rehabilitations
534    Bridge replacement       $2M    2005        2006
 11    Reconstruction/Passing  $14M    2005        2006
       lanes
 17E   New 4 lane highway/      $9M    2006        2007
       advance clearing
 17E   New 4 lane highway      $63.4M  2000        2007
 17E   New 4 lane highway      $37.1M  2004        2007
 69    Four laning/new         $60.4M  2005        2008
       highway

New 2006-07 Highway Construction

                                                   Target Completion
Hwy #  Description             Value   Start Date  Date

 17    Reconstruction/         $13.7M  2006        2007
       Culvert
       rehabilitation
 11    Bridge Rehabilitation    $3.9M  2006        2007
 69    Reconstruction           $4.9M  2006        2006
 63    Resurfacing/Culvert      $7.3M  2006        2006
       rehabilitation
 11    Resurfacing/             $4.1M  2006        2006
       intersection
       improvements/culvert
       rehab.
129    Reconstruction           $7.0M  2006        2006
624    Culvert replacements     $4.5M  2006        2007
 17    Culvert replacements     $0.6M  2006        2006
       Culvert
       Rehabilitation
655    Reconstruction,         $13M    2006        2007
       Culvert
       rehabilitation
 17    Culvert replacements     $4.3M  2006        2007
 69    Four-laning             $72M    2006        2008

NOTE: Project timing is subject to change based on funding, planning,
design, environmental approval, property acquisition and construction
requirements.
(SHIP): Strategic Highway Infrastructure Program--Provincial/Federal
Partnership Program. Information provided by Ministry of Transportation
COPYRIGHT 2006 Laurentian Business Publishing, Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2006, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:SPECIAL REPORT: CONSTRUCTION
Publication:Northern Ontario Business
Geographic Code:1CANA
Date:Aug 1, 2006
Words:460
Previous Article:Cottage country moves north.(Parry Sound)
Next Article:Tenders out for hospital projects.(SPECIAL REPORT: CONSTRUCTION)
Topics:



Related Articles
Going deeper poses challenges.
Northern Ontario construction projects (planned/proposed). (Northern Numbers).(Brief Article)(Illustration)(Statistical Data Included)(Directory)
Mill owners fear North's wood, jobs on route to Quebec.(Forestry)
Four-laning paves way for new business case.(NORTH BAY)
Hydro project has power to create 250 jobs.(SPECIAL REPORT: TIMMINS)
Timmins Science Village to open in 2008.(SPECIAL REPORT: TIMMINS)
NEOnet downloads innovation award: non-profit web-spreader recognized for technology development model.(TIMMINS)(North Eastern Ontario Communications...
Town may convert mothballed mill: a Quebec company is looking at producing wood chips and hog fuel at a vacated Tembec sawmill in Opasatika.
Chambers call for Highway 11 upgrades.(SPECIAL REPORT: TIMMINS)
CITY TO ROLL OUT BUDGET TUESDAY SANTA CLARITA EXPENDITURES TO RISE DESPITE EXPECTED REVENUE DECLINE.(News)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles