Music city showdown: a Nashville project studies the benefits of re-using segregated and salvaged materials. (Demolition Trends).When the Metropolitan Government of Nashville and Davidson County Davidson County is the name of two counties in the United States:
Gershman, Brickner & Bratton Inc. (GBB GBB Groningen Biomolecular Sciences and Biotechnology Institute (The Netherlands) GBB Gas Blow Back GBB General Broadband GBB Globe Broadband ), Fairfax, Va., is a consultant to Metro Nashville responsible for overseeing parts of the project, including preparation of the site on which a utility company will construct a new District Energy System (DES) near downtown Nashville. GBB sought several bids using different dismantling dis·man·tle tr.v. dis·man·tled, dis·man·tling, dis·man·tles 1. a. To take apart; disassemble; tear down. b. , demolition and construction methods to yield a process that would be environmentally responsible, while also serving the taxpayers by holding costs down. The bid involved two major construction projects currently progressing directly to the south of the Nashville Thermal Transfer See thermal wax transfer printer and direct thermal printer. Corporation (NTTC NTTC National Technology Transfer Center NTTC Naval Technical Training Center NTTC National Tank Truck Carriers, Inc. NTTC North Texas Technology Council NTTC Non-Taxable Transaction Certificate (state of New Mexico) ), a waste-to-energy plant that provided heating and cooling to more than 35 buildings in the downtown Nashville area for almost 30 years. Ray Bell Construction Co. is working under contract to the Tennessee Department of Transportation The Tennessee Department of Transportation (TDOT) monitors all road projects in the state of Tennessee. It is headquartered in Nashville, Tennessee, located at the confluence of three major Interstate Highways. (TDOT TDOT Tennessee Department of Transportation TDOT Tucson Department of Transportation TDOT Texas Department of Transportation TDOT Tuscaloosa Department of Transportation (Tuscaloosa, AL) ) to complete the new Gateway Bridge/Boulevard construction project. Also nearby, and the principal subject of this article, the new Metro Nashville District Energy System (DES) contract has been awarded to Constellation Energy Constellation Energy (NYSE: CEG), headquartered in Baltimore, Maryland, generates, trades, supplies, and distributes energy. The company operates over 35 power plants in 11 states (mainly Maryland, Pennsylvania, New York, West Virginia, and California) under its operating Source Inc. (CES) of Baltimore, Md. The development of these two neighboring neigh·bor n. 1. One who lives near or next to another. 2. A person, place, or thing adjacent to or located near another. 3. A fellow human. 4. Used as a form of familiar address. v. projects required the ultimate demolition and site-related cleanup of a total of six buildings, collectively known throughout this article as the Work Zone. GBB issued a Request for Proposal (RFP (Request For Proposal) A document that invites a vendor to submit a bid for hardware, software and/or services. It may provide a general or very detailed specification of the system. 1. (business) RFP - Request for Proposal. 2. ) indicating that the overall project site demolition would involve all six buildings in the Work Zone. The RFP described the overall needs of the project, but by doing so in an integrated manner with subdivided costs, assigned the respective costs to the two main parties involved--TDOT and Metro Nashville--that were funding the overall project. It was expected that the selected demolition contractor from the RFP process would sign an agreement for five building parcels with the TDOT general contractor A general contractor is an organization or individual that contracts with another organization or individual (the owner) for the construction of a building, road or any other execution of work or facility. and an additional contract with Metro for Guardian Building The Guardian Building, designated a National Historic Landmark on June 29, 1989, is a skyscraper in downtown Detroit, Michigan. Built in 1928 and finished in 1929, the building was originally called the Union Trust Building No. 2. Because the two prime contractors had contracts with TDOT and Metro respectively, certain terms and conditions of their prime contracts were also included in two unique subcontracts provided as attachments or references in GBB's RFP. THE RFP PROCESS GBB solicited formal written proposals from a group of pre-selected contractors to demolish de·mol·ish tr.v. de·mol·ished, de·mol·ish·ing, de·mol·ish·es 1. To tear down completely; raze. 2. To do away with completely; put an end to. 3. the current structures, while hopefully maximizing the beneficial reuse reuse - Using code developed for one application program in another application. Traditionally achieved using program libraries. Object-oriented programming offers reusability of code via its techniques of inheritance and genericity. of the demolition debris to the greatest extent economically practicable practicable adj. when something can be done or performed. . The RFP noted that both the new Metro DES facility and the new Gateway Boulevard Gateway Boulevard is a major one-way street in Edmonton, Alberta. It is part of the Alberta provincial highway 2. It's a northbound road and it runs parallel with Calgary Trail, which is the southbound part of Highway 2. would require certain "fill materials." The selected demolition contractors were encouraged by GBB to confirm the quantities and the specifications of the on-site "fill material" they could produce, reducing the off-site hauling and landffiling of materials and optimizing the recovery of recyclable re·cy·cle tr.v. re·cy·cled, re·cy·cling, re·cy·cles 1. To put or pass through a cycle again, as for further treatment. 2. To start a different cycle in. 3. a. materials from the Work Zone. GBB issued the RFP and proposals were accepted on June 17, 2002. A table with the specific key target dates for demolition of the six buildings was included in the RFP. Bidders were required to consider and pay careful attention to this timetable in the preparation of the proposal, because the schedule and interface of Work Zone activities were critical to the schedules of the new construction to be undertaken by CES and Ray Bell, the bridge building contractor building contractor n → contratista m/f de obras building contractor n → entrepreneur m (en bâtiment) building contractor . Therefore, site activities and coordination with each of the prime contractors were important to the success of the demolition project. The demolition contractor was required, at minimum, to achieve and maintain the performance outcomes listed in the RFP, consistent with performance standards agreed to through the two contracts resulting from the RFP process. Additionally, all salvaged materials, including an estimate of materials stockpiled or used as "fill materials" were also required to be inventoried by the demolition contractor for use by CES and Ray Bell on their respective new construction projects. The demolition contractor was required to follow contract requirements; obtain all permits from appropriate agencies; establish site security; interface with all utility companies with service lines within the Work Zone; provide/coordinate appropriate road closures as required; provide a responsible on-site manager(s); assign qualified persons to the contracts; provide the equipment required to do the assigned task or accomplish the requirements and outcomes; maintain records of expenditures, deliverables and progress; submit required reports in a timely fashion; and maintain a clear line of communication for prompt resolution of problems. The use of explosives by the demolition contractor was not permitted for the project, and during the term of Work Zone activity by the demolition contractor, the "onsite" selling of salvaged materials was not permitted. A MENU OF OPTIONS As provided for within the terms of the RFP, the bidder could propose three specific methodologies for the project's work effort. However, the bidder was not required to propose on all options. The alternatives for the on-site work included: (1) Traditional demolition- with limited salvage salvage, in maritime law, the compensation that the owner must pay for having his vessel or cargo saved from peril, such as shipwreck, fire, or capture by an enemy. Salvage is awarded only when the party making the rescue was under no legal obligation to do so. as determined to be economically viable by the proposer. Under method one, it was assumed that the majority of all project materials (probably everything but metals) would be removed from the Work Zone and disposed of in a nearby C&D landfill. (2) Selected demolition- with the on-site inerts (concrete, block, brick, asphalt asphalt (ăs`fôlt, –fălt), brownish-black substance used commonly in road making, roofing, and waterproofing. Chemically, it is a natural mixture of hydrocarbons. , dirt, rocks, etc.) segregated from the non-inert materials at the Work Zone and processed by the demolition contractor into "fill material" at properties within the Work Zone or as part of the bridge-building project. (3) Optimum Material Segregation segregation: see apartheid; integration. and Salvage- with the same work parameters as detailed in method two above, except that the red brick facades would be peeled from all of the buildings to the greatest extent possible, cleaned of all mortar and any other disfigurations and organized/stockpiled/wrapped on pallets for future use on site as part of a new construction project. For purposes of this proposal option, the demolition contractor was to assume that the palletized bricks would be relocated re·lo·cate v. re·lo·cat·ed, re·lo·cat·ing, re·lo·cates v.tr. To move to or establish in a new place: relocated the business. v.intr. and transported for storage by the demolition contractor until needed within the Work Zone. Using cost forms provided in the RFP, the bidder provided the related costs for each building for which the firm would provide the work described in the RFP. As a result of the RFP process, Levy Wrecking Co., Nashville, was the demolition company selected as the contractor, subject to successful negotiations with each prime contractor. Based on the competitive RFP structure developed by GBB, the "selective demolition" process with inerts processing for use as fill material during the subsequent construction process (method two) was the least expensive by approximately $60,000, or about 6 percent less than the traditional demolition with materials (exclusive of salvaged metals) hauled to a disposal site (method one). Within the materials markets of Nashville, the method three cost proposal for adding a large-scale red brick segregation/cleaning/stacking/palletizing activity for future re-use came in at slightly more than $1 million. The cost to set up and operate a segregation/cleaning operation for the entire project was proposed at a marginal cost Marginal cost The increase or decrease in a firm's total cost of production as a result of changing production by one unit. marginal cost The additional cost needed to produce or purchase one more unit of a good or service. of $170,000. This created a total cost that was 18.9 percent more expensive than the method-two option ultimately selected. Equally important was the fact presented in Levy's RFP response that they only expected to be able to recover about 30 percent of the face-brick available on the outside of the project buildings. CONCLUSIONS In finalizing the Metro contract with Levy, Metro also received a supplemental price from Levy of $9.00 per cubic yard for bringing additional fill material onto the site (price delivered and spread onto the site) if needed for final site grading of the new construction Work Zone. Based on their proposal, Levy estimated a total of 12,400 cubic yards of fill materials would be generated from the buildings, including their foundations. With an established value of $9.00 per cubic yard, upfront cooperation on keeping the material on site and having it reduced by the demolition company to meet the specifications of the construction contractors saved the two projects an estimated $111,600. During final contract negotiations, Ray Bell decided to use another demolition firm for its project, while Metro did contract with Levy for handling the Guardian Building No. 2. The TDOT-Ray Bell Gateway Project generated approximately 11,800 cubic yards of "fill material" that was reduced to specifications and left on the Work Zone site. Another 3,800 cubic yards of fill material was hauled off site. The C&D material hauled to landfill was 3,720 cubic yards. Additionally, the TDOT-related Projects generated approximately 122.5 tons of concrete reinforcing bar and 254 tons of scrap metal. All of this metal was recycled. Another 150 tons of metal and rebar re·bar n. 1. A rod or bar used for reinforcement in concrete or asphalt pourings. 2. A group of such rods forming a grid. [re(inforcing) bar.] was recycled from the Metro DES building, with approximately 600 cubic yards of materials landfilled. Metro was very pleased with the overall savings associated with the "selective demolition" project that was created because of the ability to understand the "future needs" of the follow-on new construction contractors of both the Gateway Bridge and the Metro DES project. Without a demolition-new construction coordinator, the demolition company may have removed all materials, including footers down to subgrade sub·grade n. The level layer of rock or earth upon which the foundation of a road or railway is laid. , and left a "clean site" for the two new construction companies, potentially at a cost $58,750 higher than proposed. While it would have been nice to preserve some of the used bricks for reuse at other Metro projects, the current economics within the Nashville area (as determined by this public RFP process) did not justify an extensive brick salvage/ re-use project. In summary, Metro's commitment to "green demolition" saved Metro an estimated $200,000 ($58,750 on the specific demolition activity plus another $140,000 by eliminating the purchase of off-site fill material for the two projects). GBB estimates that at least 82 percent of the overall volume of materials within the six buildings was re-used as fill material at the DES or contiguous Adjacent or touching. Contrast with fragmentation. See contiguous file. Gateway Bridge site, and more than 525 tons were recovered as scrap metal. The author is a senior vice president with solid waste and recycling recycling, the process of recovering and reusing waste products—from household use, manufacturing, agriculture, and business—and thereby reducing their burden on the environment. consulting firm Noun 1. consulting firm - a firm of experts providing professional advice to an organization for a fee consulting company business firm, firm, house - the members of a business organization that owns or operates one or more establishments; "he worked for a Gershman, Brickner & Bratton Inc. (GBB), Fairfax, Va. He can be contacted at bbrickner@gbbinc.com. General Work Specifications for the DES Project * All material from such work designated for segregation and/or salvage, to be processed by the demolition contractor into "fill material" or cleaned and stacked Stacked is an American television sitcom that premiered on Fox on April 13, 2005. On May 18, 2006, Stacked was cancelled, leaving five episodes unaired in the United States. The last episode aired on January 11, 2006. in the case of salvaged whole Fed brick was to be removed from the buildings without unnecessary damage in sections or pieces which could be readily transported and processed and/or cleaned to meet typical market conditions and stored and protected by the demolition contractor at specified places within the Project limits. * All materials not so designated were to become the property of the demolition contractor and be disposed of outside the limits of view from the project. If the material was going to be disposed of on private property, the demolition contractor was required to secure written permission from the property owner. * Foundations of buildings and other structures were to be removed to a depth of not less than one foot below natural ground, except within construction limits where removal was to be to a depth of not less than two feet below sub-grade elevation elevation, vertical distance from a datum plane, usually mean sea level to a point above the earth. Often used synonymously with altitude, elevation is the height on the earth's surface and altitude, the height in space above the surface. . All basement floors and vertical support walls/columns were also to be removed. Basements or cavities left by structure removal were required to be filled to the level of the surrounding ground or to sub-grade elevation within the plan of the new construction area, if any. * Roadway support walls, culverts and drainage structures, the removal of which might cause traffic or pedestrian problems, or structures currently in use by traffic were not allowed to be removed until satisfactory arrangements had been made by the demolition contractor to accommodate traffic and/or shore-up the supporting structures or prevent earthen earth·en adj. 1. Made of earth or clay: an earthen fortification; an earthen pot. 2. Earthly; worldly. collapse under or around such structures. Inert inert /in·ert/ (in-ert´) inactive. in·ert adj. 1. Sluggish in action or motion; lethargic. 2. materials designated to become the property of TDOT or Metro as "fill material" were required to be handled and processed according to according to prep. 1. As stated or indicated by; on the authority of: according to historians. 2. In keeping with: according to instructions. 3. the "fill material" specifications. WWW WWW or W3: see World Wide Web. (World Wide Web) The common host name for a Web server. The "www-dot" prefix on Web addresses is widely used to provide a recognizable way of identifying a Web site. .CDRECYCLER.COM
Estimated Costs Via Three Different Methods
Method #1 Method #2
(Traditional (Selected
Demolition (1)) Demolition (2))
I. Metro Project:
A. Guardian/Metro DES $258,750 $245,000
II. TDOT Project(s):
A. Bolden $30,000 $28,000
B. Guardian--TDOT $96,000 $89,000
C. Ragland--Install America $78,000 $75,000
D. Ragland--Stephens $477,000 $444,000
E. Norma's $18,000 $18,000
III. Cost to set up and operate N/A N/A
brick segregation & cleaning
operation for entire 5-
building project:
Total Project Cost $957,750 $899,000
Method #3
(Brick Facade
Removal (3))
I. Metro Project:
A. Guardian/Metro DES $287,000
II. TDOT Project(s):
A. Bolden $44,000
B. Guardian--TDOT $125,000
C. Ragland--Install America $110,000
D. Ragland--Stephens $478,000
E. Norma's $25,000
III. Cost to set up and operate $170,000
brick segregation & cleaning
operation for entire 5-
building project:
Total Project Cost 1,069,000 (4)
Note (1): With waste hauled to licensed disposal facility.
Note (2): With all brick, block and concrete from all buildings
processed on site "to spec" and excess stockpiled in specified area
for use later as prime contractors fill material.
Note (3): Red brick facades peeled from the buildings to the greatest
extent possible, cleaned of mortar and stockpiled on pallets; all
concrete block and concrete walls/slabs/floors from all buildings
processed on site "to spec" and excess stockpiled in specified area
for use later by prime contractors fill material or at other metro
sites.
Note (4): Based in part on demolition contractor's estimate of
percentage (30 percent) of total available project bricks that might be
recoverable/salvageable.