Managing a product development team: Part II; growing the team.


In Part I of this article (Defense AT & L, March-April 2004), the authors presented several of the management issues hampering the effective startup of a project to re-engineer the aging Hubble Space Telescope Hubble Space Telescope (HST), the first large optical orbiting observatory. Built from 1978 to 1990 at a cost of $1.5 billion, the HST (named for astronomer E. P. Hubble) was expected to provide the clearest view yet obtained of the universe.  (HST (1) See Hubble Space Telescope.

(2) An earlier asymmetrical modem protocol from U.S. Robotics that included error control and compression and transmits from 4800 to 14400 bps in one direction and from 300 to 400 bps in the other.
) ground system. The initial challenges facing the management team were significant. The schedule was aggressive and non-negotiable. The team had to maximize use of existing maintenance personnel to undertake new development, while at the same time creating "new and better ways of doing business" that required discarding business processes that were ingrained in·grained  
adj.
1. Firmly established; deep-seated: ingrained prejudice; the ingrained habits of a lifetime.

2.
 in the user community. The primary project management goal became to eliminate the sources of inefficiency on the project by building a culture that fostered an atmosphere of cooperation and that was success-oriented. Several of the actions taken to overcome these issues were presented in the previous article. Part II builds upon these, discusses the methods used to build a cohesive cohesive,
n the capability to cohere or stick together to form a mass.
, synergistic synergistic /syn·er·gis·tic/ (sin?er-jis´tik)
1. acting together.

2. enhancing the effect of another force or agent.


syn·er·gis·tic
adj.
1.
 team environment, and presents several implementation strategies that were used successfully on the project.

**********

As noted in Part I, one of the original constraints of the Hubble Space Telescope (HST) project was to use a legacy software staff. Despite our doubts about the technical currency of this team, they embodied em·bod·y  
tr.v. em·bod·ied, em·bod·y·ing, em·bod·ies
1. To give a bodily form to; incarnate.

2. To represent in bodily or material form:
 the Hubble domain knowledge that was both critical and necessary to development of the new control center. Since a decision had been made to develop the control center using object oriented See object technology and object-oriented programming.  (OO) technology targeting a Unix[R] environment, the challenge became one of "converting" as many legacy programmers as possible to the object management technology (OMT (Object Modeling Technique) An object-oriented analysis and design method developed by James Rumbaugh. See Rational Rose.

OMT - Object Modelling Technique
) methodology. One of the greatest obstacles was convincing the team of both the personal and programmatic pro·gram·mat·ic  
adj.
1. Of, relating to, or having a program.

2. Following an overall plan or schedule: a step-by-step, programmatic approach to problem solving.

3.
 benefit to transitioning their design skills. This the management team did through a series of technical briefings that demonstrated the additional capabilities and flexibility of the OO technologies. These briefings served to convince senior members of the legacy staff that the HST project would benefit from employing modern software design principles, such as OO programming, in order to develop a system that had to last at least another decade.

At this point, the green light was given by HST senior management for a hiring binge to acquire additional staff with key OO and C++/Java skills. A major objective was to use these new team members to bring the legacy staff up to the necessary level of technical capability. This was accomplished through the following multi-faceted training approach.

We initiated a massive, just-in-time training effort for the whole development team (at this point the architecture of the new Hubble control center system was just about completed). We brought in house some of the top OO trainers in the nation to provide targeted training. The traditional training approach was reversed by first training the team in the C++ language specifics (they were already familiar with FORTRAN and in some cases the C language) and then providing onsite training courses in generalized OO analysis and OO design. This approach worked better because the staff were more comfortable with implementation technologies from which they could then abstract the methodological underpinnings.

The vendors of the major commercial off-the-shelf Commercial off-the-shelf (COTS) is a term for software or hardware, generally technology or computer products, that are ready-made and available for sale, lease, or license to the general public.  (COTS (Commercial Off-The-Shelf) Refers to ready-made merchandise that is available for sale. See MOTS.

(software) COTS - commercial off-the-shelf. See commercial software.
) products that were selected into the architecture of the new system were willing to train the team in the specifics of their products. To supplement the standard classroom training, technical consultants (see next page) were brought in; they not only mentored the team, but were exemplar ex·em·plar  
n.
1. One that is worthy of imitation; a model. See Synonyms at ideal.

2. One that is typical or representative; an example.

3. An ideal that serves as a pattern; an archetype.

4.
 software developers in their own right.

To improve our contacts with outside industry, the staff were encouraged to attend technical conferences and to present papers or provide demonstrations of the Control Center System (CCS (1) (Common Channel Signaling) A communications system in which one channel is used for signaling and different channels are used for voice/data transmission. Signaling System 7 (SS7) is a CCS system, also known as CCS7. See SS7. ) technologies under development.

Internal technical demonstrations of mature software were scheduled not only for the CCS staff, but for Goddard senior management as well. This was not only a morale boost for the presenters, but provided another means for communicating technical information throughout the development team and to the stakeholders Stakeholders

All parties that have an interest, financial or otherwise, in a firm-stockholders, creditors, bondholders, employees, customers, management, the community, and the government.
 back at Goddard. A side benefit of the demonstrations was that they helped identify specific technical skills of project teammates to the rest of the staff.

[ILLUSTRATION OMITTED]

In spite of the focused training effort, it became apparent during our design activities that we needed to sprinkle our emerging OO team with some experienced onsite OO and C++ expertise. With senior management's approval and as part of the CCS management philosophy to engage outside expertise, we contracted with an organization expert in OO development to provide a small number of on-site consultants. To avoid the traditional (often contentious) consultant-client relationship, the management team decided to assimilate as·sim·i·late
v.
1. To consume and incorporate nutrients into the body after digestion.

2. To transform food into living tissue by the process of anabolism.
 these consultants rapidly into our own evolving culture and make them an active part of the CCS team. For their part, the consultants provided mentoring services on a one-to-one basis in analysis and design, C++ language skills, and software debugging (programming) debugging - The process of attempting to determine the cause of the symptoms of malfunctions in a program or other system. These symptoms may be detected during testing or use by real users. . We also made them an integral part of the development team by assigning them key pieces of application software to design and code. (One of the consultants was tasked to lead the Middleware Software that functions as a conversion or translation layer. It is also a consolidator and integrator. Custom-programmed middleware solutions have been developed for decades to enable one application to communicate with another that either runs on a different platform or comes from a  team until a permanent replacement could be found.) The consultants were instrumental to the successful, on-time delivery of the Release 1 system and provided a significant return on investment for their services.

Developing a Cohesive, Cooperative Culture: the Badgeless Team

By being physically separate from the Goddard mainstream, the product development team (PDT PDT
abbr.
Pacific Daylight Time


PDT Pacific Daylight Time

PDT n abbr (US) (= Pacific Daylight Time) → hora de verano del Pacífico

PDT 
) was able to develop its own unique management culture and style to fit the environment and its goals. One of the first management goals was to replace the typical atmosphere of competition and animosity between contractors and the customer with a more universally cooperative environment. This transformation was effected by restructuring the team dynamics
Did you mean group dynamics?
Team Dynamics (currently racing under the guise of Team Halfords in deference to their title sponsor) is a UK-based motor-racing team based in Pershore (Worcestershire), best known for their successes as an independent
 to implement and expand upon the concept of a "badgeless team."

The badgeless team concept meant breaking down traditional barriers and roles--often contractual--between civil servants (HST being a government-run project) and contractor personnel, as well as among a variety of support contractors, since there were eventually over a dozen different companies represented on this PDT. A bigger challenge, however, turned out to be convincing the various contractor and government supervisors that such an approach would work. In practice, there were civil servants reporting to contractor personnel; contractors reporting to contractors of the same company; and contractors reporting to contractors of different companies. This represented a radical departure from what senior NASA NASA: see National Aeronautics and Space Administration.
NASA
 in full National Aeronautics and Space Administration

Independent U.S.
 management viewed as the way civil servants and contractors were supposed to relate to each other. It should be noted that this was an evolutionary process, since not everyone on the CCS PDT was comfortable with this new management philosophy, and some chose to leave the project.

In retrospect, this management strategy became one of the main reasons the team was so successful. The emphasis on technical achievements and shared vision, along with a tight focus on the CCS goals (rather than on which particular company should get the credit for the work accomplished), created a unique situation. The ultimate goal was to erase from people's mindset mind·set or mind-set
n.
1. A fixed mental attitude or disposition that predetermines a person's responses to and interpretations of situations.

2. An inclination or a habit.
 the process of going through "channels." Everything you needed to get your job done was resident at the collocation collocation - co-location  facility (lovingly referred to by the staff simply as "Colo"). Again, the relative physical isolation enabled the staff to significantly reduce, but not entirely eliminate, traditional corporate politics and jurisdictional disputes Conflicting claims made by two different labor unions to an employer regarding assignment of the work or union representation.

Two basic types of controversies ordinarily arise in such disputes.
 that had previously hindered close, technical exchanges and cooperation between different companies working on the same project.

[ILLUSTRATION OMITTED]

To achieve this cohesive, cooperative culture, the management team recognized early on that the internal naysayers needed either to be converted or to be strongly encouraged to leave the project. Teamwork and the free exchange of ideas were to be the hallmarks of this project. Over time, these radical ideas bore fruit as team members freely circulated around the building and became comfortable creating ad hoc For this purpose. Meaning "to this" in Latin, it refers to dealing with special situations as they occur rather than functions that are repeated on a regular basis. See ad hoc query and ad hoc mode.  teams in the hallways. There was a high measure of trust between management and team personnel as well as between and among the individual teams. The overall collegial col·le·gi·al  
adj.
1.
a. Characterized by or having power and authority vested equally among colleagues: "He . . .
, community atmosphere allowed all members of the CCS project to excel and exceed expectations from both a technical and personal perspective.

Management Principles: Implementation Strategies

The following management principles (listed in no significant order) served to sustain the high productivity environment. Some of these principles are obvious, some are espoused in current management science texts, and some will work only in a collocated environment.

Use integrated product teams to provide short-term results

A meta-goal of every project is to make good design decisions and to develop the corresponding products as quickly as possible. The CCS PDT management selected from the entire organization those persons who could best produce a particular product; assembled them into a small team; gave them the authority to make the necessary decisions; and when the product was completed, returned them to their core technical teams.

Use the 80/20 rule

As is the case with most projects, the CCS PDT existed in a very dynamic environment where technology was rapidly evolving, and user requirements were negotiable NEGOTIABLE. That which is capable of being transferred by assignment; a thing, the title to which may be transferred by a sale and indorsement or delivery.
     2.
. Recognizing this, a decision was made to expedite ex·pe·dite  
tr.v. ex·pe·dit·ed, ex·pe·dit·ing, ex·pe·dites
1. To speed up the progress of; accelerate.

2.
 the decision-making process and to avoid "paralysis paralysis or palsy (pôl`zē), complete loss or impairment of the ability to use voluntary muscles, usually as the result of a disorder of the nervous system.  by analysis" by employing the 80/20 rule. For example, if a COTS product could be found that satisfied at least 80 percent of the target user requirements, then feedback from the users would be solicited to determine if this was adequate. The process was driven by the understanding that not all user requirements are equal, and thus, implementation of the least important 20 percent can often be deferred, sometimes indefinitely. This process also served to keep the user community involved in critical design decisions so they remained part of the solution.

Establish proof of concept and/or prototyping teams

Early on, the core technical teams were tasked with performing risk-mitigation activities while the final architecture of the control center was being hammered ham·mered  
adj.
1. Shaped or worked with a metalworker's hammer and often showing the marks of these tools: a bowl of hammered brass.

2. Slang Drunk or intoxicated.

Adj.
 out. (Remember that the team was originally front-loaded with a legacy software staff.) The proof-of-concept (POC (Proof Of Concept) See PoC exploit.

POC - Point Of Contact
) team was instrumental in identifying and demonstrating promising new technologies, such as Java applets A Java program that is downloaded from the server and run from the browser. The Java Virtual Machine built into the browser is interpreting the instructions. Contrast with Java application. , collaborative tools, and COTS packages. The results were fed back to the top-down architecture team to help justify and substantiate To establish the existence or truth of a particular fact through the use of competent evidence; to verify.

For example, an Eyewitness might be called by a party to a lawsuit to substantiate that party's testimony.
 the proposed control center architecture. This served as an excellent risk-mitigation activity by introducing the staff to a significant number of new (and sometimes unproven unproven Dubious, nonscientific, not proven, quack, questionable, unscientific adjective Relating to that which has not been validated by reproducible experiments or other scientific methods for determining effect or efficacy ) technologies. One of the PDT's primary objectives was to leverage COTS hardware and software solutions as much as feasible; and thus, many of the teams worked to prototype these packages in an environment as close as possible to that envisioned for the actual control center. Out of these prototyping activities emerged a suite of commercial off-the-sheft (COTS) and government off-the-shelf Government off-the-shelf (GOTS) is a term for software and hardware products that are typically developed by the technical staff of the government agency for which it is created.  (GOTS) solutions that was later integrated into the control center design, with the added benefit of reducing both risk and implementation time.

Implement a "rewards and awards" program

After each successful delivery of a control center system release, the project lead acknowledged each individual who contributed to that release with a KUDOS[R] Brand candy bar. These informal rewards were so well received that team members came to expect a visit right after each software delivery. It was one strategy that cost so little but paid out with immeasurable returns. The upper management team at Goddard was also very supportive of both individual and team efforts. Instead of just funding the prime contractor's award fee, management funded an incentive program that rewarded the Hubble control center team members with bonus checks upon a successful software delivery

Integrate and elevate el·e·vate  
tr.v. ele·vat·ed, ele·vat·ing, ele·vates
1. To move (something) to a higher place or position from a lower one; lift.

2. To increase the amplitude, intensity, or volume of.

3.
 traditionally background activities into the main software development cycle

The PDT recognized the importance and value of traditional support functions to the successful development and deployment of the control center system. Four examples illustrate this:

* The infrastructure team provided the systems administration, networking, and hardware expertise necessary to define the overall system topology topology, branch of mathematics, formerly known as analysis situs, that studies patterns of geometric figures involving position and relative position without regard to size.  and operations concept.

* The quality assurance team was responsible for ensuring that processes were followed and that design and coding standards were adhered to during all phases of development.

* The methodology team was responsible for tailoring and maintaining the CASE tool used to capture all the design information for the developers.

* The configuration and change management team developed the electronic tools necessary to support our software baseline control process (configuration management) and the rapid capture and dissemination dissemination Medtalk The spread of a pernicious process–eg, CA, acute infection Oncology Metastasis, see there  of problem reports (change management).

Hire college students for the summer

An often-overlooked area that paid big dividends for this PDT, three summer-hire college interns This article or section is written like an .
Please help [ rewrite this article] from a neutral point of view.
Mark blatant advertising for , using .
 contributed significantly to the development process. Specifically, these summer interns contributed to the conversion of the command subsystem from VMS (1) (Virtual Memory System) A multiuser, multitasking, virtual memory operating system for the VAX series from Digital. VMS applications run on any VAX from the MicroVAX to the largest unit. See OpenVMS.  to Unix, developed and tested Java applets for the GUI (Graphical User Interface) A graphics-based user interface that incorporates movable windows, icons and a mouse. The ability to resize application windows and change style and size of fonts are the significant advantages of a GUI vs. a character-based interface.  subsystem, and developed performance benchmarks for a newly procured tape-based archive system. The interns were treated as full members of the overall team, were challenged technically, and helped the PDT to maintain an optimal skill mix.

Establish a mechanism for detecting and resolving conflict as quickly as possible

Conflict is inevitable no matter the size of the team or its objectives. Establishing mechanisms to deal with the various forms of conflict is critical to the success of any team. In this case, specific technical issues that cut across core team boundaries were referred to the Control Center System Architecture Board (CAB), chaired by the lead systems engineer. All issues related to the architecture, design, implementation, and correction of the control center software were also referred to the CAB for resolution. Intra-team conflicts were expected to be resolved within the specific core team boundaries. At any time, a member of a core team could refer unresolved non-technical conflicts directly to the PMT See photomultiplier tube. . In such cases, the staff member's company supervisor could be included in the process to ensure a timely and equitable resolution.

[ILLUSTRATION OMITTED]

Final Remarks

Because of the relative isolation from its predecessor culture, the Hubble Control Center System PDT management team was granted a great degree of latitude (Geog.) on the earth, the distance on a meridian between two parallels of latitude whose latitudes differ from each other by one degree. This distance is not the same on different parts of a meridian, on account of the flattened figure of the earth, being 68.  in applying unconventional management techniques. The goals of the management team were no different from those of most systems development projects:

* To establish an organizational structure This article has no lead section.

To comply with Wikipedia's lead section guidelines, one should be written.
 that provides the right level of control without impeding im·pede  
tr.v. im·ped·ed, im·ped·ing, im·pedes
To retard or obstruct the progress of. See Synonyms at hinder1.



[Latin imped
 progress

* To establish and maintain a high level of morale that fosters a team identity

* To allocate project resources in a balanced manner

* To intelligently manage technical and non-technical (e.g., schedule, cost) risk

* To leverage the existing skill set of the staff while continuing to build up weaker areas

* To acquire accurate and timely status of the overall project as well as each sub-element

* To meet or exceed expected productivity estimates

* To develop and deliver a high quality product to the customer

* To empower the staff to make timely and accurate design decisions to minimize rework re·work  
tr.v. re·worked, re·work·ing, re·works
1. To work over again; revise.

2. To subject to a repeated or new process.

n.


* To institute a method of achieving internal process improvement

* To enable synergy and a spirit of cooperation within the project

* To detect and resolve internal conflict quickly.

Figure 1 (page 39) summarizes this information. Each column represents one of the management goals itemized in the previous list. The rows identify key management actions presented throughout the main body of this paper. Marks in the table indicate those management actions that directly or indirectly contributed to the satisfaction of the corresponding goal. It should be noted that these marks represent the assessments of the authors and were not measured using any formal metrics metrics Managed care A popular term for standards by which the quality of a product, service, or outcome of a particular form of Pt management is evaluated. See TQM. .

In summary, despite the progress made over the last 25 years in advancing the state of system and software engineering practices--including improved methodologies, new languages, visual tools, online debuggers, lightning-fast PCs, and CASE tools--project success still comes down to people. Management still needs to find the best people available or be willing to invest the time and training dollars in the current staff. Once an exceptional staff is in place, it's necessary to keep the team focused on the technical milestones (eliminating the politics if possible) and to provide means of recognition from something as simple as a candy bar to a full-scale incentive bonus.

The Hubble control center PDT management team undertook all of these actions and was rewarded with a highly skilled, productive, cohesive, and communicative com·mu·ni·ca·tive  
adj.
1. Inclined to communicate readily; talkative.

2. Of or relating to communication.



com·mu
 staff with an attrition rate Noun 1. attrition rate - the rate of shrinkage in size or number
rate of attrition

rate - a magnitude or frequency relative to a time unit; "they traveled at a rate of 55 miles per hour"; "the rate of change was faster than expected"


 that was significantly less than industry norms of the time. However, like all good things acquired, there is an upkeep cost: people need technical challenges, opportunities for additional training and professional growth, and a little TLC TLC total lung capacity; thin-layer chromatography.

TLC
abbr.
1. thin-layer chromatography

2.
 and recognition every now and then. But the results are well worth it--and besides, you can't be successful without them!
FIGURE 1. Management Actions Contributing to Goal Satisfaction

                        Organizational  Team      Balance    Manager
                        Structure       Identity  Resources  Risk

Flatten Organizational  *
  Structure
Empower Staff                           *
Create Dynamic Matrix   *                         *
Allow Failure without
  Retribution
Perform Post-Mortems                                         *
Collocate Staff         *               *         *
Encourage Internal                      *                    *
  Communication
Sponsor Social Events                   *
  (Barbecues)
Management By Walking                             *          *
  Around
Up-to-date Design                                            *
  Information on Web
Mandatory CASE Tool                                          *
  Usage
Multi-faceted Staff                     *                    *
  Training (Formal,
  OJT)
External Technical
  Interaction
  (Conferences)
Internal Technical                      *                    *
  Demos
Establish Badgeless     *               *
  Team
Remove Naysayers                        *
Use Integrated                                    *          *
  Product Teams
80-20 Rule
Actively Perform                                             *
  Prototyping
Provide Rewards and                     *                    *
  Awards

                        Leverage      Accurate  High
                        Staff Skills  Status    Productivity

Flatten Organizational                *         *
  Structure
Empower Staff           *                       *
Create Dynamic Matrix
Allow Failure without   *
  Retribution
Perform Post-Mortems                            *
Collocate Staff                       *         *
Encourage Internal      *             *         *
  Communication
Sponsor Social Events                           *
  (Barbecues)
Management By Walking   *             *
  Around
Up-to-date Design                     *         *
  Information on Web
Mandatory CASE Tool                             *
  Usage
Multi-faceted Staff     *
  Training (Formal,
  OJT)
External Technical      *
  Interaction
  (Conferences)
Internal Technical      *
  Demos
Establish Badgeless     *
  Team
Remove Naysayers                                *
Use Integrated          *                       *
  Product Teams
80-20 Rule
Actively Perform        *
  Prototyping
Provide Rewards and                             *
  Awards

                        High Quality  Minimize  Process      Staff
                        Product       Rework    Improvement  Synergy

Flatten Organizational  *                                    *
  Structure
Empower Staff           *                                    *
Create Dynamic Matrix                 *
Allow Failure without                           *
  Retribution
Perform Post-Mortems                  *         *
Collocate Staff         *             *
Encourage Internal      *             *                      *
  Communication
Sponsor Social Events   *
  (Barbecues)
Management By Walking                           *
  Around
Up-to-date Design                     *                      *
  Information on Web
Mandatory CASE Tool     *             *
  Usage
Multi-faceted Staff     *                       *
  Training (Formal,
  OJT)
External Technical                              *
  Interaction
  (Conferences)
Internal Technical      *                       *            *
  Demos
Establish Badgeless                                          *
  Team
Remove Naysayers        *                                    *
Use Integrated          *             *
  Product Teams
80-20 Rule                            *
Actively Perform        *
  Prototyping
Provide Rewards and     *                       *
  Awards

                        Conflict Resolution

Flatten Organizational  *
  Structure
Empower Staff
Create Dynamic Matrix
Allow Failure without   *
  Retribution
Perform Post-Mortems
Collocate Staff
Encourage Internal
  Communication
Sponsor Social Events   *
  (Barbecues)
Management By Walking   *
  Around
Up-to-date Design
  Information on Web
Mandatory CASE Tool
  Usage
Multi-faceted Staff
  Training (Formal,
  OJT)
External Technical
  Interaction
  (Conferences)
Internal Technical
  Demos
Establish Badgeless
  Team
Remove Naysayers        *
Use Integrated
  Product Teams
80-20 Rule
Actively Perform
  Prototyping
Provide Rewards and     *
  Awards


Editor's note Editor's Note (foaled in 1993 in Kentucky) is an American thoroughbred Stallion racehorse. He was sired by 1992 U.S. Champion 2 YO Colt Forty Niner, who in turn was a son of Champion sire Mr. Prospector and out of the mare, Beware Of The Cat.

Trained by D.
: The authors welcome comments and questions. Barrett can be reached at lbarrett@hst.nasa.gov and Lehtonen kenneth.e.lehtonen@nasa.gov

Barrett is the chief systems engineer for the HST control center system. He is primarily responsible for system architecture oversight and technical risk management. Lehtonen has over 35 years of experience in software engineering. His experience includes designing, implementing, testing, and managing a wide variety of mission software applications for NASA.
COPYRIGHT 2004 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2004, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:Best Practices; Acquisition Technology and Logistics
Author:Lehtonen, Ken
Publication:Defense AT & L
Geographic Code:1USA
Date:May 1, 2004
Words:3085
Previous Article:Marine Corps Commandant releases 2004 version of Concepts & Programs.(Brief Article)
Next Article:Simulation & Modeling for Acquisition, Requirements, and Training--SMART.(United States Army)(Brief Article)
Topics:



Related Articles
F-35 Joint Strike Fighter and unique identification (UID).(Best Practices)
Parts repair ordering system.(Education And Training)
The directorate of Defense Systems: expanded mission and focus.(Organization)
Renewed focus on systems engineering at the Defense Acquisition University.(AT & L Knowledge Sharing Update)(Acquisition Technology and Logistics )
BCS3 provides actionable logistics information to the warfighter: a story of acquisition innovation.(TECHNOLOGY EXCELLENCE)
Michael W. Wynne: Acting Under Secretary of Defense (Acquisition, Technology and Logistics) presents Packard Awards.(Brief Article)
Over 10,000 served: DAU performance-based logistics resources.(WORKFORCE TRAINING AND DEVELOPMENT)
Program Execution: it all comes down to making the hard decisions.(Kenneth Krieg)
Tenth annual Admiral Stanley R. Arthur Awards for Logistics Excellence.(Acquisition & Logistics Excellence)
Program startup workshop: the CH-53K Heavy Lift Helicopter Program.(PROGRAM MANAGEMENT)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles