Printer Friendly
The Free Library
14,679,069 articles and books
Member login
User name  
Password 
 
Join us Forgot password?

Letter to the editor.


In your January-April 2004 edition of the Defense Acquisition Review Journal article entitled, "Surveying Cost Growth," the authors indicate that one way to reduce unexpected cost growth is to develop better estimates. They go on to quantify some of the reasons for this growth. According to according to
prep.
1. As stated or indicated by; on the authority of: according to historians.

2. In keeping with: according to instructions.

3.
 a 1993 RAND study of Acquisition Category I (ACAT ACAT

See: Automated Customer Account Transfer
 I) programs, by the time these programs complete the production and fielding phases, they will experience approximately a 20 percent cost growth from the initial estimate.

I would like to point out that many studies have been done in the past few years that reflect similar results, and in comparison to other complex public and private sector industries, the Department of Defense (DoD) overruns are relatively small. In a Technical Report (TR 1-00) written for the Defense Acquisition University (DAU DAU - /dow/ [German Fidonet] D"ummster Anzunehmender User. A German acronym for stupidest imaginable user. From the engineering-slang GAU for Gr"osster Anzunehmender Unfall (worst foreseeable accident), especially of a LNG tank farm plant or something with similarly disastrous ) in October 2000, entitled, "Acquisition Trend Metrics in the Department of Defense," it was shown that for engineering and manufacturing development (EMD EMD Electromechanical dissociation, see there ) programs in the DoD between 1980-1996, the average cost overrun Noun 1. cost overrun - excess of cost over budget; "the cost overrun necessitated an additional allocation of funds in the budget"
cost - the total spent for goods or services including money and time and labor
 was 40 percent. But, if the nine programs that had over 100 percent overruns were removed (considered outliers), then the average overrun was reduced to 19 percent. That would appear to indicate that either a program's cost overrun as a percentage remains fairly consistent from EMD through Production/Fielding (RAND study) or that the bulk of the program's overruns occur early-on during development and gets no worse during production.

That is not to say that there is not room for improvement because we are continuously trying to improve our cost-estimating methodologies and databases. Unfortunately, the development of new and useful Cost Estimating Relationships (CERs), the positive use of good risk analysis, and other techniques are often lacking for different reasons. Sometimes it is totally dependent on the experience of the analyst(s) who are trying to develop the estimate.

Cost estimates, by their own nature, are not precise, discrete decision-making tools. Particularly in the early stage of a program pre-System Development and Demonstration (pre-SDD or SDD (Software Design Description) The architecture of an information system. See IDD. ) phase, there is usually very little information of a technical or cost nature to use with any confidence level. Thus, there is risk inherent in the process. Cost Analysts can and often do quantify risks in their programs. Army ACAT I level programs are traditionally funded to the 50 percent confidence interval confidence interval,
n a statistical device used to determine the range within which an acceptable datum would fall. Confidence intervals are usually expressed in percentages, typically 95% or 99%.
. But even this is no guarantee that a program is adequately funded. This is equal to the flip of a coin. A program therefore starts on a playing field that is expected to have a 50/50 chance of not having a cost overrun. And as most acquisition managers can attest, the likelihood of the program having some significant changes to it during the initial years of SDD is great.

The design of the system is immature, and the details of how reliable the hardware will eventually become has not been determined. What specific kinds of testing the Program Manager (PM) and other organizations will conduct to determine the system availability, maintainability, and ability to meet technical requirements are all areas of uncertainty. At the same time, the Program Office Estimates (POEs) are being finalized for management review and approvals. Unfortunately, this becomes the baseline funding for the program and gets hardened in cement shortly afterward. A PM's ability to influence and significantly change a funding profile for anything other than 4-5 years away is quickly reduced to time zero.

I would also point out that in TR 1-00 the authors indicate, "cost growth is usually a consequence of some other occurrence and not a lead event" (Swank, Alfieri, Gailey, & Reig, 2000, p. 2). In other words Adv. 1. in other words - otherwise stated; "in other words, we are broke"
put differently
, cost status is not the predictor of a program's problems but rather the result of the program's problems. Those problems are usually either schedule- or performance-related activities. A design problem that cannot be solved or a prototype of a new circuit card assembly that keeps cracking during a stress test can be the cause of a serious technical problem. On a similar note, schedule status is the best early indicator of a program in trouble, "... a slip in early test milestones is the best indicator of a program heading into trouble" (Swank, Alfieri, Gailey, & Reig, 2000, p. 4).

What we can say about trend analysis from an Earned Value Management Earned Value Management (commonly abbreviated and referred to just as EVM) is a project management technique that seeks to measure forward progress in an objective manner. EVM is touted as having a unique ability to combine measurements of technical performance (i.e.  perspective is that when a contract is more than 15 percent complete, it is a widely accepted principle that the percent overrun at contract completion will be greater than the percent overrun incurred to date.

In addition, the software complexity of today's systems cannot be overstated o·ver·state  
tr.v. o·ver·stat·ed, o·ver·stat·ing, o·ver·states
To state in exaggerated terms. See Synonyms at exaggerate.



o
. Many of the studies were taken from Selected Acquisition Reports (SARs). It should be noted that SARs do not ask for or contain information specific to a program's software development. As a result, a major cost driver to technology in modern systems cannot be clearly delineated de·lin·e·ate  
tr.v. de·lin·e·at·ed, de·lin·e·at·ing, de·lin·e·ates
1. To draw or trace the outline of; sketch out.

2. To represent pictorially; depict.

3.
 or identified to any degree. Today's weapons systems are becoming more software intensive and complexities, due to software estimating at an early stage of development, are difficult and often underestimated.

As for the underestimating of costs on programs, we should also consider that the analyst is often given constraints while developing estimates. For example, by the time a formal estimate is required for a Milestone B decision, certain near-term funding had already been approved a few years earlier. These budget wedges are usually created from engineering best guesses and ROMs created to serve as a beginning to the financial programming process, much earlier than the technical requirements, program schedule, and systems definition are clearly defined. As a result, the analyst is often forced to estimate to budget in the near term, even as requirements dictate that more dollars are needed to be programmed for the work expected. Thus, even if risk dollars are needed, the funding may not support it, and the program may not be properly funded for unknowns likely to occur. This then appears as a cost estimate that is not aligned with optimistically op·ti·mist  
n.
1. One who usually expects a favorable outcome.

2. A believer in philosophical optimism.



op
 projected programmatics. The result of all of these constraints and what-if drills may be the cause of the estimate being low in certain fiscal years and high in out-years, when funding changes can be impacted.

While more realistic (i.e., accurate) cost estimates are certainly a commendable goal, the issue of affordability and funding programmatics tend to negate ne·gate  
tr.v. ne·gat·ed, ne·gat·ing, ne·gates
1. To make ineffective or invalid; nullify.

2. To rule out; deny. See Synonyms at deny.

3.
 each other in the final analysis.

REFERENCES

Drezner, J. A., Jarvaise, J. M., Hess, R. W., Hough n. 1. Same as Hock, a joint.
v. t. 1. Same as Hock, to hamstring.
[

imp. & p. p. os> Houghed

r>;

p. pr. & vb. n. os> Houghing.]

n. 1. An adz; a hoe.
v. t. 1. To cut with a hoe.
, P. G., & Norton, D. (1993). An analysis of weapon system cost growth. RAND Study MR-291-AF. Santa Monica Santa Monica (săn`tə mŏn`ĭkə), city (1990 pop. 86,905), Los Angeles co., S Calif., on Santa Monica Bay; inc. 1886. Tourism and retailing are important, and the city has motion-picture, biotechnology, and software industries. , CA: RAND Corporation Rand Corporation, research institution in Santa Monica, Calif.; founded 1948 and supported by federal, state, and local governments, as well as by foundations and corporations. Its principal fields of research are national security and public welfare. .

Greiner, M., Sipple, V., & White, E. (2004, January-April). Surveying cost growth. Defense Acquisition Review Journal, 11(1), pp. 79-90.

Swank, W. J., Alfieri, P. A., Gailey, C. K., & Reig, R. W. (2000, October). Acquisition trend metrics in the Department of Defense (TR 1-00). Fort Belvoir Fort Belvoir is a United States military installation and a census-designated place (CDP) in Fairfax County, Virginia, United States. The population was 7,176 at the 2000 census. , VA: Defense Acquisition University/Defense Systems Management College.
COPYRIGHT 2005 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Author:Jones, Thomas D.
Publication:Defense A R Journal
Article Type:Letter to the Editor
Date:Feb 1, 2005
Words:1138
Previous Article:Total Ownership Cost considerations in key performance parameters and beyond.(LESSONS LEARNED)
Next Article:Defense ARJ executive editor.(a note from the executive editor)(Editorial)



Related Articles
State courts uphold 'opinion' decisions in post-Milkovich era. (letters to the editor writers legally liable under Milkovich v. Lorain Journal)(News...
E-mail: Is it a blessing or curse?
Keep the spotlight on readers.(Brief Article)
A case for printing 'name withheld' letters.
Rethinking the rules. (Editor's Note).
Creating a lively letters page: how do you sustain a lively exchange with your readers? The Masthead editor collected advice from a number of...
Why women don't write: time, fear, and society get the blame for lack of letters from women writers. Still, the Courant took steps to make editorial...
A look at the perpetrators: the list of interest groups encouraging "astroturf" is as long as the list of interest groups.(Turf wars: the editor...
New research on the nature of letters and their writers.(Letter-writing demography)
Turf or astroturf? A look at the scope of the "canned letter" phenomenon.(letters to the editor campaigns)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles