It's theoretical: a ruling holds that the period of restoration is the time that it should take to rebuild.


After the World Trade Center's Twin Towers collapsed on Sept. 11, 2001, fires that smoldered in the ruins eventually were put out. But litigation An action brought in court to enforce a particular right. The act or process of bringing a lawsuit in and of itself; a judicial contest; any dispute.

When a person begins a civil lawsuit, the person enters into a process called litigation.
 has raged on between Silverstein Properties, the landlord, and its property insurers concerning the extent of coverage and valuation of the loss. Juries have rendered verdicts first against and then in favor of the policyholder Policyholder

An individual who owns an insurance policy.
 regarding the entities liable to Silverstein Properties and the limit of the remaining insurers' liability, respectively. In the third phase, an appraisal panel is proceeding with the valuation of the property damage and business income loss as a result of the destruction.

One question before that panel is a determination of the dollar amount of the rental losses incurred by Silverstein. That figure is dependent upon the period of restoration that is used to calculate the rental loss. Silverstein contends that proper measure is the actual time it takes to rebuild the Twin Towers. The property insurers contend that under the terms of the insurance policies, a theoretical measure for rebuilding time must be used. The insurers moved for partial summary judgment on this issue.

In February 2005, U. S. District Court Judge Michael Mukasey This article or section uses citations that are either broken or outdated.  made clear that the job of the appraisal panel is to determine the valuation of the loss and not issues of coverage, which must be determined by the court. Determining what's meant by "period of restoration" in an insurance policy is a coverage issue, he said.

The wording in the policies issued to Silverstein is typical of that in many business-income coverage forms. tinder the terms of the policy, the insurer is obligated ob·li·gate  
tr.v. ob·li·gat·ed, ob·li·gat·ing, ob·li·gates
1. To bind, compel, or constrain by a social, legal, or moral tie. See Synonyms at force.

2. To cause to be grateful or indebted; oblige.
 to pay for "the actual loss of ... Rental Value rental value n. the amount which would be paid for rental of similar property in the same condition in the same area. Evidence of rental value becomes important in lawsuits in which loss of use of real property or equipment is an issue, and the rental value is the  sustained by the Insured due the necessary 'suspension' of the Insured's "operations' during the 'period of restoration.' "The policy defines "period of restoration" as beginning on "the date and time of the direct physical loss or damage" and, absent resumption RESUMPTION. To reassume; to promise again; as, the resumption of payment of specie by the banks is general. It also signifies to take things back; as the government has resumed the possession of all the lands which have not been paid for according to the requisitions of the law, and the  of operations at a new permanent location, ending on "[t]he date when the property should be repaired, rebuilt or replaced with reasonable speed and similar quality." Since Silverstein did not intend to resume business in a new, permanent location, the court was left to determine the meaning of the phrase "when property should be repaired, rebuilt or replaced with reasonable speed and similar quality."

Silverstein argued that the "should" in the restoration period definition imposes a theoretical measure only where the insured does not rebuild or fails to do so with reasonable speed and similar quality. Next, it contended its position is grounded in law, supported by an unpublished 9th Circuit opinion and two older state court cases. Finally, it argued all of the cases that have applied a theoretical measure are easily distinguishable from the facts that relate to the Twin Towers.

Mukasey rejected these arguments, indicating that Silverstein's reliance on intrinsic and extrinsic evidence Facts or information not embodied in a written agreement such as a will, trust, or contract.

Extrinsic evidence is similar to extraneous evidence, which is not furnished by the document in and of itself but is derived from external sources.
 is improper if the insurance policy provision involved is unambiguous. Several courts have agreed.

Next, the judge found the argument by Silverstein that the word "should" in the "period of restoration" definition does double duty because it could apply to either an actual or hypothetical Hypothetical is an adjective, meaning of or pertaining to a hypothesis. See:
  • Hypothesis
  • Hypothetical
  • Hypothetical (album)
 restoration period to be an arbitrary statement. The argument, according to according to
prep.
1. As stated or indicated by; on the authority of: according to historians.

2. In keeping with: according to instructions.

3.
 Mukasey, flies in the face of existing legal precedent, other text in the policy, the context, and logic. Finally, he rejected the legal authorities cited by Silverstein in support of the use of an actual period of restoration.

Instead, Mukasey found that reasoning in cases that applied a theoretical period to be far more compelling, particularly the decision in the Southern District of New York New York, state, United States
New York, Middle Atlantic state of the United States. It is bordered by Vermont, Massachusetts, Connecticut, and the Atlantic Ocean (E), New Jersey and Pennsylvania (S), Lakes Erie and Ontario and the Canadian province of
 in a case involving business income loss to a World Trade Center tenant as a result of the events of Sept. 11.

Mukasey concluded by holding:" [e]specially in a case such as this, where rebuilding is likely to take many years, it would be impractical im·prac·ti·cal  
adj.
1. Unwise to implement or maintain in practice: Refloating the sunken ship proved impractical because of the great expense.

2.
, as well as inconsistent with the long-standing interpretations of the restoration period clauses at issue here, to conclude that the court and the parties should all be required to await the passage of those years until the new WTC WTC World Trade Center, see there  properties are in place to determine for just how long the Silverstein Parties will be allowed to recover their rental value losses." Thus, he granted partial summary judgment to the insurers and instructed the appraisal panel to use a theoretical period.

This decision has now answered the question frequently posed in business income claims: How is the period of restoration determined? The answer: It's theoretical--the amount of time that it should take to rebuild assuming reasonable speed and similar quality, and not the actual time.

Frederic R. Mindlin is a partner at the New York-based law firm of Mound Cotton Wollan & Greengrass. He can be reached at insight@bestreview.com.
COPYRIGHT 2005 A.M. Best Company, Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:Silverstein Properties Inc.
Comment:It's theoretical: a ruling holds that the period of restoration is the time that it should take to rebuild.(Silverstein Properties Inc.)
Author:Mindlin, Frederic R.
Publication:Best's Review
Geographic Code:1USA
Date:Jul 1, 2005
Words:789
Previous Article:Is it or isn't it? Recent court cases are exploring the definition of advertising on the uncharted terrain of the Internet.(Regulatory/Law)
Next Article:Housing stock: some life insurers are investing in funds that finance or develop affordable urban housing.
Topics:



Related Articles
Court upholds Silverstein zoning. (State Court of Appeals rejects objections by residents, upholds rezoning agreement for land owned by Silverstein...
Judge: 9-11 attack 1 incident, not 2.(Silverstein Properties Inc. insurance claim for World Trade Center buildings)
Groundbreaking of 7 WTC marks start of $700m rebuilding project.(Brief Article)
Silverstein opens show with vow to rebuild.(Larry Silverstein)
Court weighs WTC insurance claim.
Silverstein intends to share roles in historic downtown rebuilding.(Silverstein Properties, Building and Construction Trades Council, the Building...
Freedom Tower war of words rages on.(Real estate developers)
Libeskind sues Silverstein over $800,000 'genius fee'.(Brief Article)
Silverstein, Libeskind settle fee.(Larry A. Silverstein, Daniel Libeskind )
WTC stand-off as talks over rebuilding drag on.(World Trade Center)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles