Department of Defense news release (Aug. 15, 2005): DoD releases selected acquisition reports.


The Department of Defense has released details on major defense acquisition program cost and schedule changes since the December 2004 reporting period. This information is based on the Selected Acquisition Reports (SARs SAR - Search And Rescue
SAR - Sons of the American Revolution
SAR - Specific Absorption Rate (measure of the rate of absorption of RF energy in the body)
SAR - Safety Analysis Report
SAR - Safety Appraisal Report
SAR - Safety Assessment Report
SAR - Sample Assessment Report
SAR - San Antonio Rampage (hockey team)
SAR - Sarcosinemia
Sar - Sarikoli (linguistics)
SAR - Satellite Access Request
SAR - Saudi Arabian Riyal
) submitted to the Congress for the June 30, 2005, reporting period.

SARs summarize the latest estimates of cost, schedule, and technical status. These reports are prepared annually in conjunction with the president's budget. Subsequent quarterly exception reports are required for only those programs experiencing unit cost increases of at least 15 percent or schedule delays of at least six months. Quarterly SARs are also submitted for initial reports, final reports, and for programs that are rebaselined at major milestone decisions.

The total program cost estimates provided in the SARs encompass research and development, procurement, military construction, and acquisition-related operation and maintenance (except for pre-Milestone B programs, which are limited to development costs pursuant to 10 U.S.C. 2432). Total program costs reflect actual costs to date as well as future anticipated costs. All estimates include anticipated inflation allowances.

The current estimate of program acquisition costs [shown in the sidebar] for programs covered by SARs for the prior reporting period (December 2004) was $1,472,184.3 million. After subtracting the costs for six final reports (Joint Common Missile (JCM JCM - Japan Cash Machine, Inc.
JCM - Japan Collection of Microorganisms
JCM - Jesus Christ Ministries
JCM - Job Characteristics Model
JCM - Joint Common Missile
JCM - Joint Conflict Model
JCM - Joint Cruise Missile
JCM - Journal of Chinese Medicine
JCM - Journal of Clinical Microbiology
), Longbow Hellfire, Maneuver Control System (MCS), Navy Extremely High Frequency Satellite Communications System (NESP NESP - National Economic Security Program
NESP - National Education Supercomputer Program
NESP - National Environmental Studies Project
NESP - Navy EHF SATCOM Program
NESP - Navy EHF Satellite Program
NESP - Neuroendocrine Secretory Protein
NESP - New Equipment Support Package
NESP - Northeastern Society of Periodontists
), Standard Missile-2 (SM-2), and B-1 B Conventional Mission Upgrade Program (CMUP CMUP - Conventional Munitions Upgrade Program)), and adding the costs for three new programs (Mission Planning System (MPS), Mobile User Objective System (MUOS MUOS - Mobile User Objective System), and Ship Self Defense System (SSDS SSDS - Secure Software Distribution System
SSDS - Self Service Development System
SSDS - Sensor Surveillance Data System
SSDS - Sexual Self-Disclosure Scale
SSDS - Ship Self Defense System
SSDS - Silo Self Defense System
SSDS - Single-Ship Deep-Sweep
SSDS - Software System Development Specification
SSDS - Space Science Data System (NASA)
SSDS - Space Station Data System
SSDS - Sudden Sniffing Death Syndrome
SSDS - Supply System Design Specification
)) from the December 2004 reporting period, the adjusted current estimate of program acquisition costs was $1,474,122.2 million. There was a net cost decrease of $72.8 million (-0.005 percent) during the current reporting period (June 2005), which was the result primarily of revised program estimates for the Air Force's National Airspace System (NAS) program.

For the June 2005 reporting period, there were quarterly exception SARs submitted for six programs. The reasons for the submissions are provided below.

Navy

LPD 17 (Amphibious Transport Dock Ship) -- The SAR was submitted to report a schedule slip of seven months (from July 2006 to February 2007) for Lead Ship Initial Operational Capability resulting from challenges associated with completing lead ship production and testing. There were no cost changes reported since the December 2004 SAR.

MH-60S Utility Helicopter -- The SAR was submitted to report a schedule slip of six months in the Initial Operational Capability of the Airborne Mine Countermine mission capability (from September 2006 to March 2007). This delay was caused by problems with the Carriage Stream Tow and Recovery System (CSTRS CSTRS - California State Teachers Retirement System
CSTRS - Carriage Stream, Tow, and Recovery System
). Resolution of the issue requires redesign and manufacture of some CSTRS components. There were no significant cost changes reported since the December 2004 SAR.

Air Force

EELV EELV - End-Expiratory Lung Volume
EELV - Evolved Expendable Launch Vehicle
EELV - Extended Expendable Launch Vehicle
 (Evolved Expendable Launch Vehicle) -- The SAR was submitted to report a schedule slip of seven months (from May 2005 to December 2005) in approval of Full Rate Production (Milestone III) approval. The delay was due to an anomaly during the Delta IV heavy lift demonstration that delayed completion of the exit criteria required to proceed to Milestone III. There were no cost changes reported since the December 2004 SAR.

GBS (Global Broadcast Service) -- The SAR was submitted to report that the current estimate for Initial Operational Capability (IOC) 2/3 has slipped nine months (from March 2006 to December 2006), and the current estimate for the Beyond Low Rate Initial Production review has slipped five months (from November 2005 to April 2006). Both changes were caused by the need to integrate Operational Requirements Document (ORD) III changes into the Test and Evaluation Master Plan (TEMP) and other test planning documentation. Program costs decreased $12.0 million (-1.6%) from $756.0 million to $744.0 million, as the result of a revised cost estimate and a quantity reduction of 12 units from 1,049 to 1,037 units.

NAS (National Airspace System) -- The SAR was submitted to rebaseline from a Development to a Production Estimate following the June 2005 approval of Full Rate Production (Milestone III). The dates for award of the Digital Airport Surveillance Radar (DASR DASR - Defense Analysis Special Report(s)
DASR - Digital Airport Surveillance Radar
DASR - Direct Access Service Request (deregulated utilities)
DASR - Direct Air-to-Satellite Relay
DASR - Directorate of Scientific Agricultural Research (Syria)
) full rate production contract and the DoD Advanced Automation System production award exercise were both changed from March 2005 to June 2005. The changes were due to a later-than-expected Beyond Low Rate Initial Production report and the effects of a changing management structure following the departure of the previous Milestone Decision Authority. The new baseline also includes the addition of Follow-on Operational Test and Evaluation as recommended by the Air Force Operational Test and Evaluation. Program costs decreased $59.5 million (-4.0%) from $1,480.6 million to $1,421.1 million, because primarily of a refinement in the Navy's cost estimate.

SDB (Small Diameter Bomb) -- The SAR was submitted to rebaseline the program from a Development to a Production Estimate following the April 2005 approval of Low Rate Initial Production (Milestone C). There were no cost changes reported since the December 2004 SAR.

A summary table of the SARs can be found at <http://www.defenselink.mil/news/Aug2005/d20050815sars.pdf>.
CURRENT ESTIMATE ($ IN MILLIONS)

December 2004 (88 programs)                   $1,472,184.3
Less final SAR submissions for six programs:
  JCM, Longbow Hellfire, MCS, NESP,
  SM-2, and B-1B (CMUP)                           -7,136.2
Plus three new programs:
  MPS, MUOS, and SSDS                             +9,074.1
December 2004 Adjusted
  (85 programs)                               +1,474,122.2
Changes Since Last Report:
  Economic                                            $0.0
  Quantity                                            -5.8
  Schedule                                            +1.7
  Engineering                                          0.0
  Estimating                                         -55.0
  Other                                               -0.0
  Support                                            -13.7
  Net Cost Change                                   $-72.8
June 2005 (85 programs)                       $1,474,049.4
COPYRIGHT 2005 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:In the News
Publication:Defense AT & L
Geographic Code:1USA
Date:Nov 1, 2005
Words:948
Previous Article:Navy newsstand (Aug. 12, 2005): advance construction begins for CVN 21.(In the News)
Next Article:U.S. Joint Forces Command news release (Aug. 23, 2005): commands working to improve joint planning in military deployment and distribution.(In the...
Topics:



Related Articles
Department of Defense news release (Oct. 14, 2004): DoD publishes Defense Acquisition Guidebook.(Policy and Legislation)(Brief Article)
Attention acquisition workforce personnel! DoD Best Practices Clearinghouse.(Career Development)
Subject: Suspension of the Price Evaluation Adjustment for Small Disadvantaged Businesses.(Policy & Legislation)(Brief Article)
DoD policy toward military specifications & standards.(In the News)(Department of Defense)(Brief Article)
General Accounting Office (GAO) reports, studies, testimony.(POLICY & LEGISLATION)(Illustration)
Acquisition & logistics excellence: an internet listing tailored to the professional acquisition workforce; surfing the net.
USD(AT & L) to help develop support strategy for homeland defense and civil support.(Policy & Legislation)(defense acquisition, technology and...
Subject: Acquisition Action Plan.(Policy & Legislation)
Subject: Update on Transition to the Federal Procurement Data System--Next Generation (FPDS-NG).(Policy & Legislation)