Department of Defense news release (Aug. 19, 2004): SARs report.The Department of Defense has released details on major defense acquisition program cost and schedule changes since the December 2003 reporting period. This information is based on the Selected Acquisition Reports (SARs) submitted to the Congress for the June 30, 2004, reporting period. SARs summarize the latest estimates of cost, schedule, and technical status. These reports are prepared annually in conjunction with the president's budget. Subsequent quarterly exception reports are required only for those programs experiencing unit cost increases of at least 15 percent or schedule delays of at least six months. Quarterly SARs are also submitted for initial reports, final reports, and for programs that are rebaselined at major milestone decisions. The total program cost estimates provided in the SARs include research and development, procurement, military construction, and acquisition-related operations and maintenance (except for pre-Milestone B programs, which are limited to development costs pursuant to 10 U.S.C. [section]2432). Total program costs reflect actual costs to date as well as future anticipated costs. All estimates include anticipated inflation allowances. The current estimate of program acquisition costs for programs covered by SARs for the prior reporting period (December 2003) was $1,332,027.2 million. After adding the costs for new programs and subtracting the costs for final reports (shown here) from the December 2003 reporting period, the adjusted current estimate of program acquisition costs was $1,267,552.2 million. There was a net cost increase of $1,524.9 million (+0.1 percent) during the current reporting period (June 2004), which was due primarily to higher cost estimates for the CVN (Card Verification Number) See CSC. 21 and Space-Based Infrared System Please help recruit one or [ improve this article] yourself. See the talk page for details. (SBIRS SBIRS Space-Based Infrared System SBIRS Space Based Infra-Red Surveillance ) High programs. For the June 2004 reporting period, there were quarterly exception SARs submitted for 14 programs. The reasons for the submissions are provided below. Army Chem Demil (Chemical Demilitarization de·mil·i·ta·rize tr.v. de·mil·i·ta·rized, de·mil·i·ta·riz·ing, de·mil·i·ta·riz·es 1. To eliminate the military character of. 2. ) -- The SAR (Segmentation And Reassembly) The protocol that converts data to cells for transmission over an ATM network. It is the lower part of the ATM Adaption Layer (AAL), which is responsible for the entire operation. See AAL. SAR - segmentation and reassembly was submitted to report schedule slips of six months or more since the December 2003 report. Specifically, the start of operations at Pine Bluff Pine Bluff, city (1990 pop. 57,140), seat of Jefferson co., S central Ark., on the Arkansas River; inc. 1839. It is a port and trade center for an agricultural area and has industries producing metal, wood, and paper products; machinery; electrical equipment; and Chemical Agent Disposal Facility is expected to slip seven months from July 2004 to February 2005. The completion of operations at the Aberdeen Chemical Agent Disposal Facility is expected to slip 10 months from July 2005 to May 2006. The 100 percent agent destroyed milestone at Newport Chemical Agent Disposal Facility is expected to slip 16 months from January 2006 to May 2007. Finally, the start of construction at the Blue Grass Chemical Agent Destruction Pilot Plant is expected to slip eight months from January 2005 to September 2005. There were no cost changes reported since the December 2003 SAR. Navy AIM-9X Missile -- The SAR was submitted to rebaseline from a development to a production estimate following the May 2004 approval of full-rate production (Milestone III) by the assistant secretary of the Navy Assistant Secretary of the Navy (abbrev. "ASN") is the title given to certain senior officials in the U.S. Department of the Navy. They serve as chief assistants to the Secretary of the Navy (SECNAV). for research, development, and acquisition. There were no cost changes reported since the December 2003 SAR. ASDS ASDS Advanced SEAL Delivery System ASDS American Society of Dermatologic Surgery ASDS Accunet Spectrum of Digital Services (AT&T) ASDS Advanced Sensor Distribution System ASDS Air Situation Display System ASDS Airborne Serial Data System (Advanced SEAL Delivery System Advanced SEAL Delivery System (ASDS) is a midget submarine operated by the United States Navy and SOCOM, designed to provide stealthy submerged transportation for special forces, primarily U.S. Navy SEALs, from the decks of nuclear submarines. ) -- The SAR was submitted to report a schedule slip of approximately 17 months (from May 2004 to October 2005). The production decision (Milestone C) was postponed until successful demonstration of the new lithium ion A rechargeable battery technology introduced in 1991 that provides greater charge per pound than nickel metal hydride. In 1993, Toshiba introduced the first notebook in the U.S. with a Li-ion battery. battery in ASDS-1 and testing of other design changes made to improve acoustic signature For the article with regards audio files, see . Acoustic signature is used to describe a combination of acoustic emissions of ships and submarines. Contributing factors The acoustic signature is made up of a number of individual elements. and reliability. There were no cost changes reported since the December 2003 SAR. CVN 21 (Future Aircraft Carrier) -- The SAR was submitted to rebaseline the program from a planning to a development estimate following approval of entry into system development and demonstration (Milestone B) in April 2004. Program development costs increased by $727.6M (+20.2 percent) from $3,605.8 million to $4,333.4 million, due primarily to a revised estimate Revised estimate The third estimate of GDP released about three months after the measurement period. of development costs approved at Milestone B. As a result of Milestone B approval, the program entered into the system development and demonstration phase in April 2004, and $31,748.7 million of procurement for three carriers has been added to the SAR. Previously, the CVN 21 SAR was limited to development costs only (per 10 U.S.C. [section]2432). H-1 Upgrades -- The SAR was submitted to report schedule slips of six months or more. Completion of integrated testing slipped by eight months (from August 2004 to April 2005) and the start of full-rate production (Milestone III) slipped by six months (from August 2005 to February 2006), due to the tailboom annealing annealing (ənēl`ĭng), process in which glass, metals, and other materials are treated to render them less brittle and more workable. issues and associated schedule growth. Initial operational capability The first attainment of the capability to employ effectively a weapon, item of equipment, or system of approved specific characteristics that is manned or operated by an adequately trained, equipped, and supported military unit or force. Also called IOC. (IOC IOC abbr. International Olympic Committee IOC n abbr (= International Olympic Committee) → COI m IOC n abbr (= ) for the AH-1Z slipped by 15 months (from March 2008 to June 2009), due to a change in the Marine Corps procurement profile to expedite replacement of the aging UH-1Y fleet. There were no cost changes reported since the December 2003 SAR. MIDS-LVT MIDS-LVT Multifunctional Information Distribution System - Low Volume Terminal (Multi-Functional Information Distribution System-Low Volume Terminal) -- The SAR was submitted to rebaseline the program from a development to a production estimate following Navy approval of full-rate production (Milestone III) in June 2004. There were no cost changes reported since the December 2003 SAR. V-22 -- The SAR was submitted to report a schedule slip of 30 months (from September 2004 to March 2007) in initial operational capability of the MV-22, and a schedule slip of 15 months (from June 2006 to September 2007) in initial operational test and evaluation (testing) Initial Operational Test and Evaluation - (IOT&E) The first phase of operational test and evaluation conducted on pre-protectional items, prototypes, or pilot production items and normally completed prior to the first major production decision. completion of the CV-22. These delays were due to a new and expanded definition of IOC for the MV-22 in a change to the V-22 Joint Operational Requirements Document A formatted statement containing performance and related operational parameters for the proposed concept or system. Prepared by the user or user's representative at each milestone beginning with Milestone I, Concept Demonstration Approval of the Requirements Generation Process. Also called ORD. , and to a delay in developmental test of the CV-22 due to late return to flight, parts shortages, and transfer of test points from MV to CV. There were no cost changes reported since the December 2003 SAR. Air Force EELV EELV Evolved Expendable Launch Vehicle EELV End-Expiratory Lung Volume EELV Extended Expendable Launch Vehicle (Evolved Expendable Launch Vehicle The Evolved Expendable Launch Vehicle (EELV) program was a United States government, primarily a Department of Defense–sponsored effort to develop at least one family of space launch vehicles, that would meet the long term needs of the military and fulfill commercial ) -- The SAR was submitted to report a schedule slip of six months (from March 2005 to September 2005) in the heavy lift vehicle first operational flight. This delay was due to scheduling conflicts at the Spacecraft Processing and Integration Facility at Cape Canaveral Air Force Station The Cape Canaveral Air Force Station (CCAFS) is the East Coast space launch facility of the United States Department of Defense. Located on Cape Canaveral in the State of Florida, it depends on Patrick Air Force Base, home of the 45th Space Wing. CCAFS is adjacent to the John F. . Program costs decreased $557.1 million (-1.7 percent) from $32,346.5 million to $31,789.4 million, due primarily to variances between previous and new launch vehicle prices (-$8,249.0 million), launch quantity reductions (-$6,119.0 million), and shifts in payloads between vehicle classes (-$135.0 million). These decreases were partially offset by increases for infrastructure sustainment payments (+$12,791.3 million), program office technical support and operation expenses (+$908.4 million), and amortization of construction cost for the west coast launch pad (+$231.0 million). SBIRS (Space Based Infrared System) High -- The SAR was submitted to report a Nunn-McCurdy unit cost breach (i.e., a unit cost increase of 15 percent or more) and schedule delays of six months or more. Program costs increased $1,354.4 million (+15.7 percent) from $8,631.2 million to $9,985.6 million, due primarily to an increased engineering and manufacturing development estimate associated with technical performance challenges (+$1,118.4 million). Other cost increases are due to a one-year slip in geosynchronous Aligned with the earth's rotational speed. Refers to satellites that travel at the same speed as the earth, but may not always be at the same distance from the earth. See geostationary. earth orbit (GEO (Geostationary Earth Orbit) A communications satellite in orbit 22,282 miles above the equator. At this orbit, it travels at the same speed as the earth's rotation, thus appearing stationary. ) satellites 1 and 2 deliveries (from September 2006 to September 2007, and from September 2007 to September 2008, respectively) (+$45.0 million), an extension of the contract beyond FY 2010 (+$131.8 million), an increased requirement associated with GEO satellites 3, 4, and 5 parts obsolescence ob·so·les·cent adj. 1. Being in the process of passing out of use or usefulness; becoming obsolete. 2. Biology Gradually disappearing; imperfectly or only slightly developed. due to program delays (+$182.0 million), addition of GEO 4 (FY 2012) and GEO 5 (FY 2013) funding due to restoration of launch support capability (+$66.2 million), and increased sustainment costs (+$111.6 million). These increases were partially offset by decreases associated with removal of Block II redesign funds that were reported in the last two annual SARs but were not included in the approved acquisition program baseline Acquisition Program Baseline (APB) is a term used by the United States Department of Defense to refer to a program threshold and objective values for the minimum number of cost, schedule, and performance attributes that describe the program over its life cycle. (-$412.0 million). The under secretary of the Air Force signed a Nunn-McCurdy Unit Cost breach notification letter to Congress on June 17, 2004. New SARs (As of June 30, 2004) The Department of Defense has submitted initial SARs for five new programs (listed here). These reports do not represent cost growth. Baselines established on these programs will be the point from which future changes will be measured. The current cost estimates are provided to the left.
CURRENT ESTIMATE
($ IN MILLIONS)
December 2003 (78 programs) $1,332,027.2
Plus three new programs +4,856.6
(COBRA JUDY, MP RTIP, and SDB)
Less final reports (ABRAMS UPGRADE, COMANCHE, the FCR
portion of LONGBOW APACHE, the BLOCK I-III portion
of SM-2, AWACS RSIP, and JSTARS) -69,331.6
December 2003 Adjusted (77 programs) +1,267,552.2
Changes Since Last Report:
Economic $+18.5
Quantity -6,119.0
Schedule +72.1
Engineering -412.0
Estimating +7,949.0
Other 0.0
Support +16.3
Net Cost Change $+1,524.9
Plus initial procurement cost estimate for CVN 21
Future Aircraft Carrier (previous reports limited
to development costs per 10 U.S.C. 2432) +31,748.7
June 2004 (77 programs) $1,300,825.8
CURRENT ESTIMATE
($ IN MILLIONS)
Program
JCM (Joint Common Missile) $8,141.3
JTRS (Joint Tactical Radio System) CLUSTER 5 10,717.0
LCS (Littoral Combat Ship) 1,211.7
MMA (Multi-Mission Maritime Aircraft 31,428.6
TSAT (Transformational Satellite Communications
System) 17,661.3
Total $69,159.9
Pre-Milestone B program reporting development (Research, Development,
Test and Evaluation) costs only in accordance with the provisions of 10
U.S.C. [section]2432.
For more detailed information on the SARs report, please go to <http://www.defenselink.mil/news/Aug2004/d20040819PP.pdf>. |
|
||||||||||||||||||

Printer friendly
Cite/link
Email
Feedback
Reader Opinion