Department of Defense news release (Aug. 15, 2005): DoD releases selected acquisition reports.


The Department of Defense has released details on major defense acquisition program cost and schedule changes since the December 2004 reporting period. This information is based on the Selected Acquisition Reports (SARs) submitted to the Congress for the June 30, 2005, reporting period.

SARs summarize the latest estimates of cost, schedule, and technical status. These reports are prepared annually in conjunction with the president's budget. Subsequent quarterly exception reports are required for only those programs experiencing unit cost increases of at least 15 percent or schedule delays of at least six months. Quarterly SARs are also submitted for initial reports, final reports, and for programs that are rebaselined at major milestone decisions.

The total program cost estimates provided in the SARs encompass research and development, procurement, military construction, and acquisition-related operation and maintenance (except for pre-Milestone B programs, which are limited to development costs pursuant to 10 U.S.C. 2432). Total program costs reflect actual costs to date as well as future anticipated costs. All estimates include anticipated inflation allowances.

The current estimate of program acquisition costs [shown in the sidebar] for programs covered by SARs for the prior reporting period (December 2004) was $1,472,184.3 million. After subtracting the costs for six final reports (Joint Common Missile (JCM), Longbow Hellfire, Maneuver Control System (MCS), Navy Extremely High Frequency extremely high frequency
n. Abbr. EHF
A radio-frequency band with a range of 30,000 to 300,000 megahertz.

Noun 1.
 Satellite Communications System (NESP NESP Neuroendocrine Secretory Protein
NESP Navy EHF SATCOM Program
NESP Nurse Educator Scholarship Program
NESP Navy EHF Satellite Program
NESP National Environmental Studies Project
NESP National Education Supercomputer Program
), Standard Missile-2 (SM-2), and B-1 B Conventional Mission Upgrade Program (CMUP CMUP Conventional Munitions Upgrade Program )), and adding the costs for three new programs (Mission Planning System (MPS), Mobile User Objective System The Mobile User Objective System is an array of satellites being developed for the United States Department of Defense to provide global SATCOM narrowband (64 kbit/s and below) connectivity for communications uses by the United States and allies.  (MUOS MUOS Mobile User Objective System ), and Ship Self Defense System (SSDS SSDS SQL Server Data Services
SSDS Ship Self Defense System
SSDS Space Science Data System (NASA)
SSDS Sudden Sniffing Death Syndrome
SSDS Secure Software Distribution System
SSDS Sexual Self-Disclosure Scale
)) from the December 2004 reporting period, the adjusted current estimate of program acquisition costs was $1,474,122.2 million. There was a net cost decrease of $72.8 million (-0.005 percent) during the current reporting period (June 2005), which was the result primarily of revised program estimates for the Air Force's National Airspace System (NAS (1) See network access server.

(2) (Network Attached Storage) A specialized file server that connects to the network. A NAS device contains a slimmed-down operating system and a file system and processes only I/O requests by supporting the popular
) program.

For the June 2005 reporting period, there were quarterly exception SARs submitted for six programs. The reasons for the submissions are provided below.

Navy

LPD 17 (Amphibious Transport Dock A ship designed to transport and land troops, equipment, and supplies by means of embarked landing craft, amphibious vehicles, and helicopters. Designated as LPD.  Ship) -- The SAR (Segmentation And Reassembly) The protocol that converts data to cells for transmission over an ATM network. It is the lower part of the ATM Adaption Layer (AAL), which is responsible for the entire operation. See AAL.

SAR - segmentation and reassembly
 was submitted to report a schedule slip of seven months (from July 2006 to February 2007) for Lead Ship Initial Operational Capability The first attainment of the capability to employ effectively a weapon, item of equipment, or system of approved specific characteristics that is manned or operated by an adequately trained, equipped, and supported military unit or force. Also called IOC.  resulting from challenges associated with completing lead ship production and testing. There were no cost changes reported since the December 2004 SAR.

MH-60S Utility Helicopter -- The SAR was submitted to report a schedule slip of six months in the Initial Operational Capability of the Airborne Mine Countermine mission capability (from September 2006 to March 2007). This delay was caused by problems with the Carriage Stream Tow and Recovery System (CSTRS CSTRS California State Teachers Retirement System
CSTRS Carriage Stream, Tow, and Recovery System
). Resolution of the issue requires redesign and manufacture of some CSTRS components. There were no significant cost changes reported since the December 2004 SAR.

Air Force

EELV (Evolved Expendable Launch Vehicle The Evolved Expendable Launch Vehicle (EELV) program was a United States government, primarily a Department of Defense–sponsored effort to develop at least one family of space launch vehicles, that would meet the long term needs of the military and fulfill commercial ) -- The SAR was submitted to report a schedule slip of seven months (from May 2005 to December 2005) in approval of Full Rate Production (Milestone III) approval. The delay was due to an anomaly during the Delta IV heavy lift demonstration that delayed completion of the exit criteria required to proceed to Milestone III. There were no cost changes reported since the December 2004 SAR.

GBS See GB/sec.  (Global Broadcast Service) -- The SAR was submitted to report that the current estimate for Initial Operational Capability (IOC) 2/3 has slipped nine months (from March 2006 to December 2006), and the current estimate for the Beyond Low Rate Initial Production review has slipped five months (from November 2005 to April 2006). Both changes were caused by the need to integrate Operational Requirements Document A formatted statement containing performance and related operational parameters for the proposed concept or system. Prepared by the user or user's representative at each milestone beginning with Milestone I, Concept Demonstration Approval of the Requirements Generation Process. Also called ORD.  (ORD) III changes into the Test and Evaluation Master Plan (TEMP) and other test planning documentation. Program costs decreased $12.0 million (-1.6%) from $756.0 million to $744.0 million, as the result of a revised cost estimate and a quantity reduction of 12 units from 1,049 to 1,037 units.

NAS (National Airspace System) -- The SAR was submitted to rebaseline from a Development to a Production Estimate following the June 2005 approval of Full Rate Production (Milestone III). The dates for award of the Digital Airport Surveillance Radar Radar displaying range and azimuth that is normally employed in a terminal area as an aid to approach- and departure-control.  (DASR) full rate production contract and the DoD Advanced Automation System production award exercise were both changed from March 2005 to June 2005. The changes were due to a later-than-expected Beyond Low Rate Initial Production report and the effects of a changing management structure following the departure of the previous Milestone Decision Authority. The new baseline also includes the addition of Follow-on Operational Test and Evaluation (testing) operational test and evaluation - (OT&E) Formal testing conducted prior to deployment to evaluate the operational effectiveness and suitability of the system with respect to its mission.  as recommended by the Air Force Operational Test and Evaluation. Program costs decreased $59.5 million (-4.0%) from $1,480.6 million to $1,421.1 million, because primarily of a refinement in the Navy's cost estimate.

SDB (Small Diameter Bomb) -- The SAR was submitted to rebaseline the program from a Development to a Production Estimate following the April 2005 approval of Low Rate Initial Production (Milestone C). There were no cost changes reported since the December 2004 SAR.

A summary table of the SARs can be found at <http://www.defenselink.mil/news/Aug2005/d20050815sars.pdf>.
CURRENT ESTIMATE ($ IN MILLIONS)

December 2004 (88 programs)                   $1,472,184.3
Less final SAR submissions for six programs:
  JCM, Longbow Hellfire, MCS, NESP,
  SM-2, and B-1B (CMUP)                           -7,136.2
Plus three new programs:
  MPS, MUOS, and SSDS                             +9,074.1
December 2004 Adjusted
  (85 programs)                               +1,474,122.2
Changes Since Last Report:
  Economic                                            $0.0
  Quantity                                            -5.8
  Schedule                                            +1.7
  Engineering                                          0.0
  Estimating                                         -55.0
  Other                                               -0.0
  Support                                            -13.7
  Net Cost Change                                   $-72.8
June 2005 (85 programs)                       $1,474,049.4
COPYRIGHT 2005 Defense Acquisition University Press
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2005, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:In the News
Publication:Defense AT & L
Geographic Code:1USA
Date:Nov 1, 2005
Words:948
Previous Article:Navy newsstand (Aug. 12, 2005): advance construction begins for CVN 21.(In the News)
Next Article:U.S. Joint Forces Command news release (Aug. 23, 2005): commands working to improve joint planning in military deployment and distribution.(In the...
Topics:



Related Articles
Department of Defense news release (Oct. 14, 2004): DoD publishes Defense Acquisition Guidebook.(Policy and Legislation)(Brief Article)
Attention acquisition workforce personnel! DoD Best Practices Clearinghouse.(Career Development)
Subject: Suspension of the Price Evaluation Adjustment for Small Disadvantaged Businesses.(Policy & Legislation)(Brief Article)
DoD policy toward military specifications & standards.(In the News)(Department of Defense)(Brief Article)
General Accounting Office (GAO) reports, studies, testimony.(POLICY & LEGISLATION)(Illustration)
Acquisition & logistics excellence: an internet listing tailored to the professional acquisition workforce; surfing the net.
USD(AT & L) to help develop support strategy for homeland defense and civil support.(Policy & Legislation)(defense acquisition, technology and...
Subject: Acquisition Action Plan.(Policy & Legislation)
Subject: Update on Transition to the Federal Procurement Data System--Next Generation (FPDS-NG).(Policy & Legislation)
Web-enabling the integrated framework chart.(LEARNING RESOURCES)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles