Printer Friendly
The Free Library
14,734,713 articles and books
Member login
User name  
Password 
 
Join us Forgot password?

Crane delay leads to late start for terminal rent income.


A permitting quandary involving eight large cranes at the Port of Los Angeles The Port of Los Angeles is located on San Pedro Bay in the San Pedro neighborhood of Los Angeles, approximately 20 miles (30 km) south of downtown. Also called Los Angeles Harbor and WORLDPORT LA  is costing close to $2 million a month rent from its largest tenant.

A unit of Maersk Sealand, which the L.A. port lured from the rival Port of Long Beach in August 2002, has delayed occupancy of the 165-acre second phase of its facility at Pier pier, in engineering, term applied to a mass of reinforced concrete or masonry supporting a large structure, such as a bridge. When piers are built on ground of poor bearing value, it is often necessary to drive piles to obtain a firm base.  400 by at least a month, to Oct. 1.

The rent being foregone fore·gone
v.
Past participle of forego1.

adj.
Having gone before; previous.

Usage Note: The word foregone has recently developed a new meaning as a truncation of the phrase
 by the city-owned port amounts to $10,250 per acre per month, or $1.7 million.

Delays have been caused by port officials who waited more than a year to decide how to proceed with the permitting of the cranes, according to according to
prep.
1. As stated or indicated by; on the authority of: according to historians.

2. In keeping with: according to instructions.

3.
 a letter sent to port officials by a lawyer working for Maersk's APM (Advanced Power Management) A programming interface (API) from Intel and Microsoft for battery-powered computers that lets programs communicate power requirements to slow down and speed up components. See ACPI.

APM - Advanced Power Management
 Terminals unit. During that time, the letter states, port staff members asked APM not to order any of the cranes, which have about a 12- to 18-month lead time for delivery.

"The port's delay in acting on APM Terminals' request has resulted in a situation whereby the subject wharfage WHARFAGE. The money paid for landing goods upon, or loading them from a wharf. Dane's Ab. Index, h.t.  will sit idle until the cranes are delivered," according to the letter, sent to the port's chief operating officer Chief Operating Officer (COO)

The officer of a firm responsible for day-to-day management, usually the president or an executive vice-president.
, Bruce Seaton, by Elizabeth P. Beazley, the lawyer representing Maersk. "The delay costs to the parties will be significant."

Beazley's letter indicated that the cranes won't be ready for use until at least June 2005. The letter also states: "In order to account for this delay, the parties need to meet for purposes of deferring the occupancy date for Phase II ... and working out a financial solution."

October start date

Arley Baker, the port's director of public affairs Those public information, command information, and community relations activities directed toward both the external and internal publics with interest in the Department of Defense. Also called PA. See also command information; community relations; public information. , denied that the cranes had caused any delay in the terminal's opening, saying it is still 30 days from "substantial completion," which requires fenders (bumpers that protect the docks from the ships) to be installed on the edge of the dock, some electrical work, lighting and final pavement pavement, the wearing surface of a road, street, or sidewalk. Parts of Babylon and Troy are believed to have been paved; Roman roads were noted for their durable stone paving. Cobblestones were common from late medieval times into the 19th cent.  work.

"We are expecting the billing schedule to start Oct. 1, a month behind schedule but terms unchanged," Baker said.

However, a source said port officials have essentially stopped work on the facility to buy time while they work out a financial arrangement with Maersk. The source said that materials for the fenders, for example, are already at the port or easily obtained.

According to this source, the terminal could have opened and been drawing rent as early as July.

Beazley referred calls to Maersk Sealand. Maersk spokesman John Heenehan said "the crane permit was issued and things are moving forward. I can't speak to when those cranes are going to be here. That's a question mark I can't answer. We really wouldn't want to go any further than that."

Baker also said he did not know about the arrival time of the cranes, which are needed to unload To remove a program from memory or take a tape or disk out of its drive.  large cargo containers from the ship. But he said the facility could open without them, using other cranes. "It would depend on how many ships were docked at one time," said Baker.

Separate dispute

The delays arose from a separate environmental dispute over the China Shipping terminal that overtook o·ver·took  
v.
Past tense of overtake.
 the port around the same time Maersk was planning its second phase.

In the first phase of its terminal construetion, Maersk installed 10 of the 250-foot cranes without incident. But before the second batch could be ordered, the size of the cranes became a hot-button issue Noun 1. hot-button issue - an issue that elicits strong emotional reactions
gut issue

issue - an important question that is in dispute and must be settled; "the issue could be settled by requiring public education for everyone"; "politicians never discuss
 for residents near the port, who complained they blocked views of the ocean.

As part of the eventual $60 million settlement with environmentalists over the construction of the China Shipping terminal, the port agreed to install two cranes that are about 100 feet shorter. Port officials were contemplating requiring similar cranes at the APM terminal.

According to Beazley's letter, APM Terminals advised the port in early 2003 of its intention to order eight standard cranes. But the port's executive director, Larry Keller, subsequently sent a letter to all terminal operators advising that they needed to coordinate with port staff on all future crane orders to secure a Coastal Development Permit.

APM contended that a new permit was unnecessary, since one had been obtained earlier covering both phases of the terminal's development.

The port then suggested that APM complete a Harbor Development Application. The application, completed last August, was never approved by the port.

The port eventually reconsidered the necessity of a new Coastal Development Permit, agreeing with the view that APM Terminals held all along. Instead, a more general Harbor Engineer's Permit was to be granted, Beazley's letter said.

In her letter, Beazley also implied that the port has agreed to provide political cover for APM if friction arises from the decision on the permits.

"We appreciate and expect that the port will publicly acknowledge that APM Terminals is only obligated ob·li·gate  
tr.v. ob·li·gat·ed, ob·li·gat·ing, ob·li·gates
1. To bind, compel, or constrain by a social, legal, or moral tie. See Synonyms at force.

2. To cause to be grateful or indebted; oblige.
 to obtain a harbor engineer's permit prior to the installation of the balance of the cranes," the letter states.
COPYRIGHT 2004 CBJ, L.P.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2004, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:Up Front
Comment:Crane delay leads to late start for terminal rent income.(Up Front)
Author:Greenberg, David
Publication:Los Angeles Business Journal
Geographic Code:4EUDE
Date:Aug 30, 2004
Words:816
Previous Article:Port backups don't ease despite new hires.(Up Front)
Next Article:'Rooftops' seen as key element for downtown's future protects.(Up Front)(Apartment buildings)
Topics:



Related Articles
Boom with a view. (L.A. Stories).(collapsible cranes at Port of L.A.)(Brief Article)
'Model' port offers distinct lessons. (Up Front).(Singapore)(Brief Article)
Environmental review will delay port project. (Up Front).(constructionon port terminal halted in California by Court of Appeal)
Ports digging deep to service bigger ships.(Up Front)(Port of Los Angeles)
GROCERY STRIKE HURTS OPENINGS AT NEW MALL.(News)
Work comes to those who waited: for 'casuals' hired on an as-needed basis at ports, jobs are plentiful.(Up Front)
MOTSU moves ahead! New equipment supports more efficient cargo handling at Sunny Point.(Military Ocean Terminal Sunny Point )
Maersk lease feud heads to court.(UP FRONT)(Maersk SeaLand, Port of Long Beach)
Low-income apartment building set for opening.(Real Estate & Housing)
7 SMALL AIRLINES SEEK RELIEF FROM LAX RENT INCREASES.(News)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles