Cost savings from nuclear regulatory reform: an econometric model.


I. Introduction

The nuclear-generated power touted in the 1950s as someday some·day  
adv.
At an indefinite time in the future.

Usage Note: The adverbs someday and sometime express future time indefinitely: We'll succeed someday. Come sometime.
 being "too cheap to meter" got dismissed in the 1980s as incapable of being both safe and cost effective. Today, less than 20 percent of American's electricity is nuclear-generated, no new plants are planned or on order, and some of the earliest units are scheduled for decommissioning Decommissioning is a general term for a formal process to remove something from operational status. Some specific instances include:
  • Ship decommissioning
See also:
 within the next decade. Even so, interest in nuclear power has been revived by increasing energy demands, concerns about global warming global warming, the gradual increase of the temperature of the earth's lower atmosphere as a result of the increase in greenhouse gases since the Industrial Revolution. , and the uncertainty surrounding oil resources in the Persian Gulf Persian Gulf, arm of the Arabian Sea, 90,000 sq mi (233,100 sq km), between the Arabian peninsula and Iran, extending c.600 mi (970 km) from the Shatt al Arab delta to the Strait of Hormuz, which links it with the Gulf of Oman. . As a long-term alternative to fossil fuels fossil fuel: see energy, sources of; fuel.
fossil fuel

Any of a class of materials of biologic origin occurring within the Earth's crust that can be used as a source of energy. Fossil fuels include coal, petroleum, and natural gas.
, atomic energy atomic energy: see nuclear energy.  offers the important advantages of clean air and domestic availability of fuel. But these advantages will count for little unless and until the costs of nuclear power can be seen as reasonable.

Our premise is that the relevant costs are those of providing safe and environmentally clean electric energy. To the extent that increased costs have resulted from increasingly stringent regulations, they reflect the internalization Internalization

A decision by a brokerage to fill an order with the firm's own inventory of stock.

Notes:
When a brokerage receives an order they have numerous choices as to how it should be filled.
 of external costs. Indeed, the external costs of nuclear power (particularly safety and environmental protection) have been internalized to a greater degree than with most alternative fuel sources used by electric utilities. Nuclear construction costs are properly compared with those of alternative sources only after the latter are adjusted for environmental damage and endangerment, including, as examples, the costs of oil spills This is a list of oil spills throughout the world. Large Oil Spills to Date
Oil Spills of over 100,000 tonnes or 30 million US gallons, ordered by Tonnes
Spill / Tanker Location Date *Tons of crude oil link
, of building double-hulled tankers, and of building off-shore offloading facilities. A shift to nuclear sources could reduce these costs whereas it would increase disposal costs for radioactive materials radioactive material Radiation A substance that contains unstable–radioactive–atoms that give off radiation as they decay. See Radioactive decay. . We do not estimate any of these environmental costs in this article; each would be a major study in itself. We nonetheless contend that a better understanding of nuclear plant construction costs is pivotal to a balanced evaluation of the merits of uranium relative to other fuel choices.

Several regulatory reforms Regulatory Reform concerns improvements to the quality of government regulation.

At the international level, the "OECD Regulatory Reform Programme is aimed at helping governments improve regulatory quality -- that is, reforming regulations that raise unnecessary obstacles to
 have been under consideration. At the federal level, the utilities are currently seeking to streamline and expedite ex·pe·dite  
tr.v. ex·pe·dit·ed, ex·pe·dit·ing, ex·pe·dites
1. To speed up the progress of; accelerate.

2.
 the licensing process in an effort to abbreviate construction durations. Utilities are proposing pre-approved, standardized standardized

pertaining to data that have been submitted to standardization procedures.


standardized morbidity rate
see morbidity rate.

standardized mortality rate
see mortality rate.
 designs, pre-approved sites, one-stop licensing and legislative-style NRC NRC
abbr.
1. National Research Council

2. Nuclear Regulatory Commission

Noun 1. NRC - an independent federal agency created in 1974 to license and regulate nuclear power plants
 hearings instead of adjudicatory proceedings. At the state level they propose the elimination of retroactive Having reference to things that happened in the past, prior to the occurrence of the act in question.

A retroactive or retrospective law is one that takes away or impairs vested rights acquired under existing laws, creates new obligations, imposes new duties, or attaches a
 prudence reviews [11]. Our study provides insights into the effects of these proposals.

Despite the public clamor over nuclear power costs, the population of related articles in the economic literature is small. In a study by Mooz [5], nuclear construction costs are related to significant regional effects, scale economies and learning effects. Mooz also finds higher costs related to cooling towers in the plant's design. A follow-up study [6], with an expanded data base, confirmed learning effects but failed to find scale economies. Zimmerman [12] examines learning-by-doing effects both for the firm and the industry, with internal learning reducing costs at nearly twice the rate of external learning. He finds that construction costs rise in a one-to-one proportion to duration (construction start date to commercial operation date). Komanoff [3] and Cantor and Hewlett [1] respectively find reductions in overnight costs of 13 percent and 47 percent upon doubling plant size. Both studies nonetheless find scale economies are largely offset by a rise in duration associated with project size.

A U.S. Department of Energy (DOE) study [2] distinguishes resources costs and "time related" costs, attributing 75 percent of construction cost to increases in the former. Duration, however, adds to resources cost because it increases with (unmeasured) design changes as well as with safety and environmental retrofits required by regulations. DOE finds significantly higher costs for utilities using outside firms for design and engineering than for utilities performing these functions themselves. Thus, internal experience has a positive learning effect. Radlauer, Bauman, and Chapel [9] attribute a shift in construction costs from the pre-1972 era to the post 1971 era to an abrupt change in the regulatory environment.

Our model has several unique features. (1) The cost data are carefully adjusted to limit the number of remaining explanatory variables, increasing the degrees of freedom and minimizing multicollinearity. (2) Economies of scale for nuclear projects are correctly identified for the first time. (3) Learning effects are detected by an experience variable. (4) A duration variable is introduced to measure the effects of delay. Our findings comprise a bridge across the earlier findings [1; 2; 5; 6; 8; 12].

II. Theory

The real cost of nuclear power projects has greatly increased since the first plant became operational in 1957. Theory suggests three important contributors to this trend: increased regulatory requirements Regulatory requirements are part of the process of drug discovery and drug development. Regulatory requirements describe what is necessary for a new drug to be approved for marketing in any particular country. , changing market conditions, and lengthening lengthening (lengkˑ·the·ning),
n the use of various massage or muscle energy techniques to relax and stretch muscle and connective tissue.
 construction durations.

Designed to ensure the reliability and safety of output, regulations since at least the 1960s have tended to be increasingly stringent. Their impact will differ among plants, depending on the efficiency with which each utility and architect/engineer deal with them. We nonetheless can expect that plants completed under later regulatory requirements will tend to cost more than those built earlier.(1) The consequent engineering features (e.g., a cooling tower requirement) may account for a sizable part of the cost differences among nuclear power plant construction projects. However, the cost effects of NRC regulation should not be allowed to mask the effects of mismanagement mis·man·age  
tr.v. mis·man·aged, mis·man·ag·ing, mis·man·ag·es
To manage badly or carelessly.



mis·manage·ment n.
 or incompetence in·com·pe·tence or in·com·pe·ten·cy
n.
1. The quality of being incompetent or incapable of performing a function, as the failure of the cardiac valves to close properly.

2.
. If poor design or construction work require portions of the plant to be torn out and rebuilt, the resulting delays and increased costs may owe more to poor management than to the NRC. Therefore, project duration is an important cost variable. Unusually lengthy construction indeed may indicate a comparatively inefficient, ineffective, or incompetent project team. A short duration can imply that the team managing and building the plant is particularly effective. Presently, each U.S. plant is unique; however, intuition suggests that the experience variable would have higher values and construction duration would be significantly reduced if the industry were to repeatedly build one or two standard designs.

Demographics The attributes of people in a particular geographic area. Used for marketing purposes, population, ethnic origins, religion, spoken language, income and age range are examples of demographic data.  also play a role in nuclear plant costs. A small cost differential is attributable to climate, since very cold or wet weather can impede im·pede  
tr.v. im·ped·ed, im·ped·ing, im·pedes
To retard or obstruct the progress of. See Synonyms at hinder1.



[Latin imped
 construction. Urban congestion The condition of a network when there is not enough bandwidth to support the current traffic load.

congestion - When the offered load of a data communication path exceeds the capacity.
 can also add to plant costs, creating difficulties in the shipping of materials or forcing the imposition of additional safety requirements. Because it is often difficult to isolate the various contributors to these geographically related costs, a categorical That which is unqualified or unconditional.

A categorical imperative is a rule, command, or moral obligation that is absolutely and universally binding.

Categorical is also used to describe programs limited to or designed for certain classes of people.
 variable is sometimes used, capturing the significance of all regional factors combined. A more sophisticated approach - the one we use - is an accounting of known wage and materials cost differentials. When adjusting the plant cost data for inflation (putting all plants into equivalent real terms), we also adjust for regional differences in cost of living and other costs of construction.

Learning based upon project design experience can lower costs. As a utility gains experience in the hiring and use of architect and engineering firms, it may gain a learning-by-doing effect in design efficiency. Construction efficiency is closely related both to design efficiency and to technological improvements shared by the entire power plant construction industry.

Economies of scale can also lower plant costs. Beyond some point, however, the scale economy diminishes as larger volumes come to require extra structural reinforcement, special materials, unusual construction techniques, or complex management or monitoring systems.

Finally, whereas there is a cost to regulatory standards, there also is a benefit. Output in terms of Mwe capacity is qualitatively improved by design enhancements (rising regulations). We assume, in the interests of simplicity, that regulations effect output in such a way that relative input shares remain constant along the expansion path (Hicksian neutrality). Paik and Shriver shrive  
v. shrove or shrived, shriv·en or shrived, shriv·ing, shrives

v.tr.
1. To hear the confession of and give absolution to (a penitent).

2.
 [8] find some evidence supporting Hicksian neutrality. The most general construction production function would be

q = G(R)F(L, K), (1)

in which labor and capital are adjusted by a function of the regulatory requirements or G(R). By the same token, the value of q embodies an environmentally cleaner and safer capacity. If other inputs such as materials are affected by regulation, we have

q = G(R)H(L, K, M), (2)

where M is a vector representing other inputs.

According to according to
prep.
1. As stated or indicated by; on the authority of: according to historians.

2. In keeping with: according to instructions.

3.
 duality Duality (physics)

The state of having two natures, which is often applied in physics. The classic example is wave-particle duality. The elementary constituents of nature—electrons, quarks, photons, gravitons, and so on—behave in some respects
 theory, we can be indifferent between estimation of the production or of the cost relationship. Either would provide full explanation of the structure of production. We select the cost function because it provides a more reliable estimate of the effects of exogenous Exogenous

Describes facts outside the control of the firm. Converse of endogenous.
 forces and because regulation, learning-by-doing, and managerial inefficiency in the architectural engineering Architectural engineering

A discipline that deals with the technological aspects of buildings, including the properties and behavior of building materials and components, foundation design, structural analysis and design, environmental system analysis and
 stages are directly related to construction inputs rather than to construction output.

The most general dual cost function (as related to equation(2)) is

C = J(q, N, R, P, Z), (3)

where q is net reliable, safe electric generating capacity (Mwe), N is an index of learning-by-doing, R is a measure of regulation, P is a vector of input prices, and Z is a vector of special design choices.

Sometimes it is useful to "deflate (file format, compression) deflate - A compression standard derived from LZ77; it is reportedly used in zip, gzip, PKZIP, and png, among others.

Unlike LZW, deflate compression does not use patented compression algorithms.
" or "inflate inflate - deflate " the dependent variable by known prices of inputs or other price differentials. Since nuclear construction projects are of long duration and are completed over different periods and with different variable price sets, an alternative version of equation (3) would be

L[(X).sup.-1]K[(P).sup.-1]C = J(q, N, R, Y), (4)

in which K is a function of the vector of input prices over time, L is a function of X which is a subset of Z, and Y represents the residual subset of Z. Then equation (4) can be simplified to

[C.sup.*] = J(q, N, R, Y), (5)

where [C.sup.*] is the adjusted cost variable.

From these equations, we estimate the parameters for two models. The initial choice for the cost equation is a multiplicative mul·ti·pli·ca·tive  
adj.
1. Tending to multiply or capable of multiplying or increasing.

2. Having to do with multiplication.



mul
 form in order to capture the interaction of variables and the expectation that cost increases due to duration and decreases due to size are nonlinear A system in which the output is not a uniform relationship to the input.

nonlinear - (Scientific computation) A property of a system whose output is not proportional to its input.
. Therefore, in Model A, ordinary least squares (OLS OLS Ordinary Least Squares
OLS Online Library System
OLS Ottawa Linux Symposium
OLS Operation Lifeline Sudan
OLS Operational Linescan System
OLS Online Service
OLS Organizational Leadership and Supervision
OLS On Line Support
OLS Online System
) is applied to

In [C.sup.*] = [B.sub.0] + [B.sub.1] lnR + [B.sub.2] ln q + [B.sub.3]DUR DUR Drug utilization review, see there  + [B.sub.4]N, (6)

where [C.sup.*] is adjusted construction cost per kilowatt hour Kil´o`watt` hour

1. (Elec.) A unit of work or energy equal to that done by one kilowatt acting for one hour; - approximately equal to 1.34 horse-power hour.

Noun 1.
 (details below), R is the number of total regulations up to the completion date of the last unit of a project, DUR is the number of months between construction start and commercial operation, and N is the number of previous nuclear projects owner-operated by the utility prior to the construction start date (the experience variable).

In Model B, OLS is applied to

In [C.sup.*] = [C.sub.0] + [C.sub.1] lnR + [C.sub.2] lnR([D.sub.1]) + [C.sub.3] lnq + [C.sub.4] lnq([D.sub.2]) + [C.sub.5]DUR + [C.sub.6]DUR([D.sub.3]) + [C.sub.7]N + [C.sub.8]N([D.sub.4]). (7)

This estimation allowed us to use the entire sample but distinguish values of the coefficients for two separate periods. The dummy variables This article is not about "dummy variables" as that term is usually understood in mathematics. See free variables and bound variables.

In regression analysis, a dummy variable
 (the Ds) were used to determine whether the slope coefficients differed between the two eras selected.

III. Data Issues in Nuclear Plant Comparisons

Our selection of a well-defined population avoids potentially thorny thorn·y  
adj. thorn·i·er, thorn·i·est
1. Full of or covered with thorns.

2. Spiny.

3. Painfully controversial; vexatious: a thorny situation; thorny issues.
 statistical problems. We include in the study all plants whose construction began after 1966 and was completed by 1987. Thus, the small number of projects built in the pre-1967 turnkey period are excluded; they were somewhat experimental in nature, and their costs were partially subsidized sub·si·dize  
tr.v. sub·si·dized, sub·si·diz·ing, sub·si·diz·es
1. To assist or support with a subsidy.

2. To secure the assistance of by granting a subsidy.
 by manufacturers who were anxious to promote the new technology. These criteria provide a sample comprised of 53 projects.

By considering the total costs of each construction project, we avoided problems with inconsistent accounting treatments of the common costs of multiple units. By adjusting the cost data to reflect the amount of disallowances for imprudence im·pru·dence  
n.
1. The quality or condition of being unwise or indiscreet.

2. An unwise or indiscreet act.

Noun 1.
 as established by regulators, we ensured that the model would provide better estimates of the "reasonable" costs of all projects in the population.(2) We updated the Tennessee Valley Authority Tennessee Valley Authority (TVA), independent U.S. government corporate agency, created in 1933 by act of Congress; it is responsible for the integrated development of the Tennessee River basin. (3) data with more recent cost and schedule estimates obtained directly from the utilities.

Initially, the construction costs in each year are reported in current dollars of those years. Over time, of course, these are not the same dollars. The industry has developed the idea of "overnight" dollars as a method for expressing costs in terms of comparable dollars. Thus, the nominal outlays Outlays

Payments on obligations in the form of cash, checks, the issuance of bonds or notes, or the maturing of interest coupons.
 for each project, once estimated, must be inflated over time to express costs in today's like dollars ("overnight" dollars). This is done with the regional Handy-Whitman nuclear power plant construction cost index that measures cost of labor, material, and equipment.(4) The overnight costs ([C.sup.*]) are

[C.sup.*] = [summation summation n. the final argument of an attorney at the close of a trial in which he/she attempts to convince the judge and/or jury of the virtues of the client's case. (See: closing argument)  of]([C.sub.[Tau]]/[I.sub.[Tau]]) where [Tau] = s to f, (8)

where [I.sub.[Tau]] is the Handy-Whitman nuclear power plant construction index, s = start date of construction and f = finish date of construction. The index of construction ([I.sub.[Tau]]) provides a sequence of annual inflation rates where

[Mathematical Expression A group of characters or symbols representing a quantity or an operation. See arithmetic expression.  Omitted],

for t = s + 1, s + 2, . . ., f. The concept of overnight costs is a variation of present discounted value, differing in appearance only because time-f dollars comprise the numeraire rather than time-s dollars.

A meaningful comparison of project costs requires distribution of cash expenditures over the construction cycle for each period. To accomplish this task we applied an industry-standard S curve, a formula used by the Energy Information Administration [2, 89]. The pattern is established by

[y.sub.t] = [{1 - [[cos([Pi]/2)([x.sub.t])].sup.4.08198]}.sup.3.24948] (10)

where [y.sub.t] = cumulative percent of total cost in year t and [x.sub.t] = fraction of total elapsed e·lapse  
intr.v. e·lapsed, e·laps·ing, e·laps·es
To slip by; pass: Weeks elapsed before we could start renovating.

n.
 construction time. The proportion or share spent during year t is [k.sub.t] = [y.sub.t] - [y.sub.t-1]. In turn, these shares for each year are used to derive the annual costs in equation (8). With this normal pattern, total nominal project expenditures can be spread year by year over the entire construction period.(5)
Table I. Nuclear Power Plant Disallowances (000,000)


Plant                  Disallowance    Plant
Disallowance


Byron 1                   $101.5       River Bend         1,400.0
Callaway 1                 440.0       San Onofre 2         344.6
Fermi 2                    397.0       Shearon Harris       322.8
Hope Creek                 489.2       Shoreham           1,395.0
Limerick 1                 368.9       Vogtle 1             951.0
Nine Mile Point 2        1,803.0       Waterford 3          284.0
Palo Verde                  60.0       Wolf Creek           257.3
Perry 1                    628.0


Sources: Commonwealth Edison, Annual Report, 1985; Illinois Power
Company, Kansas City Power & Light Company, Louisiana Power & Light
Company, Philadelphia Electric Service Company, Southern California
Edison Company, Union Electric, Annual Reports, 1986; Gulf States
Utilities, Annual Report, 1987; Michigan Public Service Commission,
Final Order, Case U-7760; New York Public Service Commission,
Opinion No. 86-24, Case 29124; Texas Public Utilities Commission,
Final Order, Docket No. 7460; Moody's Public Utility Manual, 1987;
NARUC Bulletin, January 6, 1986; NASUCA Newsletter, March 1988.


Mooz [5] concluded that Northeastern region plants are the most expensive. Possible causes include a denser population, fewer suitable plant sites, and - most notably - higher construction wage rates. We adjusted the cost of all plants for differences in wage and material costs in each of the six Handy-Whitman regions.(6) By this means costs are pre-adjusted for input price differentials between regions (see equation (4)). This conversion of all plant costs to regionally equivalent overnight dollars permits use of the largest possible sample. The unique conversion ratio for each estimate is dependent primarily on the timing and duration (as well as the regional location) of each construction project.(7)

As the sample includes not only prudent projects, but also projects for which regulators have disallowed certain costs due to mismanagement and inefficiency, we adjusted the cost of imprudent im·pru·dent  
adj.
Unwise or indiscreet; not prudent.



im·prudent·ly adv.
 plants by the value of known disallowances, thereby putting the projects on a common basis, as if all were constructed in a prudent manner. This adjustment is not perfect because regulators often lack sufficient evidence to quantify the excessive costs.(8) The plants and disallowances used appear in Table I.

IV. Results

We reduced the set of explanatory variables to the smallest number that will adequately explain construction cost per kw of capacity. Prior to the regression analysis In statistics, a mathematical method of modeling the relationships among three or more variables. It is used to predict the value of one variable given the values of the others. For example, a model might estimate sales based on age and gender. , costs were adjusted for substantial regional differences, disparate inflation rates at different times, and imprudent or unreasonable costs. The reduction in explanatory variables increases degrees of freedom and reduces multicollinearity. In particular, we no longer need region or inflation variables. These adjusted project costs appear in Table II.

We also tested several potential measures of the unique design characteristics of each project (e.g., the presence of cooling towers, the depth to bedrock, the type of reactor vessel reactor vessel
n.
The protective containment vessel surrounding the nuclear fission core in a nuclear reactor.
). These were not consistently significant, probably because the cost of various design features varies with the method chosen by the architect/engineer. Our final equations thus include no design variables. We identified proxy variables for the remaining explanatory variables.

Descriptive statistics descriptive statistics

see statistics.
 are reported in Table III. The final equation for the first test (Model A) is simple but powerful, containing four independent variables, all significant at the 0.0001 level. The regression results appear in Table IV for both models. We tested for heteroscedasticity, with negative results.(9) The signs and magnitude of all the coefficient estimates accord with our theoretical expectations. Regulatory requirements have a positive effect on construction cost, as the external impacts on safety and the environment have been internalized. Also, in a simulation from the model, cost per kw declines as project size increases, providing the textbook-like graph reflecting economies of scale [ILLUSTRATION FOR FIGURE 1 OMITTED]. The experience variable shows large and favorable learning-curve effects. Construction duration also is significant. The greater the number of months between the construction start date and commercial operation of the final unit, the greater the cost per kw. This result fits our expectations: projects with long durations tend to have very high costs per kw.(10)

Radlauer, Bauman, and Chapel [9] have suggested that the structure of pre-1972 nuclear plant costs is different from that of post-1971 costs, attributing the differences to changes in the regulatory environment commencing with the Calvert Cliffs Calvert Cliffs may refer to:
  • Calvert Cliffs Nuclear Power Plant, a nuclear power plant located on the Chesapeake Bay
  • Calvert Cliffs State Park, a state park on the Chesapeake Bay
 decision in 1972. While there are undoubtedly differences between the two regulatory environments, a properly specified regulatory variable should account for most increases in cost due to these changes. Hence, we considered it appropriate to use data from both periods.

Nevertheless, we used Model B to test for structural changes between the early (pre-1972) and late (post-1971) eras. In Model B we pooled the two sub-samples and used dummy variables to identify any changes in the slope coefficients between the two eras. In this model, D is a dummy variable having a value equal to unitary unitary

pertaining to a single object or individual.
 for the post-1971 era and zero for the pre-1972 era.(11) The results are reported in Table IV. Most of the nondummy coefficient estimates are significant at the 0.0001 level, a pattern consistent with that of Model A. The slope dummies are generally insignificant, suggestive of suggestive of Decision making adjective Referring to a pattern by LM or imaging, that the interpreter associates with a particular–usually malignant lesion. See Aunt Millie approach, Defensive medicine.  no structural differences between the two periods.

[TABULAR tab·u·lar
adj.
1. Having a plane surface; flat.

2. Organized as a table or list.

3. Calculated by means of a table.



tabular

resembling a table.
 DATA FOR TABLE II OMITTED]

[TABULAR DATA FOR TABLE III OMITTED]

The predicted values from Model A are compared with actual values (in 1986 dollars) in Figure 2. As we see, only about five of the actual project costs stray far from their predicted values. Moreover, Model B should not be dismissed entirely. The insignificance in·sig·nif·i·cance  
n.
The quality or state of being insignificant.

Noun 1. insignificance - the quality of having little or no significance
unimportance - the quality of not being important or worthy of note
 of some of the variables results from multicollinearity, according to several standard statistical tests. Model B remains a good predictive model. Each time, when a single slope dummy Sham; make-believe; pretended; imitation. Person who serves in place of another, or who serves until the proper person is named or available to take his place (e.g., dummy corporate directors; dummy owners of real estate).  was introduced into Model A, it was statistically significant at minimally the .1000 level.

V. Policy Simulations

We now return to nuclear policy reform proposals. If a standardized plant size and design were selected, economies of scale advantages close to a "reasonable optimum" could be gained. Then replication of standard designs would cause experience to accumulate quickly. Such homogeneity Homogeneity

The degree to which items are similar.
 could speed the construction process greatly. Pre-approved sites, one-stop licensing, and standardized inspection procedures would also serve to reduce duration by simplifying and expediting the regulatory process. To estimate the probable effects of such policy reforms, we used Model A to simulate alternative costs per kw at different values for the independent variables. A policy simulation matrix of the most plausible possibilities within and outside the sample is presented in Table V.
Table IV. Regression Results Dependent Variable: Log of Cost per KW


Independent Variables                    Model A          Model B


Intercept                               5.489150          6.171802
                                       (0.676939)(a)     (1.049015)
                                          0.0001(b)         0.0001


Log of Cumulative Regulations           1.111391          0.847764
                                       (0.097138)        (0.246081)
                                          0.0001            0.0001


Log of Project Net Mwe                 -0.512734         -0.474663
                                       (0.097138)        (0.098971)
                                          0.0001            0.0001


Project Duration                        0.003721          0.005040
                                       (0.001148)        (0.002248)
                                          0.0001            0.0001


Utility Nuclear Project Experience      -0.13427         -0.291892
                                       (0.050057)        (0.136477)
                                          0.0001            0.0150


Regulation Slope Dummy                                    0.085264
                                                         (0.216844)
                                                            0.6502


Size Slope Dummy                                         -0.029657
                                                         (0.137998)
                                                            0.5980


Duration Slope Dummy                                     -0.000109
                                                         (0.002424)
                                                            0.5100


Experience Slope Dummy                                    0.168144
                                                         (0.145461)
                                                            0.8670


n                                             53                53


[R.sup.2]                                  0.893             0.903


F-Ratio                               109.676275         68.652985


a. Standard error.


b. Significance level.


Across the top of the matrix the project size is varied between 800 and 2400 Mwe. The experience variable has been fixed, in turn, at 2 and 3 (within the sample) and then at 4 and 5 (outside the sample values). The value of the experience variable is assumed to increase with standardization standardization

In industry, the development and application of standards that make it possible to manufacture a large volume of interchangeable parts. Standardization may focus on engineering standards, such as properties of materials, fits and tolerances, and drafting
 because firms would be replicating the same prototype plant. The value of the cumulative regulations is set at its maximum of 153, which assumes no existing rule will be rescinded.

Project duration in our sample ranged from 40 to 213 months, averaging 125. Duration varies (along the vertical) from 60 to 150 in the policy simulation matrix. The larger the size of the project, the lower the costs on each line of the matrix. However, the costs per kw decline by smaller and smaller percentages with each Mwe increase in scale. Moreover, these gains are achieved only if we assume a constant duration. In the real world, of course, duration is not constant. From the sample and from the findings of Komanoff [3] and Cantor and Hewlett [1] we know that duration sometimes increases with the project size. For example, returning to the policy matrix, a 2400-Mwe project completed in 60 months at sample maximal max·i·mal
adj.
1. Of, relating to, or consisting of a maximum.

2. Being the greatest or highest possible.
 experience (3) costs $1002 per kw (1986 dollars); extended to 150 months it costs $1401 per kw. Often during the 1980s, the larger the project, the greater was the duration and the higher the costs.

Japan's experience suggests that duration need not be closely related to size, according to Navarro [7]. Exceeding the established 600-900 Mwe range raised construction time by only 10 months. Realistically, however, it seems unlikely that an extremely large plant size could be accepted as a standard by the industry, since it would exceed the needs of all but the most densely populated pop·u·late  
tr.v. pop·u·lat·ed, pop·u·lat·ing, pop·u·lates
1. To supply with inhabitants, as by colonization; people.

2.
 regions. If designs were standardized in the U.S., the optimally-sized project would probably be in the 800-Mwe to 1200-Mwe range. This would ensure usability by both small and large utilities and would allow more frequent repetition of the construction process.

The potential cost savings from more rapid construction is very significant. Duration for the 1979-86 period averaged 61.64 months in Japan versus 140.71 months in the U.S. [7,3-4). Since 1975, the Japanese utility industry has adopted a two-design program, with standardized reactors. In our policy matrix, a 1200-Mwe project would cost $1729 per kw if completed in 75 months by a utility with experience building two previous projects. Increasing the experience value to the sample-maximal value of three reduces the cost to $1512 per kw. If additional experience were gained beyond this historical maximum, the simulated cost would be reduced to $1322 and $1156 as successive projects were built, strongly suggesting the potential benefits of moving down the learning curve through replication. (The outside-of-sample extrapolations can be defended on the grounds of the near-linearity of cost and experience within the sample.)

If a policy of standardization The policy of standardization law was passed by the Sri Lankan parliament in 1971 in order to rectify disparities created in university enrolment under Colonial rule. The reasoning for the law  were to achieve these changes in duration and experience, the effect on construction costs would be dramatic - allowing nuclear power to become a viable, low-cost alternative for new baseload electric generating capacity. Pre-approved sites, one-stop licensing, and standardized inspections could reduce costs even more.
Table V. Policy Simulation Matrix: Model A


                                          Project Size (Mwe)
Project Duration (Months)    800     1200     1600     2000
2400


Experience = 2


60                           2013    1635     1411     1258
1146
75                           2128    1729     1492     1330
1212
90                           2250    1828     1577     1407
1281
105                          2380    1933     1668     1488
1355
120                          2516    2044     1764     1573
1433
135                          2661    2161     1865     1663
1515
150                          2813    2285     1972     1759
1602


Experience = 3


60                           1760    1430     1234     1100
1002
75                           1861    1512     1304     1163
1059
90                           1968    1598     1379     1230
1120
105                          2081    1690     1458     1301
1185
120                          2200    1787     1542     1375
1253
135                          2326    1890     1631     1454
1325
150                          2460    1998     1724     1538
1401


Experience = 4


60                           1539    1250     1079      962
876
75                           1627    1322     1140     1017
926
90                           1721    1398     1206     1076
980
105                          1819    1478     1275     1137
1036
120                          1924    1563     1348     1203
1095
135                          2034    1652     1426     1272
1158
150                          2151    1747     1508     1345
1225


Experience = 5


60                           1346    1093      943      841
766
75                           1423    1156      997      889
810
90                           1504    1222     1054      940
857
105                          1591    1292     1115      994
906
120                          1682    1366     1179     1052
958
135                          1779    1445     1247     1112
1013
150                          1881    1528     1318     1176
1071


VI. Conclusions

We use two models in order to estimate the reasonable cost per kw of capacity in the construction of nuclear projects as well as to identify the sources of these costs. The estimated models are statistically reliable and support theoretical expectations. For example, our results confirm that the cost per kw is less if the utility has already moved down the learning curve by building other nuclear plants during this era. Similarly, our results confirm the existence of economies of scale. As expected, the level of NRC regulation has contributed to the cost of nuclear projects.

Duration is critical. Higher costs per kw are associated with less efficient project management and with more complex, more costly designs. Our estimated costs depend heavily on the duration and level of experience assumed so that the policy simulation matrix adds to the case for regulatory reform - a need for pre-approved, standardized designs. Such designs would shorten construction durations and allow the industry to move more rapidly down the learning curve. Since economies of scale increase at a decreasing rate, the "reasonably optimal" size is not necessarily the largest possible; duration can be reduced and experience augmented by the selection of a standard "right-sized" project for regional requirements.

The authors thank an anonymous referee for several helpful suggestions that improved the final product.

1. Some analysts give the impression that NRC regulation is a new phenomenon born of the Three Mile Island accident For details on this station, see .

The Three Mile Island accident was the most significant in the history of the American commercial nuclear power generating industry. It resulted, however, in no deaths or injuries to plant workers or members of the nearby community.
. This is false; some regulations are as old as the industry. A realistic view of regulation should take into account the overall trend, not dwell on specific incidents.

2. This adjustment of the data does not change the reliability of the parameter estimates. The estimated coefficients and significance levels are similar with or without adjustments for disallowances. This adjustment simply reduces the total costs of construction of projects with disallowances.

3. These data are from the TVA TVA: see Tennessee Valley Authority.  Office of Nuclear Power [10].

4. Individual cost components are weighted to reflect the relative share of each in the construction of a typical nuclear facility.

Marshall and Navarro [4] contend that the use of "overnight costs" contradicts accepted capital theory and such a measure biases the estimate of scale economies upward because "overnight costs" do not include inflation. This argument derives from their misdefinition of "overnight costs": such costs do include inflation. As to accepted capital theory, since rates of return for public utilities in the U.S. are regulated, such regulation encourages utilities to "overbuild o·ver·build  
v. o·ver·built , o·ver·build·ing, o·ver·builds

v.tr.
1. To build over or on top of.

2. To construct more buildings in (an area) than necessary.

3.
" and not to minimize the cost of construction. Thus, accepted capital theory loses much of its relevance when applied to regulated public utilities. Moreover, commissions judging imprudence base the value of disallowances upon "overnight costs." The comparative estimates of what Marshall and Navarro call "true costs" are themselves seriously flawed since they separate first unit and subsequent unit costs, use a "trend" variable as the measure of regulation and fail to include "duration" as an independent variable.

5. Although widely used and accepted, the S pattern will not mirror the precise distribution of expenditures on any specific project; in some cases delays and other problems during the construction may make it a poor approximation approximation /ap·prox·i·ma·tion/ (ah-prok?si-ma´shun)
1. the act or process of bringing into proximity or apposition.

2. a numerical value of limited accuracy.
 indeed. Nevertheless, this drawback DRAWBACK, com. law. An allowance made by the government to merchants on the reexportation of certain imported goods liable to duties, which, in some cases, consists of the whole; in others, of a part of the duties which had been paid upon the importation.  must be weighed against the advantages of consistent treatment of all plants in the sample. In any event, the actual monthly patterns of expenditure are not comprehensively available. Hence, an approximation of this sort is not only useful but also necessary.

6. This adjustment does not fully account for the cost savings one would expect in an uncongested area rather than a congested con·gest·ed
adj.
Affected with or characterized by congestion.


congested ENT adjective Referring to a boggy blood-filled tissue. See Nasal congestion.
 urban area. Nevertheless, it does neutralize neutralize

to render neutral.
 many regional cost differences.

7. For consistency, the cost per kw figures for the comparison group excluded AFUDC AFUDC Allowance for Funds Used During Construction
AFUDC Accumulated Funds Used During Construction
, since governmental utilities typically do not accrue it (although they do incur financing costs) and there is variability in the AFUDC rates and accrual accrual,
n continually recurring short-term liabilities. Examples are accrued wages, taxes, and interest.
 policies applicable to investor-owned utilities.

8. Regulators subjectively evaluate this phenomena based upon an evidentiary ev·i·den·tia·ry  
adj. Law
1. Of evidence; evidential.

2. For the presentation or determination of evidence: an evidentiary hearing.

Adj. 1.
 record consisting primarily of thousands of pages of qualitative evidence concerning the history of each individual project. Data limitations force us to draw inferences about the cost of imprudent and inadequate management, rather than measure it directly for each plant in the sample.

9. The generalized least squares generated parameter estimates are not significantly different from those of OLS.

10. The additional cost per kw associated with an additional month of work is particularly important for projects with durations substantially longer than average. These also are the projects that have encountered the most problems. At the extreme, those projects that have encountered massive difficulties tend to have extremely long durations and tend to be the most costly of all, by a wide margin.

11. The complete effect of a particular explanatory variable in this specification is the sum of its regression coefficient Regression coefficient

Term yielded by regression analysis that indicates the sensitivity of the dependent variable to a particular independent variable. See: Parameter.


regression coefficient 
 and its post-1971 slope dummy coefficient.

References

1. Cantor, Robin A. and James G. Hewlett. "The Economies of Nuclear Power: Further Evidence on Learning Economies of Scale and Cost Estimation." Unpublished manuscript, Oak Ridge National Laboratory Oak Ridge National Laboratory (ORNL) is a multiprogram science and technology national laboratory managed for the United States Department of Energy by UT-Battelle, LLC. ORNL is located in Oak Ridge, Tennessee, near Knoxville. , 1987.

2. Energy Information Administration. An Analysis of Nuclear Power Plant Construction Costs. Washington, D.C.: DOE/EIA-0485, 1985.

3. Komanoff, Charles. Power Plant Cost Escalation es·ca·late  
v. es·ca·lat·ed, es·ca·lat·ing, es·ca·lates

v.tr.
To increase, enlarge, or intensify: escalated the hostilities in the Persian Gulf.

v.intr.
. New York New York, state, United States
New York, Middle Atlantic state of the United States. It is bordered by Vermont, Massachusetts, Connecticut, and the Atlantic Ocean (E), New Jersey and Pennsylvania (S), Lakes Erie and Ontario and the Canadian province of
: Van Nostrand Reinhold, 1981.

4. Marshall, John Marshall, John, 1755–1835, American jurist, 4th Chief Justice of the United States (1801–35), b. Virginia. Early Life


The eldest of 15 children, John Marshall was born in a log cabin on the Virginia frontier (today in Fauquier co., Va.
 M. and Peter Navarro Peter Navarro is Associate Professor of Public Policy at the Paul Merage School of Business, University of California, Irvine and holds a Ph.D. in Economics from Harvard University. , "Costs of Nuclear Power Plant Construction: Theory and New Evidence." RAND Journal of Economics, Spring 1991, 148-54.

5. Mooz, William E. Cost Analysts of Light Water Reactor

Main article: Nuclear power
"LWR" redirects here. See also: LWR (disambiguation)


A light water reactor or LWR
 Power Plants. Washington, D.C.: R-2304-DOE (Rand Corporation Rand Corporation, research institution in Santa Monica, Calif.; founded 1948 and supported by federal, state, and local governments, as well as by foundations and corporations. Its principal fields of research are national security and public welfare. ), 1978.

6. -----. A Second Cost Analysis of Light Water Reactor Power Plants. Santa Monica Santa Monica (săn`tə mŏn`ĭkə), city (1990 pop. 86,905), Los Angeles co., S Calif., on Santa Monica Bay; inc. 1886. Tourism and retailing are important, and the city has motion-picture, biotechnology, and software industries. , Calif.: R-2794-RC (Rand Corporation), 1979.

7. Navarro, Peter, "Comparative Energy Policy: The Economics of Nuclear Power in Japan and the United States United States, officially United States of America, republic (2005 est. pop. 295,734,000), 3,539,227 sq mi (9,166,598 sq km), North America. The United States is the world's third largest country in population and the fourth largest country in area. ." The Energy Journal, October 1988, 1-15.

8. Paik, Soon and William R. Shriver, "The Effect of Increased Regulation on Capital Costs and Manual Labor Requirements of Nuclear Power Plants." The Engineering Economist, Spring 1981, 223-44.

9. Radlauer, Marcy A., David S. Bauman, and Stephen W. Chapel, "Nuclear Construction Lead Times: Analysis of Past Trends and Outlook for the Future." The Energy Journal, January 1985, 45-62.

10. TVA Office of Nuclear Power. U.S. Nuclear Plants Cost Per KW Report. Washington: TVA, September 1987.

11. Yates, Marshall, "Nuclear Energy: A Failed Promise or a Promising Future?" Public Utilities Fortnightly fort·night·ly  
adj.
Happening or appearing once in or every two weeks.

adv.
Once in a fortnight.

n. pl. fort·night·lies
A publication issued once every two weeks.
, April 1, 1990, 12-13.

12. Zimmerman, Martin B., "Learning Effects and the Commercialization of New Energy Technologies." Bell Journal of Economics, Autumn 1982, 297-310.
COPYRIGHT 1996 Southern Economic Association
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1996, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Author:Reading, Don
Publication:Southern Economic Journal
Date:Jan 1, 1996
Words:5306
Previous Article:Testing theories of real government size: U.S. experience, 1959-89.
Next Article:Double marginalization and vertical integration: new lessons from extensions of the classic case.
Topics:



Related Articles
Recharging nuclear power.
False start at TMI. (Three Mile Island)
Nuclear and fossil fuel steam generation of electricity: differences and similarities.
Explaining regulatory commission behavior in the electric utility industry.
Models, Methods, and Applications of Econometrics: Essays in Honor of A.R. Bergstrom.
The impact of federal deposit insurance on savings and loan failures: a comment. (response to Richard J. Cebula, Southern Economic Journal, p. 620,...
Cost savings from nuclear regulatory reform: reply.
U.S. DEPARTMENT OF ENERGY SELECTS ETNUS DEBUGGER/ANALYZER FOR USE IN WORLD'S FASTEST SUPERCOMPUTER.(Product Information)
FIELD LAB CLEANUP WORRIES EXPERTS; SANTA SUSANA EFFORTS MAY NOT BE ENOUGH.(NEWS)
SAFETY DRILLS IN PROGRESS.(Higher Education)(An OSU lab tests scale models of reactor designs for future viability)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles