Real estate development is a risky and difficult enterprise. However, a small group of specialists is laboring at making the process a little more transparent and less perilous. These professionals are conceptual estimators. A conceptual estimate for a real estate development can make a tremendous difference in the efficiency, cost-effectiveness and desirability of the entire project.

An estimator with experience breadth of knowledge, and a thorough technique can steer steer

castrated male cattle beast over a year of age. See also bullock, buller steer.


steer bulling
see bulling.


steer Medtalk verb
 the developer clear of any potential disasters, and towards the best possible outcome. A first-rate conceptual estimate can make a difference not only in the quality of the finished product, but in the financing of it, since naturally the overall soundness of the project will affect the cost of capital.

Typically, the developer and the architect will come to me and my staff at the very beginning of the process--having already determined the zoning issues, the setback setback

In architecture, a steplike recession in the profile of a high-rise building. Usually dictated by building codes to allow sunlight to reach streets and lower floors, the building must take another step back from the street for every specified added height interval.
 requirements, and so on--and tell us, "We're thinking of buying this property, on which we want to build X number of stories, with a footprint of Y square feet." We then go over the proposed project, item by item, and determine how much the whole concept will cost. As we put the estimate together, naturally, we look for ways to make the project better, smarter, cheaper, whether by using a certain mechanical system, exterior wall construction, carpeting, or plumbing plumbing, piping systems inside buildings for water supply and sewage. The Romans had a highly developed plumbing system; water was brought to Rome by aqueducts and distributed to homes in lead pipes—hence the name plumbing from the Latin word plumbum  fixtures.

The conceptual estimate is part art and part science. At the start, it requires a lot of research, and a lot of consulting. We need to know not only the size and purpose of the proposed building, but how many cellars are required, what kind of exterior walls are contemplated, and so on. We need to determine what environmental issues must be dealt with, such as ground contamination. We need to know where the water table is, and ensure that the building can remain above it. We have to ride herd Verb 1. ride herd - driving animals such as horses and cattle while riding along with them; "Joe was riding herd during the day"
ride, sit - sit and travel on the back of animal, usually while controlling its motions; "She never sat a horse!"; "Did you ever ride a
 on the developer, the architect, and their associates, to ensure they've given us all the necessary information.

There's no template (1) A pre-designed document or data file formatted for common purposes such as a fax, invoice or business letter. If the document contains an automated process, such as a word processing macro or spreadsheet formula, then the programming is already written and embedded in the  for a conceptual estimate. At HRH HRH
abbr.
Her (or His) Royal Highness


HRH Her (or His) Royal Highness

HRH abbr (= His (or Her) Royal Highness) → S.A.R.
 Construction, we keep a master list of 88 different trades--everything from demolition Demolition is the opposite of construction: the tearing-down of buildings and other structures. It contrasts with deconstruction, which is the taking down of a building while carefully preserving valuable elements for re-use.  to asbestos abatement Noun 1. asbestos abatement - the removal of asbestos from a public building
abatement of a nuisance, nuisance abatement - (law) the removal or termination or destruction of something that has been found to be a nuisance
 to dampproofing to kitchen cabinets to lobby fixtures--each of which has to be factored into the overall estimate. Still, one new item or another always must be considered, in every project. Office buildings, apartments, hotels, factories: all have unique requirements, unique challenges.

HRH has been in business for more than 75 years. Our estimators average about 15 years of experience, and have seen all kinds of different conditions. The learning process is ongoing, of course, but the extent of their knowledge is phenomenal. They also communicate very well with our purchasing people, who can sometimes point out items that we need to add to our checklist, or update our information on item costs.

Quite often, our estimates will lead to improvements in the developer's plans. I might ask, for instance, "What kind of mechanical system will you use?" If it's a residential rental building, you might use an incremental Additional or increased growth, bulk, quantity, number, or value; enlarged.

Incremental cost is additional or increased cost of an item or service apart from its actual cost.
 system, which would cost about $6,000 per unit. For a mid-priced condo building you might use a heat pump heat pump: see air conditioning.
heat pump

Device for transferring heat from a substance or space at one temperature to another at a higher temperature.
 system, which could cost $7,500 per unit. For a more luxurious condo, you might use fan coils, which are the most expensive: $10,000 to $15,000 or even more. Which of those systems you choose will also affect the architectural exterior. Incremental systems require louvering on the exterior, while the other two systems require cooling towers. That leads to another big cost differential.

At Bank Street Commons, an apartment complex we're working on in White Plains, we determined that the HVAC (Heating Ventilation Air Conditioning) In the home or small office with a handful of computers, HVAC is more for human comfort than the machines. In large datacenters, a humidity-free room with a steady, cool temperature is essential for the trouble-free  should be changed from an incremental to the more expensive heat pump system. That actually resulted in a savings of about $200,000, because it enabled us to reduce the number of air-conditioning units required. Moreover, it gave a nicer look to the exterior of the building, because we didn't need to put grilles on the facade facade (fəsäd`), exterior face or wall of a building. The term implies ordered placement of its openings and other features and thus seems inapplicable to a wall without design. .

At City Center, another project in White Plains, we also found a considerable savings, this time by determining that prefabricated pre·fab·ri·cate  
tr.v. pre·fab·ri·cat·ed, pre·fab·ri·cat·ing, pre·fab·ri·cates
1. To manufacture (a building or section of a building, for example) in advance, especially in standard sections that can be easily shipped and
 panel would be just as good as, and much more cost-effective than, the original facade.

Sometimes, of course, a conceptual estimate will prove that for best results, the more expensive option is the better one. A few years ago, two buildings on East 86th Street that contained a Ronald McDonald House were sold to Frank Gifford Francis Newton Gifford (born August 16 1930 in Santa Monica, California) is a former American football player and one of the better-known American sports commentators in the latter part of the 20th century who made the transition from an athlete to broadcasting.  to be turned into Cassidy's Place, the therapeutic nursery named after his daughter. We discovered that the buildings had two different floor levels, which would make them difficult to connect satisfactorily. I jokingly said to Gifford, "Why don't we just tear it down and rebuild from scratch?" This he did, at a cost of $2 million more than the original projection, but it got him what he wanted: a more modern, more functional building.

The conceptual estimating business is both challenging and interesting. It stretches the mind remarkably, and exposes you to aspects of the real estate business that you might not know existed. I was lucky, when I started work for an estimating service about 40 years ago, to be exposed to all kinds of different jobs: everything from office and institutional buildings to airport control towers. Most of our associates have similarly broad experience. We're good at what we do, and we're constantly improving.
COPYRIGHT 2003 Hagedorn Publication
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2003, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:real estate development helped by services of conceptual estimator
Author:Muscianesi, James
Publication:Real Estate Weekly
Geographic Code:1USA
Date:Feb 26, 2003
Words:899
Previous Article:Sweeney: changing workstyles are creating new corporate interiors.
Next Article:Alliance vp gives ways to promote infrastructure improvements.(rebuilding Lower Manhattan in wake of World Trade Center destruction must focus on...
Topics:



Related Articles
New online cost-estimating service available to construction industry.
1.5M SF Cedarbridge Corporate Campus planned. (New Jersey).(business park planned for Lakewood, New Jersey)(Brief Article)(Statistical Data Included)
Derek W. Trulson. (Management Personnel).(Brief Article)
SwiftEstimator introduces new software application. (Technology: Update).(New online property estimating software product)(Brief Article)
SwiftEstimator now includes new estimating tool. (Technology Update).(Brief Article)
Building confidence key to successful construction business.
Get real: how can you arrive at an accurate construction estimate when you only have a vision? Simply follow these four steps to a credible...
What it's worth: correctly estimating a demolition project almost always separates success from failure.(Demo Estimating)