CanArgo Energy Corporation: N22H Well Re-Scheduled.


TBILISI, Georgia -- CanArgo Energy Corporation (AMEX AMEX

See: American Stock Exchange
:CNR See riser card.

CNR - Communication and Network Riser
) (OSE OSE - Open Systems Environment :CNR) ("CanArgo") today announced that it has re-scheduled the Ninotsminda Field N22H horizontal well, the first well in the planned Under Balanced Coiled Tubing Coiled tubing refers to metal piping, normally 1" to 2" in diameter, used for interventions in oil and gas wells, which comes spooled on a large drum. The main benefits over wireline are the ability to pump chemicals through the coil and the ability to push it into hole rather than  Drilling ("UBCTD") development program being carried out in conjunction with Weatherford International Weatherford International Ltd (NYSE: WFT) is one of the world's largest diversified upstream oilfield service companies. Weatherford provides services ranging from directional drilling, open and cased-hole wireline logging to underbalanced systems expertise, drilling, , due to a fault in the directional drilling Directional drilling (sometimes known as slant drilling outside the oil industry) is the science of drilling non-vertical wells. Directional drilling can be broken down into three main groups: Oilfield Directional Drilling, Utility Installation Directional Drilling (commonly  equipment.

This should not affect the overall timing of the UBCTD program as it is now planned to drill three wells consecutively commencing at the end of January with no break in activities. Previously the first well was to be drilled with an end of year break followed thereafter by two wells every four weeks with a break thereafter. Three consecutive wells would allow the program to get back on schedule.

CanArgo Energy Corporation and Weatherford International have successfully mobilized over 500 tons of UBCTD equipment to the Ninotsminda 22 well site in the Republic of Georgia. The rig up on the first well was completed despite the coldest weather experienced in Georgia since 1994 with temperatures at the well site falling to some -20 degrees C.

The cement shoe in the 4 1/2" liner was successfully drilled together with a short distance of new formation. At this point in time an error was detected in the down-hole telemetry telemetry

Highly automated communications process by which data are collected from instruments located at remote or inaccessible points and transmitted to receiving equipment for measurement, monitoring, display, and recording.
 equipment and despite intensive efforts it has proven impossible to fix without taking these items to the UK and Norway for repair. As this equipment is critical for steering the well trajectory and maintaining underbalanced conditions, it was mutually agreed to temporarily suspend drilling operations in order to fix the problem.

It is anticipated that drilling operations shall recommence Re`com`mence´   

v. i. 1. To commence or begin again.
2. To begin anew to be; to act again as.
He seems desirous enough of recommencing courtier.
- Johnson.

v. t. 1. To commence again or anew.
 about January 26, 2005. It is planned to then drill Ninotsminda horizontal UBCTD wells 22, 100 and 49 without a break to bring the program back on schedule.

On the appraisal of the Manavi oil discovery, drilling operations are progressing satisfactorily on the on the M11Z sidetrack well which is currently at a depth of approximately 3,393 meters (11,132 feet).

Dr David Robson, CanArgo's CEO (1) (Chief Executive Officer) The highest individual in command of an organization. Typically the president of the company, the CEO reports to the Chairman of the Board.  commented, "Whilst this is frustrating for our team in Georgia it is only a short-term problem and we are working with Weatherford to bring the program back on track by early next year. This should not affect our program as a whole, however the initial results will now be realised in early February 2005 instead of January 2005".

CanArgo is an independent oil and gas exploration and production company with its oil and gas operations currently located in the Republic of Georgia and the Caspian area.

The matters discussed in this press release include forward-looking statements, which are subject to various risks, uncertainties and other factors that could cause actual results to differ materially from the results anticipated in such forward-looking statements. Such risks, uncertainties and other factors include the uncertainties inherent in oil and gas development and production activities, the effect of actions by third parties including government officials, fluctuations in world oil prices and other risks detailed in the Company's reports on Forms 10-K and 10-Q filed with the Securities and Exchange Commission. The forward-looking statements are intended to help shareholders and others assess the Company's business prospects and should be considered together with all information available. They are made in reliance upon the safe harbor Safe Harbor

1. A legal provision to reduce or eliminate liability as long as good faith is demonstrated.

2. A form of shark repellent implemented by a target company acquiring a business that is so poorly regulated that the target itself is less attractive.
 provisions of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. The Company cannot give assurance that the results will be attained.
COPYRIGHT 2004 Business Wire
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2004, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Publication:Business Wire
Geographic Code:4EUUK
Date:Dec 20, 2004
Words:581
Previous Article:CompuBug By Larry Blasko For Business Wire.
Next Article:CompuDyne Acquires Copperfire Software Solutions; Automated Report Writing Software Designed For First Responders.
Topics:



Related Articles
CanArgo Energy Corporation: Q2 Results 2003.
CanArgo Announces Q3 Results.
CanArgo Energy Corporation: Georgian Operations Continue Unaffected.
CanArgo Energy Corporation: Third Successful Horizontal Well On Ninotsminda.
CanArgo Announces Preliminary 2003 Year End Results.
CanArgo Energy Corporation: UBCTD Program Commences.
CanArgo Energy Corporation: Update on Georgian Activities.
CanArgo Signs $15 Million Loan Note.
CanArgo Energy Corporation: AGM Update.
CanArgo Energy Corporation: $25 Million Convertible Financing Closed.

Terms of use | Copyright © 2012 Farlex, Inc. | Feedback | For webmasters | Submit articles