CONSTRUCTION CONTRACT DELAYED BIDS FOR WILSONA REFURBISHMENT NEARLY $400,000 OVER PROJECTIONS.


Byline: KAREN MAESHIRO Staff Writer

LAKE LOS ANGELES Los Angeles (lôs ăn`jələs, lŏs, ăn`jəlēz'), city (1990 pop. 3,485,398), seat of Los Angeles co., S Calif.; inc. 1850.  -- Wilsona School District trustees have postponed awarding a bid for the replacement of 16 relocatable classrooms at Wilsona Elementary School elementary school: see school.  after bids came in over budget.

The district has been approved to receive state hardship funding to refurbish re·fur·bish  
tr.v. re·fur·bished, re·fur·bish·ing, re·fur·bish·es
To make clean, bright, or fresh again; renovate.



re·fur
 the school, but bids for the prep work and new modular buildings Modular buildings are sectional prefabricated buildings that are manufactured in a plant, and delivered to the customer in one or more complete modular sections. Modular buildings are considerably different from mobile homes.  are nearly $400,000 over the projected cost.

``Right now the bids are too high,'' Superintendent Ned McNabb said. ``We are not sure what we are going to do. We will be meeting with the architect to make a decision on how to proceed.''

Trustees delayed awarding a bid at last week's meeting. McNabb said he will present options at the next board meeting June 9.

A contract must be awarded by late July or the district has to give the money back to the state, McNabb said.

The high bids are being pegged peg  
n.
1.
a. A small cylindrical or tapered pin, as of wood, used to fasten things or plug a hole.

b. A similar pin forming a projection that may be used as a support or boundary marker.

2.
 to dramatic increases in construction costs.

The district has available $2.25 million in hardship funding from the state to replace the 16 classrooms. The district spent about $540,000 on architect and inspector fees, leaving $1.71 million for construction.

The bid for the modular buildings came in at $1.25 million and the lowest of three bids for the work to prepare the site was $839,250, McNabb said.

``I don't think we can get the costs any lower,'' McNabb said. ``We might keep the ones we have and do a rehab instead.''

Soaring construction costs also have plagued two other of Wilsona's projects -- the construction of Saddleback Saddleback

see Wessex saddleback.
 Elementary School and expansion of Challenger Middle School -- forcing the district to re-examine re·ex·am·ine also re-ex·am·ine  
tr.v. re·ex·am·ined, re·ex·am·in·ing, re·ex·am·ines
1. To examine again or anew; review.

2. Law To question (a witness) again after cross-examination.
 building plans to see where costs can be cut.

Wilsona has also been approved to receive nearly $19 million in state hardship funding to build Saddleback Elementary School at a cost of $11.84 million and to add 11 classrooms at Challenger Middle School for $4.54 million.

Design changes include installing three modular buildings instead of permanent ones -- two at the Saddleback campus and one at Challenger -- that would save about $600,000, officials said.

Wilsona also plans to reduce asphalt asphalt (ăs`fôlt, –fălt), brownish-black substance used commonly in road making, roofing, and waterproofing. Chemically, it is a natural mixture of hydrocarbons.  paving and concrete work and simplify landscaping at Saddleback and Challenger.

Saddleback will be the district's third elementary school. The kindergarten-through-fifth-grade campus will be at 150th Street East and Avenue N-12 and will be designed to hold 750 students.

karen.maeshiro(at)dailynews.com

(661) 267-5744
COPYRIGHT 2006 Daily News
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2006, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Publication:Daily News (Los Angeles, CA)
Date:May 31, 2006
Words:403
Previous Article:LITTLE BOWL ON THE PRAIRIE GARRISON KEILLOR BRINGS HIS SMALL-TOWN PHENOMENON TO L.A.
Next Article:GOVERNOR SIGNS BILL ON ROOF INDUSTRY.



Related Articles
OFFICIALS TO SELECT CONTRACTOR.
SIMI MAY SCRAP BIDS FOR NEW POLICE STATION.
SIMI MAY SCRAP BIDS FOR NEW POLICE STATION.
STATE FUNDS MAY PAY FOR NEW SCHOOL WSD SEEKS FINANCIAL HARDSHIP STATUS.
LONG WAIT TO END FOR NEW SCHOOL $9.5 MILLION STATE GRANT OK'D FOR SADDLEBACK ELEMENTARY.
WILSONA WILL GET NEARLY $19 MILLION FUNDS WILL BUILD SCHOOL, FIX OTHERS.
WILSONA TRIMS PROJECTS TO STAY WITHIN BUILDING BUDGET.
EASIER SCHOOL CONSTRUCTION? ASSEMBLYWOMAN'S LEGISLATION TARGETS `BUREAUCRACY AND INEFFICIENCY'.
WILSONA SET TO REFURBISH CLASSROOMS.
SADDLEBACK ELEMENTARY GROUNDBREAKING CAMPUS EXPECTED TO OPEN NEXT FALL.

Terms of use | Copyright © 2012 Farlex, Inc. | Feedback | For webmasters | Submit articles