Bridge's Delay to Bring Gridlock at Intersection.


The $2.4 billion Alameda Corridor The Alameda Corridor is a 20 mile (32 km) freight rail "expressway"[1] owned by the Alameda Corridor Transportation Authority (AAR reporting marks ATAX  has long been touted as the solution to massive traffic congestion The condition of a network when there is not enough bandwidth to support the current traffic load.

congestion - When the offered load of a data communication path exceeds the capacity.
 caused by trains crossing over south Los Angeles South Los Angeles is the official name for a large geographic and cultural area lying to the southwest and southeast of downtown Los Angeles, California. The area was formerly called South Central Los Angeles, and is still sometimes called South Central.  County roads to and from the ports.

Tell that to the 31,000 drivers who travel each day along Pacific Coast Highway Pacific Coast Highway may refer to:
  • Pacific Coast Highway (United States), a segment of State Route 1 in California
  • Pacific Coast Highway (New Zealand), a 420 kilometre highway http://www.newzealand.
 in Wilmington.

After more than a decade of delays by Caltrans in building a bridge over two railways that intersect the highway and Alameda Street, the Alameda Corridor Transportation Authority has wrested control of the project. But the action comes too late to beat the corridor's April 2002 opening -- and massive traffic jams could result as the bridge is built amid increased train traffic.

"Some people think (congestion) is already intolerable," said Jim Hankla, chief executive of the Alameda Corridor Transportation Authority (ACTA). "Train traffic is going to be increasing substantially -- longer trains and more of them. It's implicit that some of the delays are going to involve emergency vehicles. In the minds of some motorists waiting for the trains to go by, it will become a commuting disaster."

Delays so far will push the bridge's cost from $74 million to $107 million. Construction will be done 18 months after the Alameda Corridor opening.

The 20-mile rail expressway corridor will allow trains to move twice as fast from the Ports of Los Angeles Los Angeles (lôs ăn`jələs, lŏs, ăn`jəlēz'), city (1990 pop. 3,485,398), seat of Los Angeles co., S Calif.; inc. 1850.  and Long Beach to the rail yards east of downtown L.A. As a result, daily traffic is expected to increase from the current 25 trains -- most with dozens of cargo cars linked to the locomotives -- to as many as 40 trains. By 2020, 100 trains will use the rail daily.

To eliminate traffic congestion, 29 bridges are being constructed over the railway while 200 at-grade crossings are being eliminated.

Planned since 1993

Caltrans initially took on the PCH PCH Paroxysmal cold hemoglobinuria, see there  grade separation project -- its only contribution to the corridor -- because PCH is a state highway. It hired the Los Angeles Department of Public Works public works
pl.n.
Construction projects, such as highways or dams, financed by public funds and constructed by a government for the benefit or use of the general public.

Noun 1.
 in 1993 to design a mile-long bridge using a portion of the $74 million appropriated by the state in 1987.

But Caltrans placed those plans on the back burner Noun 1. back burner - reduced priority; "dozens of cases were put on the back burner"
precedence, precedency, priority - status established in order of importance or urgency; "...
, despite years of pleas from Alameda Corridor officials and state legislators, Hankla said. No intersection along the corridor has a greater volume of train and vehicle traffic.

By the time full designs began about three years ago, inflation had taken its toll. Caltrans ordered the DPW DPW n abbr (US) (= Department of Public Works) → ministerio de obras públicas  to begin designing a bridge to fit the original $74 million budget -- cutting the length of the mile-long grade separation in half.

Caltrans' bridge would have crossed over the rail expressway, formerly Burlington Northern Santa Fe's line, as well as the adjacent Alameda Street. But the San Pedro branch of the Union Pacific Railroad Union Pacific Railroad, transportation company chartered (1862) by Congress to build part of the nation's first transcontinental railroad line. Under terms of the Pacific Railroads Act, the Union Pacific was authorized to build a line westward from Omaha, Nebr.  to the west would have remained uncovered, bringing traffic to a halt every time light-rail trains coming to and from San Pedro crossed PCH.

"We based our decisions on the data we were given," said Karen Fong, design office chief with Caltrans. "At the time, we were told we only needed one (short) bridge."

Caltrans rebuffed claims that it placed the bridge low on its priority list, attributing the delays to difficult right-of-way negotiations with Equilon Enterprises, which operates nearby oil refineries This is a list of oil refineries. The Oil and Gas Journal also publishes a worldwide list of refineries annually in a country-by-country tabulation that includes for each refinery: location, crude oil daily processing capacity, and the size of each process unit in the refinery. . Tearing up the existing road will require the temporarily moving of some of the refinery's underground pipes, officials said.

"Don't underscore the level of complexity that this adds," said Doug Failing, chief deputy of Caltrans district 7, which covers the L.A. area.

"It's an exceedingly sensitive operation and one that has to be approached with all caution. That oil refinery must remain in operation (during construction.)"

ACTA began pressuring the state in 1998 to assume control of the project. But it was not until early 2001, when the agency learned of the plans for the short bridge, that ACTA stepped up its pressure to take over management of the grade separation. Caltrans agreed to relinquish control in July.

Almost immediately, HDR (1) (High Data Rate) A wireless data technology from QUALCOMM that provides up to a 2.4 Mbps data rate in a standard 1.25MHz CDMA voice channel. HDR can be used to enhance data capabilities in existing cdmaOne networks or in stand-alone data networks.  Inc. of Orange was hired to design the mile-long bridge. With ACTA now managing the project, negotiations have restarted with Equilon -- a process expected to take 12 to 14 months. ACTA, meanwhile, has budgeted $37.5 million from the $107 million for utility relocations, soil clean up and other expenses.

"The frustrating part was getting the recognition at the state level that this was a serious problem," said Hankla." (Caltrans) basically felt the short bridge was an adequate solution. I don't think they had a keen understanding of the number of trains that would be traversing at Alameda Corridor and PCH."

Once bridge construction commences, the gridlock Gridlock

A government, business or institution's inability to function at a normal level due either to complex or conflicting procedures within the administrative framework or to impending change in the business.
 will shift from PCH to whichever detour routes are approved by Caltrans.

"There is going to be a lot of traffic in that area," Failing acknowledged. "(Motorists) will have to decide whether it's a necessary trip or a trip of convenience. Then they will have to make a choice: can they make the trip at a different time or can they use a different route away from the congestion. Once the new (bridge) is open, they'll be very forgiving."
COPYRIGHT 2001 CBJ, L.P.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2001, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:Government Activity; Los Angeles County 20-mile rail expressway corridor
Comment:Bridge's Delay to Bring Gridlock at Intersection.(Los Angeles County 20-mile rail expressway corridor)(Government Activity)
Author:GREENBERG, DAVID
Publication:Los Angeles Business Journal
Article Type:Brief Article
Geographic Code:1USA
Date:Oct 1, 2001
Words:842
Previous Article:Letters.(Building designs)(Brief Article)(Letter to the Editor)
Next Article:Suit Targets Cities Over Cameras at Stop Lights.(San Diego's red light camera system)(Legal Beat)(Brief Article)
Topics:



Related Articles
Alameda corridor heads toward grand opening: Project remains on schedule, on budget. (Alameda corridor).(Brief Article)
GREEN LIGHT FOR MORE GRIDLOCK? IMPACT OF ALAMEDA CORRIDOR OPENING, PORT BOOM TO SPREAD FAR AND WIDE.(Business)(Statistical Data Included)
ALAMEDA CORRIDOR MILESTONE CARGO LINE TO OPEN, LINKING PORTS TO RAIL YARDS.(News)
Hurry up and wait for massive public projects.(Southern California's roads infrastructure)(Government Activity)
How the Corridor came together: a timeline.(Alameda Corridor)(Illustration)(Statistical Data Included)
SUBWAY EXTENSION IS WASTEFUL, MISGUIDED COUNTY WOULD BE BETTER SERVED WITH COST-EFFECTIVE TRANSIT SYSTEM.(Editorial)(Editorial)
Scramble is on to save transportation projects.(budget deficits may delay projects)
Last link of Alameda Corridor to disrupt traffic flow on PCH. (Up Front).(Pacific Coast Highway)
Border proposals.(Economic Development)(road construction)
Will governor's plan deliver the goods? Industry fears red tape, lack of funding will derail projects.(SHIPPING)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles