Most cost accounting systems are designed to handle contracts performed to completion, but with widespread military cutbacks, federal contracts are being terminated prematurely, creating complex technical problems for CPAS CPAS Corrective and Preventative Action System
CPAS Centre for the Public Awareness of Science (Australia)
CPAS National Centre for the Public Awareness of Science (Australian National University, Canberra) 
.

Companies generally are entitled to recoup their full costs when a federal agency terminates a job in midcontract for its own convenience the usual parlance Parlance - A concurrent language.

["Parallel Processing Structures: Languages, Schedules, and Performance Results", P.F. Reynolds, PhD Thesis, UT Austin 1979].
 for contracts terminated for reasons other than cause. But working out how much money the government subsequently owes the business can be difficult.

DIRECT VS. INDIRECT COSTS Indirect costs are costs that are not directly accountable to a particular function or product; these are fixed costs. Indirect costs include taxes, administration, personnel and security costs. See also
  • Operating cost
 

A major hurdle is establishing which business costs are direct and which indirect. Direct costs are charged directly to the contract; indirect costs go into cost pools, such as general and administrative, and are allocated to the contract only via some kind of rate mechanism. Differentiating between the two can be a problem when contracts are terminated because established allocation procedures often are not appropriate in these cases.

To illustrate the problems, consider this typical case:

A contractor enters into a five year, fixed-price development contract with the military. The job calls for a significant investment in test equipment, to be used exclusively in the project. However, equipment cost is not treated as direct in the original contract for these reasons.

n The equipment does not meet the special-test-equipment definition in the Federal Acquisition Regulations The Federal Acquisition Regulation (usually referred to as the FAR or F.A.R.), are a series of regulations issued by the Federal government of the United States that concern the requirements of contractors for selling to the government, the terms under which the  FAR), which regulate federal contracting. Specifically, FAR 45. 101 defines special test equipment as "single or multipurpose mul·ti·pur·pose  
adj.
Designed or used for several purposes: a multipurpose room; multipurpose software.


multipurpose
Adjective
 integrated test units engineered, designed, fabricated fab·ri·cate  
tr.v. fab·ri·cat·ed, fab·ri·cat·ing, fab·ri·cates
1. To make; create.

2. To construct by combining or assembling diverse, typically standardized parts:
 or modified to accomplish special purpose testing in performing a contract. "

The practice is to charge special test equipment as a direct cost and general test equipment as indirect.

* Cost Accounting Standard 409 to which the company is subject, requires consistent charging; for example, depreciation costs of all like assets used for similar purposes must be treated consistently, either as direct or indirect costs.

* Depreciation of the test equipment will be included in engineering overhead in current and future years.

If the contract is terminated after the test equipment is acquired but before most of the direct costs for contemplated engineering efforts are incurred, only a minor amount of equipment depreciation can be charged to the contract using the usual engineering overhead-allocation methods.

DOUBLE COUNTING Double counting may refer to:
  • Double counting (proof technique), a proof technique in combinatorics whereby one set is counted in two different ways
  • Double counting (fallacy), a fallacy in combinatorics and probability theory whereby objects are counted more than once
 

One possible recourse for the contractor is to be more flexible in assigning costs. But a contractor that departs from its usual, accepted accounting practices runs the risk of reasonable modifications necessary to outfit an existing facility for contract performance.

* In an appeal filed by Fiesta Leasing & Sales, Inc., (AFBCA AFBCA Air Force Base Conversion Agency  no. 29311, January 30, 1987, 87-1 BCA BCA Business Case Analysis
BCA Building Code of Australia
BCA Boeing Commercial Airplanes
BCA Board of Contract Appeals
BCA Boston Center for the Arts
BCA Billiard Congress of America
BCA Bureau of Criminal Apprehension
BCA Breast Cancer Action
 19622), the board allowed depreciation on buses purchased for a busleasing contract terminated shortly after the contract was awarded. The board allowed depreciation over the full 18-month contract period, saying, "Such depreciation costs are appropriately recoverable as continuing costs .... There is ... a clear connection between the costs claimed and the terminated contract and it is clear to us that these costs could not be discontinued immediately upon termination. "

ot all the cases involve military contracts. In an appeal brought by Essex Electro Engineers, Inc. (DOT CAB no. 1025, 1119, December 11, 1980, 81-1 BCA 14838), the Department of Transportation Contract Appeals Board allowed recovery of the full cost of the net book value of equipment remaining at a plant when the contract was terminated for convenience. The contractor could not retain the equipment without sustaining a loss because the equipment was in excess of current and future operational requirements (programming) operational requirements - Qualitative and quantitative parameters that specify the desired capabilities of a system and serve as a basis for determining the operational effectiveness and suitability of a system prior to deployment. .

NO WINDFALLS

CPAS should recognize that the total termination settlement is limited to the contract price of the items terminated, plus settlement expenses. In other words Adv. 1. in other words - otherwise stated; "in other words, we are broke"
put differently
, the government guards against a company gaining a windfall from a scrapped contract. FAR 49.203 provides that, if a contractor would have suffered a loss on a fixed price contract if completed, the anticipated loss rate must be reflected in the termination settlement.

The loss adjustment is calculated by comparing the total contract price with the estimated cost at completion (that is, total cost incurred before the termination, plus the estimated costs to complete the contract if the termination had not occurred): The allowable termination settlement cost then is computed by multiplying the loss adjustment factor by the allowable costs incurred by the contractor excluding settlement costs:

Proposed settlement Loss adjustment factor x Allowable costs

SETTLEMENT EXPENSES

Accountants should be aware that FAR 31.205-42(g) also allows recovery of the following:

* Accounting, legal, clerical and similar costs incurred in preparing and negotiating settlement proposals and in terminating and settling subcontracts.

* Costs for storage, transportation, protection and disposition of property acquired for the contract.

In fact, when a contractor's personnel are involved in these contract termination Defense procurement: the cessation or cancellation, in whole or in part, of work under a prime contract or a subcontract thereunder for the convenience of, or at the option of, the government, or due to failure of the contractor to perform in accordance with the terms of the contract (default).  activities, the company can add applicable indirect costs such as the expenses for employees' payroll taxes Payroll Tax

Tax an employer withholds and/or pays on behalf of their employees based on the wage or salary of the employee. In most countries, including the U.S., both state and federal authorities collect some form of payroll tax.
, fringe benefits fringe benefits,
n.pl the benefits, other than wages or salary, provided by an employer for employees (e.g., health insurance, vacation time, disability income).
, occupancy costs and immediate supervision.

Clearly, significant settlement expenses must be separately identified for both the associated in-house costs and outside legal and accounting fees. Such costs must be excluded from indirect cost pools that are allocated to other contracts.

In the Baifield Industries case, the ASBCA ASBCA Armed Services Board of Contract Appeals
ASBCA Arkansas State Board of Collection Agencies
 ruled such costs can be included in the settlement when

* The charges are supported adequately and the time and rates charged are reasonable considering the termination claim complexity and the nature of the work that was performed.

* The contractor has limited experience in termination claims and the outside legal and accounting advisers have the necessary expertise.

Naturally, those involved in supporting a termination settlement proposal (both in-house and outside resources) should keep a contemporaneous con·tem·po·ra·ne·ous  
adj.
Originating, existing, or happening during the same period of time: the contemporaneous reigns of two monarchs. See Synonyms at contemporary.
 record of their activity.

Contract terminations are never good news. However, the adverse effects can be mitigated by thoroughly analyzing the costs associated with contract performance and pursuing the equitable recovery of costs. N
COPYRIGHT 1992 American Institute of CPA's
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1992, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Author:Worthington, Margaret M.
Publication:Journal of Accountancy
Date:Mar 1, 1992
Words:946
Previous Article:The part-time technical reviewer.
Next Article:GRITs, GRANTs and GRUNTs. (estate planning)
Topics:



Related Articles
Black defense firms battle for more contracts. (Special Report)
Society's re-engineered future. (CEOs argue for new social contract between employer and employee)(Business and Society)
Industry at the crossroads: Canada's top arms contractors.
Get In The Game.(public procurement opportunities)
Challenges to Military Financial Management in the Future.(Brief Article)
LACK OF ENGINEERS LOOMS FOR AIR BASE.(Business)
EMBATTLED CRA CHIEF QUITS JOB.(News)
Public and private partnerships in support of Performance-Based Logistics initiatives--lessons learned from Defense Logistic Agency...
Minority-owned firm gets its start with help to win federal contracts.(government contracting)
The great contracting scandal.(government contracts )

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles