Printer Friendly
The Free Library
19,604,540 articles and books
Member login
User name  
Password 
 
Join us Forgot password?

Are acceleration costs recoverable?


Are acceleration costs recoverable?

A typical scenario where the contractor is compelled to accelerate his work can be described by the following fact pattern:

Owner and contractor are parties to a contract which requires project completion by June 1990. During construction the contractor is delayed several times due to changes by the owner. Contractor requests an extension of time from the owner which the owner rejects. As the June 1990 date approaches, the owner, by letter to the contractor, impresses upon the contractor that the June 1990 completion date must be met. Consequently, the contractor is required to perform the work in a shorter time period than the time extension to which he is entitled en·ti·tle  
tr.v. en·ti·tled, en·ti·tling, en·ti·tles
1. To give a name or title to.

2. To furnish with a right or claim to something:
.

It is reasonable to expect that the contractor in the above example will incur additional costs and expenses due to acceleration, i.e., the cost of employing additional workers and working overtime and weekends to meet the original contract completion date. From a legal standpoint The Standpoint is a newspaper published in the British Virgin Islands. It was originally published under the name Pennysaver, largely as a shopping-coupon promotional newspaper, but since emerged as one of the most influential sources of journalism in the , those costs associated with acceleration are generally recoverable by a contractor from an owner upon a showing by the contractor that: (1) any delays giving rise to the order to accelerate are excusable, (2) the contractor was ordered to accelerate, either by direct order or constructively by refusal to grant a time extension and (3) the contractor in fact accelerated performance and incurred extra costs. What constitutes an excusable delay is typically spelled out in the contract?

These elements, however, are not always exclusive and some jurisdictions require an additional showing in order to recover acceleration damages.

A prerequisite pre·req·ui·site  
adj.
Required or necessary as a prior condition: Competence is prerequisite to promotion.

n.
 to the recovery of acceleration damages is a finding by the court that the owner, or in some instances, the general contractor A general contractor is an organization or individual that contracts with another organization or individual (the owner) for the construction of a building, road or any other execution of work or facility.  or construction manager, order directly or indirectly the contractor or subcontractor One who takes a portion of a contract from the principal contractor or from another subcontractor.

When an individual or a company is involved in a large-scale project, a contractor is often hired to see that the work is done.
 to accelerate. What constitutes an order to accelerate may raise numerous factual issues. The broad spectrum of factual issues giving rise to acceleration is depicted de·pict  
tr.v. de·pict·ed, de·pict·ing, de·picts
1. To represent in a picture or sculpture.

2. To represent in words; describe. See Synonyms at represent.
 in Norair, where the court stated as follows:

An order to accelerate to be effective need not be couched couch  
n.
1.
a. A sofa.

b. A sofa on which a patient lies while undergoing psychoanalysis or psychiatric treatment.

2.
a.
 in terms of a specific command. A request to accelerate, or even an expression of concern about lagging Lagging

Strategy used by a firm to stall payments, normally in response to exchange rate projections.
 progress, may have the same effect as an order.

What constitutes an order to accelerate usually depends upon the facts and circumstances CIRCUMSTANCES, evidence. The particulars which accompany a fact.
     2. The facts proved are either possible or impossible, ordinary and probable, or extraordinary and improbable, recent or ancient; they may have happened near us, or afar off; they are public or
 of each case.

Costs recoverable due to acceleration are normally those costs associated with the increase in the cost of performance resulting from a compressed progress schedule. Liability for acceleration costs can be imposed upon an owner, a general contractor or, in fact, any party compelling another party to speed up his work progress. For example, recently in Mobil Chemical Co. vs. Bloumt Bros BROS Brothers
BROS Benefits and Retirement Operations Section (King County, Washington)
BROS Barnes and Richmond Operatic Society (London, UK) 
. Corp., 809 F.2d 1175 (1987), the court held that both a general contractor and owner were equally liable for acceleration damages sustained by the subcontractors on the project.

Mobil involved the construction of a chemical plant owner by the plaintiff. The contract between the general contractor and the owner required completion by January 1983. Although work on the project began in 1981, the early phases of the project were significantly delayed because of poor management, coordination and control of the project by the owner and the general contractor. Consequently, the court found that the work of the subcontractors went "uncoordinated un·co·or·di·nat·ed  
adj.
1. Lacking physical or mental coordination.

2. Lacking planning, method, or organization.



un
 and construction proceeded chaotically and behind schedule."

In the fall of 1982, the owner and general contractor engaged in a joint effort to push the subcontractors to meet the January 1983 completion date by overmanning o·ver·man  
n.
1. A person having authority over others, especially an overseer or a shift supervisor.

2. See superman.

tr.v.
 and acceleration. The court learned that the owner knew it could not be finished on time and told the general contractor that later completion was acceptable. However, the owner and the general contractor conveyed to the subcontractors that completion by January was crucial. In fact, it was brought out at the trial that the owner even "threatened to black-ball several subcontractors if they did not add workers and make up time."

The project was completed in April 1983. Thereafter, the general contractor, subcontractors and the owner all sued each other for various breaches of contract. Particularly, the subcontractors asserted claims against the owner and the general contractor for the costs of acceleration.

It was easily established in Mobil that the subcontractors' work was accelerated. However, an important issue in the case was whether the general contractor was liable for its subcontractors' acceleration costs. Likening lik·en  
tr.v. lik·ened, lik·en·ing, lik·ens
To see, mention, or show as similar; compare.



[Middle English liknen, from like, similar; see like2
 the relationship between the general contractor and the owner to a conspiracy to accelerate, the court was not reluctant to impose liability upon the general contractor for its subcontractors' acceleration costs. In fact, the court divided the liability equally between the owner and the general contractor after finding that they were both at fault for the subcontractors' losses.

Another issue addressed in Mobil was whether the general contractor was entitled to its 5 percent mark-up on the cost of acceleration expenses incurred by its subcontractors. Pursuant to its contract with the owner, the general contractor was entitled to this mark-up for additional work. The court, however, found that the general contractor's participation in the acceleration decision negated its right to recover a mark-up on damages owed to the subcontractors by the owner. The court's reasoning was as follows:

The general contractor should be allowed a markup (text) markup - In computerised document preparation, a method of adding information to the text indicating the logical components of a document, or instructions for layout of the text on the page or other information which can be interpreted by some automatic system.  on subcontractors' acceleration damages only if it tries and fails to prevent the damages. ... A general contractor should stand with the subcontractors and request time extensions and extra payments in the face of acceleration pressures by the owner -- in other words Adv. 1. in other words - otherwise stated; "in other words, we are broke"
put differently
, it should demand an orderly and negotiated resolution of problems.

The Mobil case offers a good example of what may constitute acceleration, and it also sends out a warning to general contractors faced with acceleration pressures from the owner.

Before taking sides with the owner and compelling its subcontractors to accelerate, the general contractor should realize that by doing so it may be imposing acceleration liability upon itself that perhaps can be avoided by negotiating the appropriate extensions of time.

Peter Goetz, Esq., is a senior member of the New York- and New Jersey-based law firm of Goetz, Fitzpatrick & Flynn which concentrates its practice in construction and real estate law and related fields. The firm litigates and arbitrates construction and real estate matters throughout the United States United States, officially United States of America, republic (2005 est. pop. 295,734,000), 3,539,227 sq mi (9,166,598 sq km), North America. The United States is the world's third largest country in population and the fourth largest country in area.  and abroad. Goetz is both an attorney and a graduate civil engineer.
COPYRIGHT 1991 Hagedorn Publication
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 1991, Gale Group. All rights reserved. Gale Group is a Thomson Corporation Company.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:Construction Corner
Author:Goetz, Peter
Publication:Real Estate Weekly
Date:Oct 9, 1991
Words:1046
Previous Article:Rebound seen for domestic markets by mid-'92.
Next Article:Firm to buy office tower from RTC in Princeton.
Topics:



Related Articles
Contracting climbs 6% in Feb. for new projects.
Oil and gas royalty reporting.
NPA publications offer technical know-how & more.
UZBEKISTAN - E&P Offers.
IRWINDALE SPEEDWAY: GROUND BROKEN FOR STRIP ADDITION WILL FEATURE NHRA DRAG RACES.
UPSCALE RETAIL CENTER SLOW TO BLOSSOM\Merchants, Glendale hope to spur sales with expansion plan.
UZBEKISTAN - The E&P Offers.
Concrete Alliance's Alfred Gerosa joins MTA's construction panel.

Terms of use | Copyright © 2012 Farlex, Inc. | Feedback | For webmasters | Submit articles